| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00998983 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 02/07/2024 | 08/27/2026 | Contractor URBAN INTELLIGENCE, INC | INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2022 CHAPTER 33 . NO CHANGE IN… |
| M01247847 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 08/18/2025 | 08/26/2026 | Contractor H M SPRINKLER INC | SPRINKLER AND STANDPIPE WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 20-22. |
| M01108092 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration CO | Permit Issued | 09/17/2024 | 06/10/2026 | Design PBDW ARCHITECTS Contractor CNY BUILDING CORP | ST WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 21-24 AND TO THE 24TH FLOOR SOLARIUM STOREFRONT & ROOF. |
| M01322173 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 12/04/2025 | 06/01/2026 | Contractor EXTERIOR WALL & BUILDING | INSTALLATION OF OVERHEAD PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY … |
| M01166654 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 01/15/2025 | 01/15/2026 | Contractor EXO INDUSTRIES CORP | FACADE INSPECTIONS AND PROBES |
| M00858685 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 06/28/2023 | 01/02/2026 | Design RHL ENGINEERING, LLC Contractor DEEM PLUMBING INC Filer NEW YORK ATHLETIC CLUB | REPLACEMENT OF BUILDING'S EXISTING 4 GAS RISER WITH NEW AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| Name | Projects together | Most recent |
|---|---|---|
| Patti & Anthes Consulting Engineers | 12 | 08/14/2026 |
| PBDW Architects | 6 | 08/14/2026 |
| Custodio Consulting | 3 | 11/10/2023 |
| RHL Engineering | 3 | 10/22/2025 |
| FL&M Engineering Design & Inspection | 2 | 04/08/2026 |
| JMV Consulting Engineering | 2 | 02/16/2023 |
| Lombardo Professional Engineering | 2 | 10/01/2026 |
| Severud Associates | 2 | 08/14/2026 |
| Ashraf | 1 | 09/29/2025 |
| Cribstone Engineering | 1 | 04/01/2025 |
| Edwards and Zuck | 1 | 03/13/2024 |
| Green Design | 1 | 09/12/2020 |
| Patuxent Engineering | 1 | 04/08/2026 |
| Rand Engineering & Architecture | 1 | 08/15/2025 |
| Scalar Architecture | 1 | 07/09/2019 |
| Structural Preservation System | 1 | 12/25/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| CNY Building | 7 | 08/14/2026 |
| Exo Industries | 5 | 10/01/2026 |
| Eurostruct | 4 | 08/16/2023 |
| KG Sprinkler | 3 | 07/21/2026 |
| Deem Plumbing | 2 | 10/22/2025 |
| Donato Plumbing | 2 | 08/14/2026 |
| Everest Scaffolding | 2 | 09/12/2020 |
| Exterior Wall & Building | 2 | 04/08/2026 |
| Lane Refrigeration Co | 2 | 05/07/2024 |
| MC Gowan Builders | 2 | 11/19/2025 |
| MCLNY Plumbing & Heating | 2 | 08/16/2023 |
| Reidy Contracting Group | 2 | 07/17/2023 |
| Urban Intelligence | 2 | 04/08/2026 |
| Accurate Mechanical Indstrs | 1 | 11/20/2025 |
| Ami and Associates | 1 | 11/20/2025 |
| Dynamix Scaffold Group | 1 | 09/29/2025 |
| Midnight Express Mechanical CRP | 1 | 11/10/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| New York Athletic Club of the City | 22 | 08/14/2026 |
| Andamio Scaffolding | 1 | 09/12/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| A1 Expediting Service | 13 | 08/14/2026 |
| New York Athletic Club | 5 | 10/22/2025 |
| Domani Consulting | 2 | 05/07/2024 |
| Lombardo Building Consultants | 2 | 10/01/2026 |
| Julian A. Gomez | 1 | 08/15/2025 |
| Patuxent Engineering | 1 | 04/08/2026 |
| Smep Design & Consultation | 1 | 12/25/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00998983 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 02/07/2024 | 08/27/2026 | Contractor URBAN INTELLIGENCE, INC | INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2022 CHAPTER 33 . NO CHANGE IN… |
| M01247847 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 08/18/2025 | 08/26/2026 | Contractor H M SPRINKLER INC | SPRINKLER AND STANDPIPE WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 20-22. |
| M01108092 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration CO | Permit Issued | 09/17/2024 | 06/10/2026 | Design PBDW ARCHITECTS Contractor CNY BUILDING CORP | ST WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 21-24 AND TO THE 24TH FLOOR SOLARIUM STOREFRONT & ROOF. |
| M01322173 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 12/04/2025 | 06/01/2026 | Contractor EXTERIOR WALL & BUILDING | INSTALLATION OF OVERHEAD PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY … |
| M01166654 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 01/15/2025 | 01/15/2026 | Contractor EXO INDUSTRIES CORP | FACADE INSPECTIONS AND PROBES |
| M00858685 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 06/28/2023 | 01/02/2026 | Design RHL ENGINEERING, LLC Contractor DEEM PLUMBING INC Filer NEW YORK ATHLETIC CLUB | REPLACEMENT OF BUILDING'S EXISTING 4 GAS RISER WITH NEW AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M01136235 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 08/15/2025 | 12/24/2025 | Contractor EXO INDUSTRIES CORP Filer JULIAN A. GOMEZ | 9th Cycle FISP Repairs, No Change to Use, Egress of Occupancy. |
| M01298899 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 11/19/2025 | 12/22/2025 | Contractor MC GOWAN BUILDERS INC | MH work as per plans related to radiators, grilles, louvers, bathroom exhaust and associated ducts and piping. No change to use egress or o… |
| M01298903 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 11/20/2025 | 12/22/2025 | Contractor ACCURATE MECH INDSTRS INC | 3RD & 4TH FLOORS OF EXISTING HOTEL/SPORTS CLUB. REMOVE (3)EXISTING WOMEN'S LOCKER ROOM SHOWER STALLS. ADD (1) SAUNA INFORMER LOCATION OF SHO… |
| M01298896 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 11/18/2025 | 12/17/2025 | Design PBDW ARCHITECTS Contractor MC GOWAN BUILDERS INC | GC Work as per plans. No change to use, egress or occupancy on this application |
| M01318770 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 11/19/2025 | 11/19/2025 | Contractor EXO INDUSTRIES CORP | INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M01313092 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 11/05/2025 | 11/06/2025 | Contractor EXO INDUSTRIES CORP | Application for the installation and use of suspended scaffold for facade repair and inspection as per plans filed herein. No change in egre… |
| M01260530 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 07/25/2025 | 09/30/2025 | Design ASHRAF CORP Contractor DYNAMIX SCAFFOLD GROUP LL | INSTALLATION OF TEMPORARY MATERIAL HOIST AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER 33 OF NYC BC. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01247840 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 08/12/2025 | 08/28/2025 | Design PBDW ARCHITECTS Contractor CNY BUILDING CORP | INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 21-24 AND TO THE 24TH FLOOR SOLARIUM STOREFRONT & ROOF. |
| M01247842 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 08/12/2025 | 08/28/2025 | Design SEVERUD ASSOCIATES Contractor CNY BUILDING CORP | ST WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 21-24 AND TO THE 24TH FLOOR SOLARIUM STOREFRONT & ROOF. |
| M01247845 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 08/18/2025 | 08/28/2025 | Contractor CNY BUILDING CORP | MECHANICAL WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 21-24 AND TO THE 24TH FLOOR SOLARIUM STOREFRONT & ROOF. |
| M01247844 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 08/18/2025 | 08/27/2025 | Contractor DONATO PLUMBING, INC | PLUMBING WORK RELATED TO INTERIOR ALTERATIONS AND MODIFICATIONS TO TENANT FLOORS 21-24 AND TO THE 24TH FLOOR SOLARIUM STOREFRONT & ROOF. |
| M01200633 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 04/01/2025 | 05/12/2025 | Design CRIBSTONE ENGINEERING PLLC Contractor EXO INDUSTRIES CORP | Installation of temporary shoring posts to support two (2) window lintels at 2nd and 6th floors. |
| M01024809 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 05/07/2024 | 08/07/2024 | Design RHL ENGINEERING, LLC Contractor LANE REFRIGERATION CO.,IN Filer DOMANI CONSULTING | PROVIDE RECORD DOCUMENTATION OF EXISTING SECOND FLOOR COMMERCIAL KITCHEN EXHAUST SYSTEM PER ATTACHED PLANS. REPAIR, SUPPLEMENT OR REPLACE EX… |
| M01029259 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 04/15/2024 | 05/02/2024 | Contractor H M SPRINKLER INC | Installation of sprinkler temp loop as per plans filed herewith. No change to use, egress, or occupancy. |
| M00980162 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 02/14/2024 | 04/08/2024 | Contractor DONATO PLUMBING, INC | Plumbing and sprinkler modifications as per plans filed herewith. No change to use, egress, or occupancy. |
| M01009945 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 03/13/2024 | 03/28/2024 | Design EDWARDS AND ZUCK Contractor CNY BUILDING CORP | Mechanical modifications as per plans filed herewith. No change to use, egress, or occupancy. |
| M00980148 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 02/15/2024 | 02/26/2024 | Contractor CNY BUILDING CORP | Mechanical modifications as per plans filed herewith. No change to use, egress, or occupancy. |
| M00979330 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 01/08/2024 | 02/06/2024 | Design PBDW ARCHITECTS Contractor CNY BUILDING CORP | Interior renovations for guestrooms as per plans filed herewith. No change to use, egress, or occupancy. |
| M00973784 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 12/25/2023 | 01/10/2024 | Design STRUCTUAL PRESV SYSTEM Contractor STRUCTUAL PRESV SYSTEM | FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS, SEE ATTACHED PLANS Designated Primary Site… |
| M00912007 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 08/16/2023 | 01/03/2024 | Contractor EUROSTRUCT INC | MODIFICATION OF HVAC SYSTEM ON THE 13TH FLOOR (TENANT LEVEL 14TH) AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00912028 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 08/16/2023 | 10/03/2023 | Contractor NATIONWIDE MECHANICAL INC | MODIFICATION OF PLUMBING FIXTURES ON THE 13TH FLOOR (TENANT LEVEL 14TH) AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00911974 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 08/11/2023 | 08/22/2023 | Design PBDW ARCHITECTS Contractor EUROSTRUCT INC Filer NEW YORK ATHLETIC CLUB | INTERIOR RENOVATION WORK ON THE 13TH FLOOR (TENANT LEVEL 14TH) AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00870084 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 06/23/2023 | 08/18/2023 | Contractor EUROSTRUCT INC Filer NEW YORK ATHLETIC CLUB | MODIFICATION OF HVAC SYSTEM ON THE 10TH FLOOR AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00886715 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 07/17/2023 | 08/17/2023 | Design CUSTODIO CONSULTING, LLC Contractor FULL CAPACITY FIRE CORP Filer NEW YORK ATHLETIC CLUB | INSTALLATION OF SPRINKLERS ON THE 7TH FLOOR AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00886634 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 07/17/2023 | 08/08/2023 | Design CUSTODIO CONSULTING, LLC Contractor REIDY CONTRACTING GROUP Filer NEW YORK ATHLETIC CLUB | INTERIOR RENOVATION WORK ON THE 7TH FLOOR AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00886695 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 07/17/2023 | 08/08/2023 | Design CUSTODIO CONSULTING, LLC Contractor REIDY CONTRACTING GROUP | MODIFICATION OF HVAC SYSTEM ON THE 7TH FLOOR AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00643464 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 01/21/2022 | 08/03/2023 | Design RHL ENGINEERING, LLC Contractor DEEM PLUMBING INC Filer DOMANI CONSULTING | PLUMBING WORK TO INSTALL AUTOMATIC GAS SHUTOFF VALVES AS PER ATTACHED PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00870103 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 06/23/2023 | 07/12/2023 | Contractor NATIONWIDE MECHANICAL INC | MODIFICATION OF PLUMBING FIXTURES ON THE 10TH FLOOR AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00870033 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 06/21/2023 | 07/06/2023 | Design PBDW ARCHITECTS Contractor EUROSTRUCT INC | INTERIOR RENOVATION WORK ON THE 10TH FLOOR AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| M00689569 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Permit Issued | 02/16/2023 | 03/16/2023 | Design JMV CONSULTING ENGINEERING Contractor LANE REFRIGERATION CO.,IN | MECHANICAL WORK TO ACCOMMODATE AIR HANDLER UPGRADE ON 5TH FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M00504229 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Filed — no permit on record | 07/28/2022 | — | Design JMV CONSULTING ENGINEERING | — |
| M00188534 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 07/09/2019 | 06/30/2020 | Design SCALAR ARCHITECTURE PC Contractor EVEREST SCAFFOLDING INC Filer AE DESIGN SOLUTION INC. | INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M00354522 ↗ | 180 CENTRAL PARK SOUTH MANHATTAN | Alteration | Signed-off | 06/05/2020 | 06/08/2020 | Design GREEN DESIGN Owner ANDAMIO SCAFFOLDING LLC Contractor EVEREST SCAFFOLDING INC | INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPT… |
| Building | Filings | Most Recent |
|---|---|---|
| 180 CENTRAL PARK SOUTH ↗ | 39 | 10/01/2026 |