| Owner | Filings | Most Recent |
|---|---|---|
| MACYS INC BLOOMINGDALES | 215 | 09/22/2026 |
| TRI BOROUGH SCAFFOLDING | 3 | 07/08/2026 |
| B BROS REALTY LIMITED PARTNERSHIP | 4 | 03/22/2026 |
| BLOOMINGDALE'S | 312 | 03/22/2026 |
| THE OWNER OF | 1 | 03/22/2026 |
| TISHMAN SPEAR PROPERTIES | 6 | 03/22/2026 |
| BRIAN PAINTIN CORP | 1 | 03/22/2026 |
| TIGHMAN SPEAR PROPERTIES | 1 | 03/22/2026 |
| TO OWNER OF 749 LEXINGTON | 3 | 03/22/2026 |
| THE OWNER OF 990 3RD AVE | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GEORGE J. XERAKIAS, PE | 3 | 05/28/2026 |
| HC PEC | 3 | 05/05/2026 |
| AVCON ENGINEERING PC | 6 | 04/09/2026 |
| RAUL CABATO, ARCHITECT | 3 | 04/08/2026 |
| ANASTASIO ARCHITECTS | 2 | 03/24/2026 |
| STEFANO MORISI R.A. | 2 | 03/17/2026 |
| ROSINI ENGINEERING, PC | 13 | 01/13/2026 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 6 | 11/04/2025 |
| CALLISONRTKL ARCHITECTS, P.C. | 2 | 10/24/2025 |
| CORNERSTONE ENGINEERS & ARCHITECTUR | 2 | 07/28/2025 |
| HIGHLAND ASSOCIATES | 15 | 07/16/2025 |
| NELSON ARCHITECTURE &INTERIORS, INC | 1 | 06/17/2025 |
| ECHEVERRIA DESIGN GROUP | 2 | 05/29/2025 |
| TRICARICO ARCHITECTURE AND DESIGN | 2 | 03/20/2024 |
| 360 ENGINEERING P.C. | 6 | 01/23/2023 |
| FUTURE MADE ARCHITECTURE, PLLC | 2 | 08/24/2022 |
| SYNC ARCHITECTURE P.C | 2 | 08/19/2022 |
| ARRA ARCHITECTURE | 1 | 07/13/2022 |
| AZ ARCHITECTURE D. P.C. | 1 | 03/24/2022 |
| FISKAA ENGINEERING | 2 | 11/19/2021 |
| MAOARCH ARCHITECTURE, D.P.C. | 2 | 11/16/2021 |
| THOMAS G. HAUCK, JR. | 4 | 10/05/2021 |
| RYAN SOAMES ENGINEERING | 1 | 09/07/2021 |
| UE ARCHITECTURE | 1 | 08/11/2021 |
| ATMOSPHERE DESIGN & ARCH PLLC | 1 | 06/17/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CAESAR BUSTAMANTE, AIA | 34 | 03/21/2026 |
| CODE | 16 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 8 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 7 | 03/21/2026 |
| DAO STUDIOS | 2 | 03/21/2026 |
| JUST ARCHITECTURE | 1 | 03/21/2026 |
| PEROTTO CONSULTING MANAGEMENT | 8 | 03/21/2026 |
| METROPOLIS GROUP INC | 6 | 03/21/2026 |
| Integrated Companies | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J. PHELAN CONSTRUCTION CO | General Contractor | 28 | 09/22/2026 |
| REIKEN CONSTRUCTION MGMT | General Contractor | 28 | 07/08/2026 |
| PJP INSTALLERS INC | General Contractor | 19 | 08/26/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 14 | 09/01/2026 |
| ACM CONSULTING CORP | General Contractor | 10 | 07/08/2026 |
| BUCH CONSTRUCTION, INC | General Contractor | 9 | 03/21/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 9 | 07/08/2026 |
| BIGMAN BROS., INC. | Electrical | 8 | 03/22/2026 |
| WINICK PRODUCTIONS, LLC | General Contractor | 4 | 07/08/2026 |
| TECTONIC BUILDERS INC | General Contractor | 4 | 07/08/2026 |
| ANTHONY LUCIANO | Electrical | 3 | 03/21/2026 |
| PATRICK O'TOOLE | Electrical | 3 | 03/21/2026 |
| HEMNAUTH, SUDESH | Electrical | 2 | 03/21/2026 |
| GEORGE BRESLAW PLBNG LLC | Plumbing | 2 | 07/08/2026 |
| EAGLE SCAFFOLDING SVCS INC | General Contractor | 2 | 03/21/2026 |
| WALTON, MARC | Electrical | 2 | 03/21/2026 |
| MACREDDIN PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| BONARDI, MICHAEL | Electrical | 1 | 03/21/2026 |
| JOSHUA ANDERSON | Electrical | 1 | 03/21/2026 |
| MICHAEL BONARDI | Electrical | 1 | 03/21/2026 |
| SCOTT BIGMAN | Electrical | 1 | 03/21/2026 |
| AGGRESSIVE FIRE PROT LLC | Fire Protection | 1 | 07/08/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 1 | 03/21/2026 |
| TRI BOROUGH SCAFFOLDING | General Contractor | 1 | 07/08/2026 |
| ACM ELECTRIC CORPORATION | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AVCON ENGINEERING PC | 548 | 4 | 04/09/2026 |
| DOMANI INSPECTION SERVICE | 843 | 2 | 03/24/2026 |
| DYO DESIGN OFFICE LLC | 6701 | 2 | 03/17/2026 |
| SKYLINE ENGINEERING, PLLC | 267 | 4 | 01/13/2026 |
| MILROSE CONSULTANTS LLC | 2003 | 27 | 11/04/2025 |
| ROSINI ENGINEERING, PC | 3282 | 8 | 10/29/2025 |
| GREGORY V. PEROTTO, P.E. | 947 | 3 | 03/20/2024 |
| THE EIPEL ENGINEERING GRO | 2714 | 1 | 02/29/2024 |
| 360 ENGINEERING P.C. | 7496 | 3 | 01/23/2023 |
| RICHARD H. BALSER ENGINEE | 3028 | 1 | 07/14/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | J. PHELAN CONSTRUCTION CO | 09/21/2026 |
| DOB NOW | General Construction | Permit Issued | J. PHELAN CONSTRUCTION CO | 09/21/2026 |
| DOB NOW | Sprinklers | Permit Issued | PAR FIRE PROTECTION LLC | 08/31/2026 |
| DOB NOW | Sprinklers | Permit Issued | PAR FIRE PROTECTION LLC | 08/27/2026 |
| DOB NOW | Plumbing | Permit Issued | PAR FIRE PROTECTION LLC | 08/27/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | THE GRENADIER CORP | 08/10/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PJP INSTALLERS INC | 07/21/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | J. PHELAN CONSTRUCTION CO | 07/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | REIKEN CONSTRUCTION MGMT | 06/15/2026 |
| DOB NOW | Standpipe | Permit Issued | GEORGE BRESLAW PLBNG LLC | 06/08/2026 |
| DOB NOW | General Construction | Permit Issued | REIKEN CONSTRUCTION MGMT | 06/03/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | THE GRENADIER CORP | 05/22/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PJP INSTALLERS INC | 05/05/2026 |
| DOB NOW | General Construction | Permit Issued | REIKEN CONSTRUCTION MGMT | 04/02/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | REIKEN CONSTRUCTION MGMT | 04/01/2026 |
| DOB NOW | Structural | Signed-off | REIKEN CONSTRUCTION MGMT | 02/03/2026 |
| DOB NOW | General Construction | Signed-off | REIKEN CONSTRUCTION MGMT | 02/03/2026 |
| DOB NOW | Mechanical Systems | Signed-off | REIKEN CONSTRUCTION MGMT | 02/03/2026 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 01/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | LAWRENCE J. LEVINE | 10/21/2025 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 10/01/2025 |
| DOB NOW | Standpipe | Permit Issued | LAWRENCE J. LEVINE | 09/25/2025 |
| DOB NOW | Sprinklers | Permit Issued | LAWRENCE J. LEVINE | 09/25/2025 |
| DOB NOW | General Construction | Permit Issued | J PHELAN CONSTRUCTION | 09/25/2025 |
| DOB NOW | Structural | Permit Issued | J PHELAN CONSTRUCTION | 09/24/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | TECTONIC BUILDERS INC | 09/18/2025 |
| DOB NOW | General Construction | Permit Issued | TECTONIC BUILDERS INC | 09/10/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | J PHELAN CONSTRUCTION | 08/07/2025 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 08/05/2025 |
| DOB NOW | General Construction | Permit Issued | WINICK PRODUCTIONS, LLC | 07/29/2025 |
| DOB NOW | Mechanical Systems | Signed-off | REIKEN CONSTRUCTION MGMT | 07/18/2025 |
| DOB NOW | Mechanical Systems | Signed-off | J PHELAN CONSTRUCTION | 06/24/2025 |
| DOB NOW | General Construction | Signed-off | J PHELAN CONSTRUCTION | 06/24/2025 |
| DOB NOW | General Construction | Signed-off | REIKEN CONSTRUCTION MGMT | 06/11/2025 |
| DOB NOW | Sprinklers | Signed-off | AGGRESSIVE FIRE PROT LLC | 04/23/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | THE GRENADIER CORP | 04/17/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PJP INSTALLERS INC | 04/03/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 04/03/2025 |
| DOB NOW | General Construction | Signed-off | J PHELAN CONSTRUCTION | 03/31/2025 |
| DOB NOW | Mechanical Systems | Signed-off | REIKEN CONSTRUCTION MGMT | 03/27/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/20/2024 | Permit Issued | BUCH CONSTRUCTION, INC | Others | Other __Junk__ NA - Field Built Ductwork 1 CFM · Ductwork ×2 |
| 02/12/2021 | — | — | Associated Ducts and Piping | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2026 | Permit Issued | PAR FIRE PROTECTION LLC | 4 heads |
| 10/29/2025 | Signed-off | PAR FIRE PROTECTION LLC | 12 heads |
| 06/17/2025 | Permit Issued | PAR FIRE PROTECTION LLC | 30 heads |
| 05/23/2025 | Permit Issued | PAR FIRE PROTECTION LLC | 1,307 heads, 1 outlets |
| 04/18/2024 | Signed-off | PAR FIRE PROTECTION LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/29/2025 | — | — | — |
| 05/23/2025 | Permit Issued | GEORGE BRESLAW PLBNG LLC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/28/2026 | Complete | BLOOMINGDALES | — |
| 09/28/2026 | Complete | BLOOMINGDALES | — |
| 09/22/2026 | Complete | BLOOMINGDALES | — |
| 09/22/2026 | Complete | BLOOMINGDALES | — |
| 09/15/2026 | Complete | BLOOMINGDALES | — |
| 09/15/2026 | Complete | BLOOMINGDALES | — |
| 09/10/2026 | Complete | BLOOMINGDALES | — |
| 09/01/2026 | Complete | BLOOMINGDALES | — |
| 09/01/2026 | Complete | BLOOMINGDALES | — |
| 08/24/2026 | Complete | BLOOMINGDALES | — |
| 08/24/2026 | Complete | BLOOMINGDALES | — |
| 08/17/2026 | Complete | BLOOMINGDALES | — |
| 08/17/2026 | Complete | BLOOMINGDALES | — |
| 08/10/2026 | Complete | BLOOMINGDALES | — |
| 08/10/2026 | Complete | BLOOMINGDALES | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/04/2025 | Signed-off | REIKEN CONSTRUCTION MGMT | Steel |
| 05/21/2025 | Permit Issued | J. PHELAN CONSTRUCTION CO | Steel, Concrete |
| 02/29/2024 | Permit Issued | BUCH CONSTRUCTION, INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2026 | Permit Issued | PJP INSTALLERS INC | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | THE GRENADIER CORP | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/06/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/14/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/07/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/09/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/13/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/08/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/05/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/24/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/20/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/13/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/10/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 07/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/18/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/27/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/21/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/22/2026 | Alternative Materials - OTCR Buildings Bulletin Number | George Xerakias | special |
| 03/25/2026 | Mechanical Systems | Ella Malkin | special |
| 03/25/2026 | Sprinkler Systems | Ella Malkin | special |
| 03/25/2026 | Final | Ella Malkin | progress |
| 03/23/2026 | Final | Raul Cabato | progress |
| 03/17/2026 | Fire-Resistant Penetrations and Joints | stefano morisi | special |
| 03/16/2026 | Final | — | progress |
| 03/16/2026 | Lighting controls | JOHN MCMONAGLE | energy_progress |
| 03/11/2026 | Mechanical Systems | JOHN MCMONAGLE | special |
| 03/11/2026 | Final | JOHN MCMONAGLE | progress |
| 03/11/2026 | Final | JOHN MCMONAGLE | progress |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 03/11/2026 | Interior lighting power | JOHN MCMONAGLE | energy_progress |
| 10/30/2025 | Sprinkler Systems | David Rosini | special |
| 10/14/2025 | Post-installed Anchors | Christopher Drutjons | special |
| 10/14/2025 | Final | Christopher Drutjons | progress |
| 10/14/2025 | Structural Steel - Welding | Christopher Drutjons | special |
| 10/14/2025 | Structural Steel - High Strength Bolting | Christopher Drutjons | special |
| 10/14/2025 | Structural Steel - Details | Christopher Drutjons | special |
| 10/14/2025 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 10/14/2025 | Structural Cold-Formed Steel | Christopher Drutjons | special |
| 10/06/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 10/06/2025 | Lighting controls | Christopher Drutjons | energy_progress |
| 10/06/2025 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 10/06/2025 | Final | Christopher Drutjons | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| bloomingdale's | Retail | Floors 4, 5 | Project M01108992 |