| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00352675 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/01/2020 | 12/08/2020 | Design MG ENGINEERING D.P.C. Contractor SKH MECHANICAL CORP | SPRINKLER WORK RELATED TO INSTALLATION OF NEW SPRINKLER HEADS AT 9TH FLOOR AND DEMO OF EXISTING TEMP LOOP AS SHOWN ON PLANS FILED HEREWITH. … |
| M00368754 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/13/2020 | 12/08/2020 | Design MG ENGINEERING D.P.C. Contractor SKH MECHANICAL CORP | INSTALLATION OF TEMPORARY SPRINKLER LOOP AND REMOVAL OF EXISTING SPRINKLER HEADS ON ASSOCIATED PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY… |
| M00352580 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/01/2020 | 08/12/2020 | Design MG ENGINEERING D.P.C. Contractor PRO STAR PLBG,HTG&MECH IN | PLUMBING MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION. |
| M00352681 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/01/2020 | 07/02/2020 | Contractor NUCOR CONSTRUCTION CORP | MECHANICAL WORK AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION |
| Name | Projects together | Most recent |
|---|---|---|
| MG Engineering | 3 | 04/07/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| SKH Mechanical | 2 | 04/07/2021 |
| Nucor Construction | 1 | 07/01/2020 |
| Pro Star Plumbing & Heating & Mechanical | 1 | 07/01/2020 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00352675 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/01/2020 | 12/08/2020 | Design MG ENGINEERING D.P.C. Contractor SKH MECHANICAL CORP | SPRINKLER WORK RELATED TO INSTALLATION OF NEW SPRINKLER HEADS AT 9TH FLOOR AND DEMO OF EXISTING TEMP LOOP AS SHOWN ON PLANS FILED HEREWITH. … |
| M00368754 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/13/2020 | 12/08/2020 | Design MG ENGINEERING D.P.C. Contractor SKH MECHANICAL CORP | INSTALLATION OF TEMPORARY SPRINKLER LOOP AND REMOVAL OF EXISTING SPRINKLER HEADS ON ASSOCIATED PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY… |
| M00352580 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/01/2020 | 08/12/2020 | Design MG ENGINEERING D.P.C. Contractor PRO STAR PLBG,HTG&MECH IN | PLUMBING MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION. |
| M00352681 ↗ | 16 EAST 34TH STREET MANHATTAN | Alteration | Signed-off | 07/01/2020 | 07/02/2020 | Contractor NUCOR CONSTRUCTION CORP | MECHANICAL WORK AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION |
| Building | Filings | Most Recent |
|---|---|---|
| 16 EAST 34TH STREET ↗ | 4 | 04/07/2021 |