← Back
BuildNYC
Community center
100 WEST 146TH STREET
MANHATTAN · BIN 1060189
💬 Discuss this project
1971Year Built
2Stories
P5Building Class
C8-3Zoning
36,200 sfGross Floor Area
2Units
LL97 Covered0 Active Violations
Community center · Owner of record: CS Esplanade Gardens · 23,989 sf lot · 1.51 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofAcs School Center, Department of the Aging14p · 5 filings · 17 docs
Floor 2Acs School Center, Department of the Aging81p · 6 filings · 15 docs
Floor 1Acs School Center, Department of the Aging86p · 8 filings · 15 docs
CellarUnderground sanitary piping installation1p · 1 filing · 2 docs
Site & exteriorCitibike station construction fence9p · 3 filings · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CS Esplanade Gardens4203/22/2026
Jonas Equities203/21/2026
Ceqy103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/30/2014$7.0M—TRUST AGREEMENT DATED AUGUST 20,1990 MADE BY → CS ESPLANADE GARDENS LLC$193/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Caso Associates1803/21/2026
AE Design Solution403/21/2026
Tarek M. Zeid, P.E103/21/2026
J.A.M. Associates403/21/2026
SBLM403/21/2026
Tarek M Zeid P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A F Fire ProtectionPlumbing803/22/2026
Arsenal ScaffoldScaffold807/08/2026
Pinnacle Commercial DevelopmentGeneral Contractor603/21/2026
Nycom ElectricalElectrical303/22/2026
KG Construction ServicesGeneral Contractor307/08/2026
Forsythe P&HPlumbing207/08/2026
Aqua Plumbing & HeatingPlumbing207/08/2026
Nash Electric ServicesElectrical103/22/2026
KG Construction ServicesScaffold107/08/2026
A & F Fire Protection CoFire Protection107/08/2026
Kilo Watt ElectricElectrical103/22/2026
Casino Plumbing & HeatingFire Protection107/08/2026
R.A.M.S. Mechanicalspecialty_contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
20/20 Inspections1471905/11/2023
MJ Engineering & Design5546404/05/2021
Building Lifecycle
All (151)Filed (19)Permit Issued (17)Signed Off (13)Violation (29)Inspection (7)Objection (36)Special Inspection (30)
06/12/2026
Signed off — Alteration
M00537851-I1
03/18/2024
Signed off — Alteration
M00338167-I1
11/01/2023
Permit issued — General Construction
M00537851-I1-GC
06/02/2023
Signed off — Alteration
Install new plumbing fixtures, new electric domestic water heater, new hot & cold water piping from single point connection provided by the owner, new sanitary & vent piping to connect to landlord's provided sanitary drainage system & grease interceptor.
M00410866-I1
05/26/2023
Signed off — Alteration
Install ductwork to connect 4 existing HVAC units for heating, ventilation & install split AC unit for supplemental cooling of MDF rm, exhaust fans for ventilation of toilets & warming pantry & electric supplemental heating perimeter rms. PAA in comments
M00410990-I1
05/23/2023
Signed off — Alteration
Install sprinkler system by extending from base building sprinkler mains and risers. PAA description in comments
M00410904-I1
05/22/2023
Signed off — Alteration
Addition of steel framing at opening on roof
M00653253-S1
05/22/2023
Signed off — Alteration
CONSTRUCTION FENCE IN CONJUNCTION WITH JOB NUMBER M00653253
M00729562-I1
05/22/2023
Signed off — Alteration
Addition of steel framing at opening on roof
M00653253-I1
05/12/2023
Special inspection requirement — Sprinkler Systems
JACOB HAAS
05/11/2023
Filed — Alteration
Install sprinkler system by extending from base building sprinkler mains and risers. PAA description in comments
M00410904-P2
04/28/2023
Permit issued — Structural
M00653253-S1-ST
04/24/2023
Special inspection requirement — Sprinkler Systems
JACOB HAAS
03/24/2023
Special inspection requirement — Mechanical Systems
JACOB HAAS
03/24/2023
Special inspection requirement — HVAC and service water heating equipment
JACOB HAAS
03/24/2023
Special inspection requirement — HVAC and service water heating system controls
JACOB HAAS
03/24/2023
Special inspection requirement — Duct leakage testing
JACOB HAAS
03/24/2023
Special inspection requirement — HVAC insulation and sealing
JACOB HAAS
03/24/2023
Special inspection requirement — Maintenance information
JACOB HAAS
03/24/2023
Special inspection requirement — Shutoff dampers
JACOB HAAS
03/24/2023
Special inspection requirement — Final
JACOB HAAS
03/23/2023
Filed — Alteration
Install ductwork to connect 4 existing HVAC units for heating, ventilation & install split AC unit for supplemental cooling of MDF rm, exhaust fans for ventilation of toilets & warming pantry & electric supplemental heating perimeter rms. PAA in comments
M00410990-P1
03/07/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/07/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/07/2023
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
02/27/2023
Special inspection requirement — Shutoff dampers
JACOB HAAS
02/27/2023
Special inspection requirement — Mechanical Systems
JACOB HAAS
02/27/2023
Special inspection requirement — Final
JACOB HAAS
02/27/2023
Special inspection requirement — Duct leakage testing
JACOB HAAS
02/27/2023
Special inspection requirement — Maintenance information
JACOB HAAS
02/27/2023
Special inspection requirement — HVAC insulation and sealing
JACOB HAAS
02/27/2023
Special inspection requirement — HVAC and service water heating equipment
JACOB HAAS
02/27/2023
Special inspection requirement — HVAC and service water heating system controls
JACOB HAAS
02/17/2023
Filed — Alteration
Addition of steel framing at opening on roof
M00653253-S1
02/03/2023
Special inspection requirement — Insulation placement and R values
JACOB HAAS
02/03/2023
Special inspection requirement — Sprayed fire-resistant materials
JACOB HAAS
02/03/2023
Special inspection requirement — Post-installed Anchors
JACOB HAAS
02/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
JACOB HAAS
02/03/2023
Special inspection requirement — Final
JACOB HAAS
02/03/2023
Special inspection requirement — Fire-Resistance Rated Construction
JACOB HAAS
02/03/2023
Special inspection requirement — Lighting controls
JACOB HAAS
02/03/2023
Special inspection requirement — Interior lighting power
JACOB HAAS
02/02/2023
Filed — Alteration
Addition of steel framing at opening on roof
M00653253-P1
02/02/2023
Special inspection requirement — Post-installed Anchors
02/02/2023
Special inspection requirement — Interior lighting power
JACOB HAAS
02/02/2023
Special inspection requirement — Sprayed fire-resistant materials
JACOB HAAS
02/02/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
JACOB HAAS
10/01/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/30/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/01/2022
Filed — Alteration
Install sprinkler system by extending from base building sprinkler mains and risers. PAA description in comments
M00410904-P1
08/17/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/01/2022
Filed — Alteration
CONSTRUCTION FENCE IN CONJUNCTION WITH JOB NUMBER M00653253
M00729562-I1
08/01/2022
Permit issued — Construction Fence
M00729562-I1-FN
08/01/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/14/2022
Permit issued — Mechanical Systems
M00410990-I1-MS
07/06/2022
Permit issued — Sprinklers
M00410904-I1-EW-SP
06/28/2022
Permit issued — Plumbing
M00410866-I1-PL
06/24/2022
Permit issued — General Construction
M00653253-I1-GC
01/14/2022
Filed — Alteration
Install sprinkler system by extending from base building sprinkler mains and risers. PAA description in comments
M00410904-I1
01/14/2022
Filed — Alteration
Addition of steel framing at opening on roof
M00653253-I1
Latest 60 of 151 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPinnacle Commercial Development11/01/2023
DOB NOWStructuralSigned-offStalco04/28/2023
DOB NOWConstruction FenceSigned-offStalco08/01/2022
DOB NOWMechanical SystemsSigned-offR.A.M.S. Mechanical07/14/2022
DOB NOWSprinklersSigned-offAdvanced Automatic Sprinkler Co07/06/2022
DOB NOWPlumbingSigned-offForsythe P&H06/28/2022
DOB NOWGeneral ConstructionSigned-offStalco06/24/2022
DOB NOWMechanical SystemsSigned-offPinnacle Commercial Development06/24/2021
DOB NOWConstruction FenceSigned-offArsenal Scaffold03/21/2021
DOB NOWSprinklersSigned-offCasino Plumbing & Heating02/12/2021
DOB NOWPlumbingSigned-offAqua Plumbing & Heating01/26/2021
DOB NOWMechanical SystemsSigned-offPinnacle Commercial Development11/30/2020
DOB NOWPlumbingSigned-offAqua Plumbing & Heating06/24/2020
DOB NOWSidewalk ShedSigned-offArsenal Scaffold03/19/2020
DOB NOWConstruction FenceSigned-offArsenal Scaffold03/19/2020
DOB NOWSidewalk ShedSigned-offArsenal Scaffold07/18/2019
DOB NOWConstruction FenceSigned-offArsenal Scaffold07/16/2019
BIS—ISSUEDPinnacle Commercial Development06/28/2021
BISOTISSUEDPinnacle Commercial Development01/22/2021
BISSPISSUEDCasino Plumbing & Heating12/15/2020
BISOTISSUEDPinnacle Commercial Development10/02/2020
BISOTISSUEDPinnacle Commercial Development07/15/2020
BISOTISSUEDPinnacle Commercial Development07/15/2020
BIS—ISSUEDPinnacle Commercial Development06/17/2020
BISOTISSUEDPinnacle Commercial Development06/17/2020
BISOTISSUEDPinnacle Commercial Development06/17/2020
BISSPISSUEDA. Automatic Sprinkler03/11/2020
BISPLISSUEDAqua Plumbing & Heating02/27/2020
BIS—ISSUEDPinnacle Commercial Development02/24/2020
BISOTISSUEDPinnacle Commercial Development01/28/2020
BISOTISSUEDPinnacle Commercial Development01/28/2020
BISSPISSUEDPrecision Plumbing Services01/17/2020
BISOTISSUEDPinnacle Commercial Development01/08/2020
BISOTISSUEDPinnacle Commercial Development01/08/2020
BISOTISSUEDPinnacle Commercial Development11/18/2019
BISOTISSUEDPinnacle Commercial Development11/18/2019
BISOTISSUEDPinnacle Commercial Development10/18/2019
BISOTISSUEDPinnacle Commercial Development10/18/2019
BISPLISSUEDVillage P & H NY09/13/2019
BISPLISSUEDVillage P & H NY03/22/2019
+ 27 more permits on file
6 projects · most recent 05/23/2023
General Wiring
FiledStatusContractorScope
05/23/2023CompleteRodel Electrical ContractorsGeneral Wiring
06/08/2021CancelledNycom Electrical1 meters
04/22/2021CompleteNycom ElectricalGeneral Wiring
01/21/2020CompleteTuxedo Electrical Contracting—
08/06/2019CompleteKilo Watt ElectricGeneral Wiring
07/16/2019CompleteNash Electric Services—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
03/07/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/07/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/07/2023Certified Sprinkler - SP - RoughingCertifiedView ↗
10/01/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/30/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/17/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/01/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
05/12/2023Sprinkler SystemsJACOB HAASspecial
04/24/2023Sprinkler SystemsJACOB HAASspecial
03/24/2023Mechanical SystemsJACOB HAASspecial
03/24/2023HVAC and service water heating equipment JACOB HAASenergy_progress
03/24/2023HVAC and service water heating system controls JACOB HAASenergy_progress
03/24/2023Duct leakage testing JACOB HAASenergy_progress
03/24/2023HVAC insulation and sealing JACOB HAASenergy_progress
03/24/2023Maintenance informationJACOB HAASenergy_progress
03/24/2023Shutoff dampersJACOB HAASenergy_progress
03/24/2023FinalJACOB HAASprogress
02/27/2023Shutoff dampersJACOB HAASenergy_progress
02/27/2023Mechanical SystemsJACOB HAASspecial
02/27/2023FinalJACOB HAASprogress
02/27/2023Duct leakage testing JACOB HAASenergy_progress
02/27/2023Maintenance informationJACOB HAASenergy_progress
02/27/2023HVAC insulation and sealing JACOB HAASenergy_progress
02/27/2023HVAC and service water heating equipment JACOB HAASenergy_progress
02/27/2023HVAC and service water heating system controls JACOB HAASenergy_progress
02/03/2023Insulation placement and R valuesJACOB HAASenergy_progress
02/03/2023Sprayed fire-resistant materialsJACOB HAASspecial
02/03/2023Post-installed AnchorsJACOB HAASspecial
02/03/2023Fire-Resistant Penetrations and JointsJACOB HAASspecial
02/03/2023FinalJACOB HAASprogress
02/03/2023Fire-Resistance Rated ConstructionJACOB HAASprogress
02/03/2023Lighting controlsJACOB HAASenergy_progress
Latest 25 of 44.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Acs School CenterEducationFloors 1, 2, Roof
Project M00410904 Alteration · LOC Issued · 01/14/2022
Project M00653253 Alteration · LOC Issued · 01/14/2022
Project M00410866 Alteration · LOC Issued · 01/13/2022
Project M00410990 Alteration · LOC Issued · 01/13/2022
Department of the AgingGovernment / CivicFloors 1, 2, Roof
Project M00338167 Alteration · LOC Issued · 05/07/2020
Project M00338663 Alteration · LOC Issued · 05/07/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 430 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch5
09/03/2026M00537851-I1Request digital key ↗
09/02/2026M00729562-I1Request digital key ↗
08/31/2026M00653253-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
09/04/2026M00452187-I1Request digital key ↗
08/31/2026M00410904-I1Request digital key ↗
08/31/2026M00410904-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
09/05/2026M00338663-I1Request digital key ↗
09/04/2026M00454701-I1Request digital key ↗
09/03/2026M00410866-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/05/2026M00338167-I1Request digital key ↗
08/31/2026M00410990-I1Request digital key ↗
08/31/2026M00410990-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly2
09/04/2026M00337987-P1Request digital key ↗
08/14/2026M00337987-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/05/2026M00184638-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00184636-I1Request digital key ↗
▸Applications & Permits93
▸BISPLAN / WORK APPROVAL APPLICATION46
08/16/2024123406705Open ↗
01/23/2024123406705Open ↗
12/05/2023123406705Open ↗
Showing 3 of 46 on file for this type
▸BISWORK PERMIT APPLICATION36
01/22/2021140981267Open ↗
12/16/2020123668646Open ↗
12/16/2020123668646Open ↗
Showing 3 of 36 on file for this type
▸BISPLACE OF ASSEMBLY7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
01/13/2021123406705Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
11/19/2020140981267Open ↗
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)1
01/22/2021140981267Open ↗
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records1
▸BISVERIFY TAX LOT1
11/18/2021123406705Open ↗
▸Seals & Professional Certifications121
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION34
02/07/2020123182135Open ↗
02/07/2020123182135Open ↗
11/04/2019123492498Open ↗
Showing 3 of 34 on file for this type
▸DOB NOWProgress Inspector Seal & Signature32
09/26/2026M00184638-I1Open ↗
09/02/2026M00410866-I1Open ↗
09/02/2026M00410866-I1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature20
09/05/2026M00184638-I1Open ↗
09/05/2026M00338663-P1Open ↗
09/05/2026M00338663-I1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/25/2026M00410904-I1Open ↗
09/02/2026M00410866-I1Open ↗
09/01/2026M00410904-P2Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
06/17/2019123406670Open ↗
Showing 1 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT8
11/19/2020140981267Open ↗
06/17/2019123406670Open ↗
06/17/2019123406670Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
04/23/2020140894557Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/19/2020140981267Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/19/2020140981267Open ↗
▸Trade Schedules & Equipment21
▸BISEQUIPMENT USE APPLICATION/PERMIT6
02/05/2020123182135Open ↗
04/12/2019123421163Open ↗
Showing 2 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING3
12/22/2020123668646Open ↗
12/14/2020123668646Open ↗
Showing 2 of 3 on file for this type
▸BISEQUIPMENT USE PERMITS3
02/05/2020123182135Open ↗
04/12/2019123421163Open ↗
Showing 2 of 3 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA1
04/02/2021123890174Open ↗
▸BISSPRINKLER SYSTEMS1
01/27/2021123668646Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTANDPIPE SYSTEMS1
01/27/2021123668646Open ↗
▸Safety & Tenant Protection2
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
01/22/2021140981267Open ↗
▸BISSTREET TREE CHECKLIST1
02/25/2020123406705Open ↗
▸Environmental & Asbestos28
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
09/05/2026M00338663-P1Open ↗
09/05/2026M00338663-I1Open ↗
09/05/2026M00338167-I1Open ↗
Showing 3 of 13 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)10
12/14/2020123668646Open ↗
12/11/2020123406705Open ↗
11/19/2020140981267Open ↗
Showing 3 of 10 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance29
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
02/07/2020123182135Open ↗
02/07/2020123182135Open ↗
07/03/2019123406670Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
09/23/2021140981267Open ↗
02/07/2020123182135Open ↗
11/04/2019123492498Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY6
09/23/2021140981267Open ↗
04/22/2021123406670Open ↗
03/15/2021140894557Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.3
08/13/2026M00410990-I1Open ↗
08/13/2026M00410866-I1Open ↗
08/13/2026M00653253-I1Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
04/22/2021123406670Open ↗
03/15/2021140894557Open ↗
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
11/19/2020140981267Open ↗
▸BISINTERIOR LIGHTING POWER1
10/02/2020140894557Open ↗
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY10
09/23/2021140981267Open ↗
04/22/2021123406670Open ↗
04/22/2021123406670Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
10/03/2019123406670Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
10/02/2020140894557Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
10/03/2019123406670Open ↗
▸Approvals, Objections & Sign-offs37
▸BISSCHEDULE A - OCCUPANCY / USE12
08/16/2024123406705Open ↗
01/23/2024123406705Open ↗
03/02/2021123406705Open ↗
Showing 3 of 12 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST11
11/10/2021123890174Open ↗
09/23/2021140981267Open ↗
04/22/2021123406670Open ↗
Showing 3 of 11 on file for this type
▸BISSUPERSEDING LETTER6
12/16/2020123668646Open ↗
12/16/2020123668646Open ↗
03/13/2020123668646Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION2
11/19/2019123406670Open ↗
Showing 1 of 2 on file for this type
▸BISFINAL1
01/27/2021123668646Open ↗
▸Cost, Insurance & Ownership28
▸BISCOST AFFIDAVIT26
11/10/2021123890174Open ↗
09/23/2021140981267Open ↗
09/16/2021123890174Open ↗
Showing 3 of 26 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
04/22/2021123406670Open ↗
02/05/2021123668646Open ↗
▸Filing & Intake Forms35
▸BISEFILING COVER SHEET14
06/17/2019123406670Open ↗
06/17/2019123406670Open ↗
04/22/2019123890174Open ↗
Showing 3 of 14 on file for this type
▸BISADDITIONAL INFORMATION12
06/23/2021123406705Open ↗
02/16/2021123406670Open ↗
02/09/2021123406705Open ↗
Showing 3 of 12 on file for this type
▸BISBOROUGH INTAKE FORM7
02/07/2020123182135Open ↗
11/04/2019123492498Open ↗
07/03/2019123668646Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
11/19/2020140981267Open ↗
04/23/2020140894557Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFIRE SUPP ANSUL APPROVL: FD-FSS1
03/15/2021140894557Open ↗