| Owner | Filings | Most Recent |
|---|---|---|
| S J CONSTRUCTION SERVIC | 2 | 07/08/2026 |
| S & J CONSTRUCTION SERVIC | 2 | 03/22/2026 |
| UNITED LA LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/21/2023 | $3.1M | — | Private party → UNITED LA LLC | $763/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LAM ENGINEER PC | 6 | 10/16/2024 |
| RIGID STRUCTURAL DESIGN, LLC | 1 | 02/16/2024 |
| ENTHINK ENGINEERS LLC | 1 | 01/13/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Rigid Structural Design, LLC | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JC BROTHERS DEVELOPMENT | General Contractor | 3 | 03/21/2026 |
| KJK ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| BUILDCOX CONSTRUCTION COR | General Contractor | 1 | 07/08/2026 |
| S & J CONSTRUCTION SVC | General Contractor | 1 | 07/08/2026 |
| DYNAMIC PLBG & SPRKLR COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LAM ENGINEER PC | 1180 | 6 | 10/16/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | CITYWIDE PLBG HTG & SPKLS | 04/02/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | BUILDCOX CONSTRUCTION COR | 02/16/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JC BROTHERS DEVELOPMENT | 01/17/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | S & J CONSTRUCTION SVC | 01/21/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2025 | Complete | KJK ELECTRIC INC | General Wiring |
| 01/13/2021 | Complete | RICHARD NEU | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/07/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/07/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/27/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/31/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/26/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/17/2024 | Fire-Resistant Penetrations and Joints | YUK LAM | special |
| 10/17/2024 | Energy Code Compliance Inspections | YUK LAM | progress |
| 10/17/2024 | Maintenance information | YUK LAM | energy_progress |
| 10/17/2024 | HVAC-R and service water heating system controls | YUK LAM | energy_progress |
| 10/17/2024 | HVAC-R and service water heating equipment | YUK LAM | energy_progress |
| 10/17/2024 | HVAC-R and service water piping design and insulation | YUK LAM | energy_progress |
| 10/05/2024 | Maintenance information | YUK LAM | energy_progress |
| 10/05/2024 | Fire-Resistant Penetrations and Joints | YUK LAM | special |
| 10/05/2024 | Energy Code Compliance Inspections | YUK LAM | progress |
| 10/05/2024 | HVAC-R and service water piping design and insulation | YUK LAM | energy_progress |
| 10/05/2024 | HVAC-R and service water heating system controls | YUK LAM | energy_progress |
| 10/05/2024 | HVAC-R and service water heating equipment | YUK LAM | energy_progress |
| 09/27/2024 | Fenestration areas | YUK LAM | energy_progress |
| 09/27/2024 | HVAC-R and service water piping design and insulation | YUK LAM | energy_progress |
| 09/27/2024 | HVAC-R and service water heating equipment | YUK LAM | energy_progress |
| 09/27/2024 | Fenestration air leakage | YUK LAM | energy_progress |
| 09/27/2024 | HVAC-R and service water heating system controls | YUK LAM | energy_progress |
| 09/27/2024 | Interior lighting power | YUK LAM | energy_progress |
| 09/27/2024 | Air barrier - visual inspection | YUK LAM | energy_progress |
| 09/27/2024 | Maintenance information | YUK LAM | energy_progress |
| 09/27/2024 | Fenestration and door U-factor and product ratings | YUK LAM | energy_progress |
| 09/27/2024 | Fire-Resistant Penetrations and Joints | YUK LAM | special |
| 09/27/2024 | Mechanical Systems | YUK LAM | special |
| 09/27/2024 | Structural Stability – Alterations of existing buildings | YUK LAM | special |
| 09/27/2024 | Energy Code Compliance Inspections | YUK LAM | progress |