← Back
BuildNYC
Public elementary, junior or senior high
M.S. 145
1000 TELLER AVENUE · BIN 2097111
💬 Discuss this project
1964Year Built
4Stories
W1Building Class
R7-1Zoning
167,875 sfGross Floor Area
1Units
LL97 Covered9 Active Violations 0 unresolved · 9 paperwork only 3 likely answered ▸
Public elementary, junior or senior high · Owner of record: NYC Department of Parks and Recreation · 150,000 sf lot · 1.12 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofI.S. X145Under Construction2p · 1 filing · 20 docs
Floor 3Drinking fountain replacement in path of travel to room 343Under Construction6p · 2 filings · 20 docs
Floor 2
Floor 1I.S. X145Under Construction30p · 2 filings · 20 docs
Site & exteriorI.S. 328X (I.S. 145 Arturo Toscanini)22p · 3 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority17507/08/2026
NYC Department of Education403/22/2026
National Grid103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Precision 3Sixty NYC2003/21/2026
Dseny Engineering Services603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
WDFGeneral Contractor507/08/2026
Empire Control Abatementspecialty_contractor507/08/2026
Adam's European ContractingGeneral Contractor507/08/2026
ACS System AssociatesGeneral Contractor407/08/2026
Akm Construction Service*Scaffold403/21/2026
WDFPlumbing307/08/2026
I.M.P. Plumbing & HeatingPlumbing307/08/2026
Forsythe P&HPlumbing207/08/2026
A & S ElectricElectrical103/21/2026
Charan Electrical Enterp'sElectrical103/22/2026
Prince ElectricElectrical103/21/2026
Anco Electl ContctngElectrical103/21/2026
Everlast ScaffoldingScaffold107/08/2026
Kew ElectricElectrical103/21/2026
KLK ElectricElectrical103/21/2026
Charan Electrical Enterp'sElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Twin Peaks317707/30/2025
Future Tech Consultants O589706/06/2025
Socotec Engineering4983103/07/2024
Building Lifecycle
All (138)Filed (23)Permit Issued (25)Signed Off (3)Violation (60)Objection (18)Special Inspection (9)
04/30/2026
Permit issued — Mechanical Systems
X00985933-S1-MS
03/25/2026
Violation issued (ECB, open)
Construction
03/25/2026
Violation issued (ECB, open)
Construction
03/16/2026
Permit issued — Plumbing
X00985933-S2-PL
02/04/2026
Permit issued — Plumbing
X00985933-S2-PL
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/13/2025
Permit issued — General Construction
X00505019-S1-GC
11/13/2025
Permit issued — Plumbing
X00505019-I1-PL
10/14/2025
Permit issued — General Construction
X00985933-I1-GC
09/30/2025
Permit issued — General Construction
X01016225-I1-GC
08/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
07/30/2025
Filed — Alteration
X145_REPLACE EXISTING DRINKING FOUNTAIN IN THE PATH OF TRAVEL TO ROOM 343. NO CHANGE INUSE,EGRESS OR OCCUPANCY.
X00505019-P3
07/28/2025
Permit issued — Structural
X00985933-S3-ST
07/05/2025
Violation issued (ECB, open)
Construction
07/05/2025
Violation issued (ECB, open)
Construction
06/06/2025
Filed — Alteration
EXTEND EXISTING CONCRETE PLATFORM AT MAIN ENTRANCE AND BUILD NEW OUTDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS AT ACCESSIBLE MAIN ENTRANCE. NEW DOOR AND HARDWARE. NEW INDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS.
X01016225-P3
04/30/2025
Special inspection requirement — Concrete - Cast-In-Place
Noel Tolentino
04/07/2025
Permit issued — Mechanical Systems
X00985933-S1-MS
03/24/2025
Filed — Alteration
Installation of new beams.
X00985933-P2
03/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Noel Tolentino
03/21/2025
Special inspection requirement — Fire-Resistance Rated Construction
Michael Marchese
03/12/2025
Signed off — Alteration
FN/IS328X - FOR TEMPORARY CONSTRUCTION EQUIPMENT(FENCE) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB NUMBER 201204008 NO CHANGE IN USE, OCCUPANCY OR EGRESS
X00535282-I1
03/05/2025
Permit issued — General Construction
X00467024-S1-GC
02/11/2025
Permit issued — Plumbing
X00985933-S2-PL
12/09/2024
Permit issued — Mechanical Systems
X00985933-S1-MS
11/08/2024
Filed — Alteration
EXTEND EXISTING CONCRETE PLATFORM AT MAIN ENTRANCE AND BUILD NEW OUTDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS AT ACCESSIBLE MAIN ENTRANCE. NEW DOOR AND HARDWARE. NEW INDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS.
X01016225-P2
10/22/2024
Signed off — Alteration
SF/IS328X - FOR TEMPORARY CONSTRUCTION EQUIPMENT(SCAFFOLD) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB NUMBER 201204008 NO CHANGE IN USE, OCCUPANCY OR EGRESS
X00535291-I1
10/09/2024
Permit issued — General Construction
X00985933-I1-GC
10/03/2024
Filed — Alteration
Installation of new beams.
X00985933-S3
09/17/2024
Filed — Alteration
Installation of new beams.
X00985933-P1
09/03/2024
Permit issued — General Construction
X01016225-I1-GC
08/28/2024
Objection resolved — Addressed
08/28/2024
Objection resolved — Addressed
08/22/2024
Filed — Alteration
EXTEND EXISTING CONCRETE PLATFORM AT MAIN ENTRANCE AND BUILD NEW OUTDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS AT ACCESSIBLE MAIN ENTRANCE. NEW DOOR AND HARDWARE. NEW INDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS.
X01016225-P1
08/21/2024
Objection resolved — Addressed
08/07/2024
Objection raised — Other
08/07/2024
Objection raised — Other
08/07/2024
Objection raised — Other
07/31/2024
Filed — Alteration
Installation of new beams.
X00985933-S2
07/31/2024
Filed — Alteration
Installation of new beams.
X00985933-S1
07/29/2024
Filed — Alteration
Installation of new beams.
X00985933-I1
07/17/2024
Objection resolved — Addressed
07/16/2024
Violation issued (ECB, open)
Construction
07/16/2024
Violation issued (ECB, closed)
Construction
07/16/2024
Violation issued (ECB, closed)
Construction
06/20/2024
Permit issued — General Construction
X00467024-S1-GC
03/19/2024
Objection raised — Other
03/07/2024
Filed — Alteration
EXTEND EXISTING CONCRETE PLATFORM AT MAIN ENTRANCE AND BUILD NEW OUTDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS AT ACCESSIBLE MAIN ENTRANCE. NEW DOOR AND HARDWARE. NEW INDOOR CONCRETE ADA-COMPLIANT RAMP WITH GUARDRAILS AND HANDRAILS.
X01016225-I1
01/11/2024
Signed off — Alteration
X00535288-I1
10/02/2023
Objection resolved — Addressed
09/25/2023
Objection raised — Other
09/22/2023
Filed — Alteration
X145_ Replacement of existing drinking fountain located on the third floor.
X00467024-P3
09/01/2023
Permit issued — General Construction
X00505019-S1-GC
06/22/2023
Permit issued — General Construction
X00467024-S1-GC
06/21/2023
Permit issued — Construction Fence
X00535282-I1-FN
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 138 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedACS System Associates04/30/2026
DOB NOWPlumbingPermit IssuedI.M.P. Plumbing & Heating03/16/2026
DOB NOWPlumbingPermit IssuedI.M.P. Plumbing & Heating02/04/2026
DOB NOWGeneral ConstructionPermit IssuedWDF11/13/2025
DOB NOWPlumbingPermit IssuedWDF11/13/2025
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement10/14/2025
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement09/30/2025
DOB NOWStructuralPermit IssuedEmpire Control Abatement07/28/2025
DOB NOWMechanical SystemsPermit IssuedACS System Associates04/07/2025
DOB NOWGeneral ConstructionPermit IssuedAdam's European Contracting03/05/2025
DOB NOWPlumbingPermit IssuedI.M.P. Plumbing & Heating02/11/2025
DOB NOWMechanical SystemsPermit IssuedACS System Associates12/09/2024
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement10/09/2024
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement09/03/2024
DOB NOWGeneral ConstructionPermit IssuedAdam's European Contracting06/20/2024
DOB NOWGeneral ConstructionPermit IssuedWDF09/01/2023
DOB NOWGeneral ConstructionPermit IssuedAdam's European Contracting06/22/2023
DOB NOWConstruction FenceSigned-offAkm Construction Service*06/21/2023
DOB NOWPlumbingPermit IssuedForsythe P&H04/24/2023
DOB NOWPlumbingPermit IssuedWDF04/06/2023
DOB NOWPlumbingPermit IssuedWDF09/13/2022
DOB NOWGeneral ConstructionPermit IssuedWDF08/31/2022
DOB NOWPlumbingPermit IssuedForsythe P&H05/19/2022
DOB NOWSupported ScaffoldSigned-offEverlast Scaffolding07/15/2021
DOB NOWConstruction FenceSigned-offAkm Construction Service*07/01/2021
BISOTISSUEDAkm Construction Service*02/06/2026
BISOTISSUEDAdam's European Contracting03/14/2025
BISOTISSUEDAdam's European Contracting03/14/2025
BISOTISSUEDAdam's European Contracting03/14/2025
BISOTISSUEDAdam's European Contracting03/14/2025
BISOTISSUEDAkm Construction Service*02/18/2025
BISOTISSUEDAkm Construction Service*01/13/2025
BISPLISSUEDVarsity Plumbing and Heating07/23/2024
BISOTISSUEDAdam's European Contracting03/08/2024
BISOTISSUEDAdam's European Contracting03/08/2024
BISOTISSUEDAdam's European Contracting03/08/2024
BISOTISSUEDAdam's European Contracting03/08/2024
BISPLISSUEDVarsity Plumbing and Heating07/18/2023
BISOTISSUEDAdam's European Contracting03/16/2023
BISOTISSUEDAdam's European Contracting03/16/2023
+ 35 more permits on file
1 project · most recent 03/24/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
03/24/2025Permit IssuedACS System AssociatesHeating and Air Conditioning Systems
Heat / Cool
Daikin RXYQ98AATJA 95,200 BTU · Vrf Outdoor ×1
3 projects · most recent 07/30/2025
Water/Sanitary
FiledStatusContractorScope
07/30/2025Permit IssuedWDFWater/Sanitary
03/24/2025Permit IssuedI.M.P. Plumbing & HeatingWater/Sanitary
09/22/2023Permit IssuedForsythe P&HWater/Sanitary
21 projects · most recent 07/13/2026
General Wiring Lighting
FiledStatusContractorScope
07/13/2026Permit IssuedJamcob ElectricLighting
06/02/2025CompleteAnco Electl Contctng—
04/17/2025Permit IssuedKLK ElectricGeneral Wiring
02/05/2025CompleteAnco Electl Contctng—
10/02/2023CompleteAnco Electl ContctngGeneral Wiring
08/01/2023CompleteAnco Electl Contctng—
06/26/2023CompleteCharan Electrical Enterp'sGeneral Wiring
06/05/2023CompleteAnco Electl Contctng—
05/03/2023CompleteAnco Electl Contctng—
09/13/2022CompleteA.T.J. Electrical Co—
08/24/2022CompleteA.T.J. Electrical Co—
07/14/2022CompleteUrban ElectricalGeneral Wiring
05/26/2022CompleteCharan Electrical Enterp's—
08/05/2021CompleteMechanical Electr'lGeneral Wiring
07/02/2021CompleteP & M Elect'l ContractingGeneral Wiring
1 project · most recent 03/24/2025
Steel
FiledStatusContractorScope
03/24/2025Permit IssuedACS System AssociatesSteel
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
08/05/2025Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
04/30/2025Concrete - Cast-In-PlaceNoel Tolentinospecial
03/21/2025Fire-Resistant Penetrations and JointsNoel Tolentinospecial
03/21/2025Fire-Resistance Rated ConstructionMichael Marcheseprogress
06/07/2023Fire-Resistance Rated ConstructionMIKHAIL ZEYGMANprogress
06/05/2023Fire-Resistance Rated ConstructionMIKHAIL ZEYGMANprogress
09/02/2022Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
08/25/2022Fire-Resistance Rated ConstructionMIKHAIL ZEYGMANprogress
08/18/2022Fire-Resistance Rated ConstructionMIKHAIL ZEYGMANprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
I.S. X145EducationFloor 1, Roof
Project X00985933 Alteration · Permit Entire · 07/29/2024
Project X01016225 Alteration · Permit Entire · 03/07/2024
I.S. 328X (I.S. 145 Arturo Toscanini)Education—
Project X00535282 Alteration · LOC Issued · 06/08/2021
Project X00535288 Alteration · LOC Issued · 06/08/2021
Project X00535291 Alteration · LOC Issued · 06/08/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 215 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch20
08/25/2026X00535288-I1Request digital key ↗
08/24/2026X00505019-P2Request digital key ↗
08/24/2026X00505019-P1Request digital key ↗
Showing 3 of 20 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
08/15/2026X00467024-P1Request digital key ↗
08/14/2026X00467024-P3Request digital key ↗
08/14/2026X00467024-I1Request digital key ↗
▸Applications & Permits15
▸BISWORK PERMIT APPLICATION8
10/12/2017220516671Open ↗
09/26/2017220516671Open ↗
01/04/2017220516671Open ↗
Showing 3 of 8 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION7
01/09/2025201195330Open ↗
12/10/2024201195321Open ↗
11/13/2020220516662Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications48
▸DOB NOWDPL-1: Design Professional Seal & Signature23
08/25/2026X00535291-I1Open ↗
08/25/2026X00535288-I1Open ↗
08/24/2026X00505019-P2Open ↗
Showing 3 of 23 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
12/04/2017220516671Open ↗
12/01/2017220516671Open ↗
11/13/2017220516671Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
10/05/2026X00505019-P1Open ↗
09/12/2026X00985933-P2Open ↗
08/31/2026X00467024-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/12/2026X00985933-P2Open ↗
08/29/2026X00505019-I1Open ↗
08/25/2026X01016225-P3Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
02/12/2016220516671Open ↗
02/12/2016220516671Open ↗
02/12/2016220516671Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
02/12/2016220516671Open ↗
▸Trade Schedules & Equipment7
▸BISEQUIPMENT USE PERMITS4
01/19/2018220516671Open ↗
01/19/2018220516671Open ↗
01/19/2018220516671Open ↗
Showing 3 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA1
10/23/2017220517938Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
01/19/2018220516671Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
02/12/2016220516671Open ↗
▸Safety & Tenant Protection3
▸DOB NOWNYCSCA - Approved Site Safety Plans3
08/13/2026X00535291-I1Open ↗
08/13/2026X00535288-I1Open ↗
08/13/2026X00535282-I1Open ↗
▸Environmental & Asbestos18
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/24/2026X00505019-S1Open ↗
08/24/2026X00505019-I1Open ↗
08/24/2026X00505019-P2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/19/2026X00985933-S3Open ↗
08/19/2026X00985933-S1Open ↗
08/19/2026X00985933-I1Open ↗
Showing 3 of 5 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM2
12/04/2017220516671Open ↗
10/23/2017220517938Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
12/04/2017220516671Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
12/04/2017220516671Open ↗
12/16/2016220516671Open ↗
12/16/2016220516671Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS1
12/04/2017220516671Open ↗
▸Approvals, Objections & Sign-offs54
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)23
08/24/2026X00505019-I1Open ↗
08/24/2026X00505019-S1Open ↗
08/24/2026X00505019-P2Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter23
08/25/2026X00535288-I1Open ↗
08/24/2026X00505019-P2Open ↗
08/24/2026X00505019-S1Open ↗
Showing 3 of 23 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
01/19/2018220516671Open ↗
12/04/2017220516671Open ↗
12/04/2017220516671Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP Variance (V5) letter1
08/13/2026X00985933-S3Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)1
08/13/2026X00535282-I1Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
12/04/2017220516671Open ↗
10/23/2017220517938Open ↗
02/26/2016220517938Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms13
▸BISBOROUGH INTAKE FORM5
01/19/2018220516671Open ↗
12/04/2017220516671Open ↗
12/04/2017220516671Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
02/26/2016220517938Open ↗
02/12/2016220516671Open ↗
02/12/2016220516671Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION2
04/18/2017220516671Open ↗
12/16/2016220516671Open ↗
▸DOB NOWAI1 Form2
08/13/2026X00505019-S1Open ↗
08/13/2026X00467024-S1Open ↗
▸Other Documents25
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal23
08/24/2026X00505019-S1Open ↗
08/24/2026X00505019-I1Open ↗
08/20/2026X01016225-I1Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWNYCSCA Exhibit 22
08/13/2026X00535282-I1Open ↗
08/13/2026X00535288-I1Open ↗