💬 Discuss this project
1964Year Built
5Stories
P1Building Class
C4-7Zoning
264,420 sfGross Floor Area
0Units
LL97 Covered2 Active Violations 0 unresolved · 2 paperwork only ▸
Concert hall · 316,430 sf lot · 0.84 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofNew York Philharmonic Library, David Geffen Hall207p · 10 filings · 20 docs
BulkheadNew York Philharmonic Library1p · 1 filing · 6 docs
PenthouseNew York Philharmonic Library, David Geffen Hall227p · 13 filings · 20 docs
Floor 6New York Philharmonic Library19p · 6 filings · 20 docs
Floor 5New York Philharmonic Library, David Geffen Hall236p · 16 filings · 20 docs
Floor 4New York Philharmonic Library, David Geffen Hall237p · 17 filings · 20 docs
Floor 3New York Philharmonic Library, David Geffen Hall253p · 17 filings · 20 docs
Floor 2David Geffen Hall, New York Philharmonic Library13p · 41 filings · 20 docs
Floor 1David Geffen Hall, New York Philharmonic Library13p · 31 filings · 20 docs
MezzanineDavid Geffen Hall1p · 1 filing · 20 docs
CellarNew York Philharmonic Library, David Geffen Hall223p · 13 filings · 20 docs
Sub-CellarNew York Philharmonic Library, David Geffen Hall208p · 9 filings · 20 docs
Site & exteriorNew York Philharmonic Library, Lincoln Center29p · 15 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Lincoln Center for the Performing A25310/06/2026
The Juilliard School103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Milrose Consultants8203/21/2026
Municipal Building Consultants603/21/2026
A1 Expediting Service2203/21/2026
Direct Access Expediting1003/21/2026
AE Design Solution1003/21/2026
Patuxent Engineering203/21/2026
Sirina Fire Protection203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Turner Construction CompanyGeneral Contractor2707/08/2026
Safway AtlanticScaffold2207/08/2026
Arena Event ServicesGeneral Contractor1203/21/2026
King Hoist & ScaffoldingScaffold1207/08/2026
PJP InstallersScaffold907/08/2026
Almar Plumbing & HeatingPlumbing707/08/2026
Good Sense & Co Product SGeneral Contractor603/21/2026
Aspro PlumbingPlumbing507/08/2026
Rael Automatic Sprinkler CoFire Protection407/08/2026
Rael Automatic Sprinkler CoFire Protection407/08/2026
Winick ProductionsGeneral Contractor407/08/2026
Allran Electric of NYElectrical303/22/2026
Advanced Scaffold ServicesScaffold303/21/2026
Spring ScaffoldingScaffold307/08/2026
Sirina Fire ProtectionFire Protection207/08/2026
Commodore ConstructionScaffold203/21/2026
Jads ProductionsGeneral Contractor107/08/2026
Transel Elev. & ElectricElectrical103/22/2026
Quantum ElectricElectrical103/22/2026
Fred Geller ElectricalElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M.G. McLaren Engineering2999105/09/2023
Future Tech Consultants O5892002/01/2023
Building Lifecycle
All (300)Filed (72)Permit Issued (75)Signed Off (34)Violation (6)Inspection (3)Objection (80)Special Inspection (30)
10/20/2026
Signed off — Alteration
Temporary platform for Geffen Hall events in the promenade. Removed at the end of the programing. No changes to existing structures, use or egress.
M01316414-I1
10/08/2026
Objection resolved — Addressed
10/06/2026
Objection raised — Other
10/05/2026
Filed — Alteration
Temporary platform for Geffen Hall events in the promenade. Removed at the end of the programing. No changes to existing structures, use or egress.
M01316414-P2
10/05/2026
Filed — No Work
M01469415-I1
10/05/2026
Special inspection requirement — Final
ANDY ENGLER ROTH
06/29/2026
Special inspection requirement — Final
ANDY ENGLER ROTH
06/23/2026
Filed — No Work
M01420450-I1
06/23/2026
Filed — Alteration
Temporary platform for Geffen Hall events in the promenade. Removed at the end of the programing. No changes to existing structures, use or egress.
M01316414-P1
06/22/2026
Special inspection requirement — Final
ANDY ENGLER ROTH
06/11/2026
Filed — No Work
M01415684-I1
11/17/2025
Filed — No Work
M01317196-P1
11/17/2025
Permit issued — General Construction
M01316414-I1-GC
11/12/2025
Filed — Alteration
Temporary platform for Geffen Hall events in the promenade. Removed at the end of the programing. No changes to existing structures, use or egress.
M01316414-I1
11/12/2025
Filed — No Work
M01317196-I1
11/04/2025
Filed — No Work
M01312352-I1
09/16/2025
Filed — No Work
M01288007-I1
05/15/2025
Filed — No Work
M01226494-I1
02/26/2025
Filed — No Work
M01183891-I1
01/14/2025
Violation issued (ECB, closed)
Elevators
11/26/2024
Filed — No Work
M01147984-I1
11/12/2024
Signed off — Alteration
Temporary structures for Geffen Hall events. Removed at the end of the programing. No changes to existing structures, use or egress.
M01113334-I1
09/23/2024
Permit issued — General Construction
M01113334-I1-GC
09/18/2024
Filed — Alteration
Temporary structures for Geffen Hall events. Removed at the end of the programing. No changes to existing structures, use or egress.
M01113334-I1
09/18/2024
Filed — No Work
M01112827-I1
09/18/2024
Special inspection requirement — Final
ANDY ENGLER ROTH
06/05/2024
Filed — No Work
M01060808-I1
05/29/2024
Filed — No Work
M01056500-P1
05/24/2024
Filed — No Work
M01056500-I1
04/24/2024
Objection resolved — Addressed
04/23/2024
Filed — No Work
M01039450-I1
04/23/2024
Objection raised — Other
02/29/2024
Objection resolved — Addressed
02/27/2024
Filed — No Work
M01011059-I1
02/27/2024
Objection raised — Admin
01/10/2024
Signed off — Alteration
M00871805-I1
01/09/2024
Permit issued — General Construction
M00871805-I1-ST
11/06/2023
Filed — No Work
M00957233-P1
11/03/2023
Filed — No Work
M00957233-I1
11/03/2023
Objection raised — Scope
11/03/2023
Objection resolved — Addressed
09/25/2023
Filed — No Work
M00938613-I1
09/18/2023
Filed — No Work
M00935055-I1
09/18/2023
Objection raised — Other
09/18/2023
Objection resolved — Addressed
08/25/2023
Signed off — Alteration
Temporary structures for Geffen Hall events. Removed at the end of the programing. No changes to existing structures, use or egress.
M00809497-I1
08/21/2023
Special inspection requirement — Public Assembly Emergency Lighting
Stephen Marchese
08/16/2023
Objection resolved — Addressed
08/16/2023
Objection resolved — Addressed
05/11/2023
Permit issued — General Construction
M00871805-I1-GC
05/09/2023
Filed — Alteration
M00871805-I1
05/01/2023
Filed — No Work
M00867056-I1
05/01/2023
Objection raised — Mechanical
05/01/2023
Objection resolved — Addressed
04/21/2023
Filed — No Work
M00863047-I1
03/22/2023
Special inspection requirement — Public Assembly Emergency Lighting
Stephen Marchese
03/14/2023
Filed — No Work
M00562997-P2
03/14/2023
Objection raised — Other
03/14/2023
Objection raised — Other
03/14/2023
Special inspection requirement — Public Assembly Emergency Lighting
Stephen Marchese
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedWinick Productions11/17/2025
DOB NOWGeneral ConstructionSigned-offWinick Productions09/23/2024
DOB NOWGeneral ConstructionSigned-offGood Sense & Co Product S01/09/2024
DOB NOWGeneral ConstructionSigned-offGood Sense & Co Product S05/11/2023
DOB NOWGeneral ConstructionSigned-offWinick Productions01/12/2023
DOB NOWPlumbingSigned-offAlmar Plumbing & Heating11/29/2022
DOB NOWGeneral ConstructionSigned-offTurner Construction Company10/27/2022
DOB NOWStructuralSigned-offTurner Construction Company10/27/2022
DOB NOWGeneral ConstructionSigned-offTurner Construction Company10/27/2022
DOB NOWMechanical SystemsSigned-offTurner Construction Company10/27/2022
DOB NOWStructuralSigned-offTurner Construction Company08/04/2022
DOB NOWStandpipeSigned-offRael Automatic Sprinkler Co06/22/2022
DOB NOWStandpipeSigned-offRael Automatic Sprinkler Co06/21/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding04/16/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding04/16/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding04/15/2022
DOB NOWPlumbingSigned-offAlmar Plumbing & Heating03/21/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding03/10/2022
DOB NOWSprinklersSigned-offRael Automatic Sprinkler Co03/01/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding02/28/2022
DOB NOWGeneral ConstructionSigned-offJads Productions02/24/2022
DOB NOWProtection and Mechanical MethodsSigned-offSafway Atlantic02/18/2022
DOB NOWProtection and Mechanical MethodsSigned-offSafway Atlantic02/17/2022
DOB NOWStandpipeSigned-offRael Automatic Sprinkler Co02/09/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding02/02/2022
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding01/24/2022
DOB NOWConstruction FenceSigned-offPJP Installers01/13/2022
DOB NOWSidewalk ShedSigned-offPJP Installers01/13/2022
DOB NOWPlumbingSigned-offAlmar Plumbing & Heating01/07/2022
DOB NOWSidewalk ShedSigned-offSafway Atlantic12/30/2021
DOB NOWProtection and Mechanical MethodsSigned-offSafway Atlantic12/10/2021
DOB NOWSidewalk ShedSigned-offKing Hoist & Scaffolding12/02/2021
DOB NOWSupported ScaffoldSigned-offKing Hoist & Scaffolding12/02/2021
DOB NOWPlumbingSigned-offAspro Plumbing11/26/2021
DOB NOWBoiler EquipmentSigned-offS.J. Fuel Co11/15/2021
DOB NOWMechanical SystemsSigned-offTurner Construction Company10/27/2021
DOB NOWMechanical SystemsSigned-offTurner Construction Company10/27/2021
DOB NOWStructuralSigned-offTurner Construction Company10/27/2021
DOB NOWStructuralSigned-offTurner Construction Company10/27/2021
DOB NOWGeneral ConstructionSigned-offTurner Construction Company10/27/2021
+ 60 more permits on file
20 projects · most recent 08/31/2023
General Wiring
FiledStatusContractorScope
08/31/2023CompleteFred Geller ElectricalGeneral Wiring
06/05/2023CompleteAllran Electric of NYGeneral Wiring
01/09/2023CompleteAllran Electric of NYGeneral Wiring
12/22/2022CompleteAdco ElectricalGeneral Wiring
03/15/2022CompleteR.C.M. Electric—
12/22/2021CompleteQuantum ElectricGeneral Wiring
12/22/2021CompleteQuantum ElectricGeneral Wiring
11/04/2021CompleteStanco System Electrical Cont—
08/20/2021CompleteStar-Delta Electric—
06/11/2021CancelledTransel Elev. & ElectricGeneral Wiring
05/19/2021CompleteTransel Elev. & ElectricGeneral Wiring
04/07/2021CompleteTransel Elev. & ElectricGeneral Wiring
01/21/2021CompleteCorporate Electric Group—
10/26/2020CompleteAllran Electric of NY—
10/26/2020CompleteAllran Electric of NY—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
04/07/2022Pass-Final Boiler Equipment InspectionPassView ↗
09/07/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/03/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 67
DateRequirementInspectorRole
10/05/2026FinalANDY ENGLER ROTHprogress
06/29/2026FinalANDY ENGLER ROTHprogress
06/22/2026FinalANDY ENGLER ROTHprogress
09/18/2024FinalANDY ENGLER ROTHprogress
08/21/2023Public Assembly Emergency LightingStephen Marcheseprogress
03/22/2023Public Assembly Emergency LightingStephen Marcheseprogress
03/14/2023Public Assembly Emergency LightingStephen Marcheseprogress
03/14/2023Public Assembly Emergency LightingStephen Marcheseprogress
03/13/2023Public Assembly Emergency LightingStephen Marcheseprogress
03/13/2023Public Assembly Emergency LightingStephen Marcheseprogress
02/01/2023FinalStephen Marcheseprogress
02/01/2023Mechanical SystemsStephen Marchesespecial
02/01/2023Fire-Resistant Penetrations and JointsStephen Marchesespecial
02/01/2023Emergency and Standby Power Systems (Generator)Stephen Marchesespecial
01/31/2023Public Assembly Emergency LightingStephen Marcheseprogress
01/31/2023Public Assembly Emergency LightingStephen Marcheseprogress
01/31/2023Public Assembly Emergency LightingStephen Marcheseprogress
01/31/2023Public Assembly Emergency LightingStephen Marcheseprogress
01/09/2023FinalANDY ENGLER ROTHprogress
10/20/2022Public Assembly Emergency LightingStephen Marcheseprogress
10/19/2022Public Assembly Emergency LightingStephen Marcheseprogress
09/22/2022Public Assembly Emergency LightingStephen Marcheseprogress
09/22/2022Public Assembly Emergency LightingStephen Marcheseprogress
09/15/2022Post-installed AnchorsStephen Marchesespecial
09/15/2022FinalRENEE RAJAPPAprogress
Latest 25 of 67.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
David Geffen HallArts / Culture / EntertainmentSub-cellar, Cellar, Floors 1–5, Penthouse, Roof
Project M01316414 Alteration · LOC Issued · 11/12/2025
Project M01113334 Alteration · LOC Issued · 09/18/2024
Project M00809497 Alteration · LOC Issued · 01/10/2023
Project M00562910 No Work · PA Certificate of Operation Issued · 08/10/2021
Project M00562949 No Work · PAA Approved · 08/10/2021
Project M00562973 No Work · PAA Approved · 08/10/2021
Project M00562997 No Work · PAA Approved · 08/10/2021
Project M00566105 No Work · PAA Approved · 08/10/2021
Project M00566131 No Work · PA Certificate of Operation Issued · 08/10/2021
Project M00566163 No Work · PAA Approved · 08/10/2021
Project M00425844 Alteration · LOC Issued · 11/17/2020
Project M00423210 Alteration · LOC Issued · 11/16/2020
New York Philharmonic LibraryArts / Culture / EntertainmentSub-cellar, Cellar, Floors 1–6, Penthouse, Roof
Project M00871805 Alteration · LOC Issued · 05/09/2023
Project M00781945 Alteration · LOC Issued · 07/27/2022
Project M00695461 Alteration · LOC Issued · 03/10/2022
Project M00688442 Alteration · LOC Issued · 02/28/2022
Project M00673053 Alteration · LOC Issued · 02/02/2022
Project M00665849 Alteration · LOC Issued · 01/20/2022
Project M00642812 Alteration · LOC Issued · 12/08/2021
Project M00640650 Alteration · LOC Issued · 12/02/2021
Project M00601702 Alteration · LOC Issued · 10/01/2021
Project M00583051 Alteration · LOC Issued · 08/26/2021
Project M00578727 Alteration · LOC Issued · 08/24/2021
Project M00526000 Alteration · LOC Issued · 06/15/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 1,139 on file (BIS + DOB NOW)
▸Plans & Drawings105
▸DOB NOWPlans/Sketch - Temporary Place of Assembly29
10/06/2026M01469415-I1Request digital key ↗
09/05/2026M00160634-I1Request digital key ↗
09/05/2026M00255710-I1Request digital key ↗
Showing 3 of 29 on file for this type
▸DOB NOWPlans/Sketch26
09/06/2026M00078798-I1Request digital key ↗
09/03/2026M00515442-P1Request digital key ↗
09/03/2026M00515442-I1Request digital key ↗
Showing 3 of 26 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly16
09/03/2026M00566131-P1Request digital key ↗
09/03/2026M00562997-P2Request digital key ↗
09/01/2026M00562910-P2Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Plumbing7
09/04/2026M00365727-I1Request digital key ↗
09/04/2026M00365958-I1Request digital key ↗
09/02/2026M00443667-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Standpipe7
09/04/2026M00404664-I1Request digital key ↗
09/04/2026M00404082-I1Request digital key ↗
Showing 2 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed4
09/04/2026M00457315-I1Request digital key ↗
09/04/2026M00457315-P1Request digital key ↗
09/03/2026M00386769-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold4
09/04/2026M00388419-I1Request digital key ↗
09/04/2026M00422712-I1Request digital key ↗
09/03/2026M00422705-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/04/2026M00366149-I1Request digital key ↗
09/01/2026M00425844-P1Request digital key ↗
09/01/2026M00425844-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment2
09/04/2026M00423344-P1Request digital key ↗
Showing 1 of 2 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/04/2026M00386772-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
09/04/2026M00463612-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Protection of Mechanical Methods1
09/04/2026M00476694-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/04/2026M00403972-I1Request digital key ↗
▸Applications & Permits180
▸BISPLAN / WORK APPROVAL APPLICATION111
04/18/2025110230697Open ↗
04/16/2025110230697Open ↗
04/15/2025110230697Open ↗
Showing 3 of 111 on file for this type
▸BISWORK PERMIT APPLICATION60
10/31/2022140927870Open ↗
02/23/2021140927870Open ↗
02/01/2021140997651Open ↗
Showing 3 of 60 on file for this type
▸BISPLACE OF ASSEMBLY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)3
01/25/2021140927870Open ↗
Showing 1 of 3 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
04/05/2022140927870Open ↗
▸BISOPEN APPLICATIONS SEARCH1
08/13/2025140927870Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
01/25/2021140927870Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISZONING DIAGRAM2
01/22/2021140927870Open ↗
01/07/2021140927870Open ↗
▸BISZRD1-Zoning Resolution Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISVERIFY TAX LOT1
08/13/2025140927870Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
08/13/2025140927870Open ↗
▸Seals & Professional Certifications302
▸DOB NOWDPL-1: Design Professional Seal & Signature103
10/06/2026M01316414-P2Open ↗
10/06/2026M01469415-I1Open ↗
09/04/2026M00386772-I1Open ↗
Showing 3 of 103 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION69
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 69 on file for this type
▸DOB NOWProgress Inspector Seal & Signature39
10/18/2026M00809497-I1Open ↗
10/06/2026M01316414-P2Open ↗
09/02/2026M00526058-I1Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature24
09/23/2026M00423344-I1Open ↗
09/02/2026M00526058-I1Open ↗
09/02/2026M00423210-P1Open ↗
Showing 3 of 24 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT17
01/25/2021140997651Open ↗
12/10/2020140985575Open ↗
11/25/2020140984273Open ↗
Showing 3 of 17 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION10
01/25/2021140997651Open ↗
12/10/2020140985575Open ↗
11/25/2020140984273Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY7
01/25/2021140997651Open ↗
12/10/2020140985575Open ↗
11/25/2020140984273Open ↗
Showing 3 of 7 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Trade Schedules & Equipment20
▸BISSELF-CERT PLUMBING NOTICE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWFDNY: Letter of No Objection3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISEQUIPMENT USE PERMITS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection4
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Environmental & Asbestos43
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form9
09/04/2026M00403972-I1Open ↗
09/02/2026M00443667-I1Open ↗
09/01/2026M00425844-I1Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
03/07/2023140927870Open ↗
Showing 1 of 5 on file for this type
▸BISASBESTOS: VARIANCE (DEP FORM V5)4
01/25/2021140927870Open ↗
Showing 1 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORM PRIOR TO SIGN OFF: TRU1640MN201
03/07/2023140927870Open ↗
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORMPRIOR TO SIGN OFF: TRU1308MN201
04/15/2022140918381Open ↗
▸Energy Compliance19
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY9
12/09/2021123488626Open ↗
11/30/2021123488626Open ↗
11/23/2021123488626Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
12/09/2021123488626Open ↗
11/30/2021123488626Open ↗
11/23/2021123488626Open ↗
Showing 3 of 4 on file for this type
▸Inspections & Test Reports55
▸BISTECHNICAL REPORT: RESPONSIBILITY53
04/23/2025110230697Open ↗
07/26/2022140970233Open ↗
07/22/2022140921705Open ↗
Showing 3 of 53 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
11/25/2020140984273Open ↗
▸BISSPRAYED FIRE-RESISTANT MATERIALS1
08/03/2022140927870Open ↗
▸Approvals, Objections & Sign-offs194
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter100
10/06/2026M01316414-P2Open ↗
10/06/2026M01469415-I1Open ↗
09/04/2026M00386772-I1Open ↗
Showing 3 of 100 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST32
04/23/2025110230697Open ↗
08/05/2022140918372Open ↗
07/27/2022140970233Open ↗
Showing 3 of 32 on file for this type
▸BISADMINISTRATIVE OBJECTIONS19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION13
12/15/2022140927870Open ↗
04/01/2021140927870Open ↗
04/01/2021140927870Open ↗
Showing 3 of 13 on file for this type
▸BISFINAL9
04/22/2025110230697Open ↗
07/26/2022140970233Open ↗
07/20/2022140958024Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP Variance (V5) letter9
09/04/2026M00403972-I1Open ↗
Showing 1 of 9 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE8
06/30/2023140927870Open ↗
12/20/2022140927870Open ↗
09/23/2022140927870Open ↗
Showing 3 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
10/31/2022140927870Open ↗
02/10/2021140927870Open ↗
Showing 2 of 3 on file for this type
▸BISSUPERSEDING LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership60
▸BISCOST AFFIDAVIT52
04/22/2025110230697Open ↗
04/26/2022120753942Open ↗
12/09/2021123488626Open ↗
Showing 3 of 52 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW36
09/27/2023140927870Open ↗
06/15/2022140921705Open ↗
05/27/2022140984273Open ↗
Showing 3 of 6 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE2
02/23/2021140927870Open ↗
Showing 1 of 2 on file for this type
▸Filing & Intake Forms65
▸BISADDITIONAL INFORMATION23
03/07/2023140927870Open ↗
03/07/2023140927870Open ↗
03/07/2023140927870Open ↗
Showing 3 of 23 on file for this type
▸BISEFILING COVER SHEET23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET14
01/25/2021140997651Open ↗
12/10/2020140985575Open ↗
Showing 2 of 14 on file for this type
▸BISBOROUGH INTAKE FORM5
10/31/2022140927870Open ↗
Showing 1 of 5 on file for this type
▸Other Documents67
▸DOB NOWAlternate Plan 116
09/03/2026M00566131-P1Open ↗
09/03/2026M00562997-P2Open ↗
09/01/2026M00562910-P2Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWAlternate Plan 210
09/03/2026M00562997-P2Open ↗
09/01/2026M00562910-P2Open ↗
09/01/2026M00563024-I1Open ↗
Showing 3 of 10 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION9
04/23/2025110230697Open ↗
Showing 1 of 9 on file for this type
▸BISFEE EXEMPTION DOCUMENTATION5
01/25/2021140997651Open ↗
Showing 1 of 5 on file for this type
▸DOB NOWAlternate Plan 34
09/01/2026M00562910-P2Open ↗
09/01/2026M00563024-P1Open ↗
09/01/2026M00563024-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAlternate Plan 64
09/01/2026M00562910-P2Open ↗
09/01/2026M00563024-P1Open ↗
09/01/2026M00563024-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAlternate Plan 54
09/01/2026M00562910-P2Open ↗
09/01/2026M00563024-P1Open ↗
09/01/2026M00563024-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAlternate Plan 44
09/01/2026M00562910-P2Open ↗
09/01/2026M00563024-I1Open ↗
09/01/2026M00563024-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAlternate Plan 74
09/01/2026M00562910-P2Open ↗
09/01/2026M00563024-P1Open ↗
09/01/2026M00563024-I1Open ↗
Showing 3 of 4 on file for this type
▸BISLincoln Center Property Assesment Roll - Exempt Status3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWAlternate Plan 82
09/01/2026M00563024-P1Open ↗
09/01/2026M00563024-I1Open ↗
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type