← Back
Three families
1001 LORIMER STREET
BROOKLYN · BIN 3065542
💬 Discuss this project
1899Year Built
3Stories
C0Building Class
R6BZoning
3,000 sfGross Floor Area
3Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Three families · Owner of record: THIRDWAVE CORP., FICTITIOUS NAME, THIRDW AVE JAPAN · 2,500 sf lot · 1.2 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionLandscapeCivil
Roof7p · 1 filing · 20 docs
Floor 310p · 1 filing · 20 docs
Floor 27p · 1 filing · 20 docs
Floor 14p · 1 filing · 20 docs
Cellar14p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TOPLINE NYC CONTRACTING507/08/2026
GW EQUITIES2907/08/2026
THIRDWAVE CORP., FICTITIOUS NAME, THIRDW AVE JAPAN103/22/2026
AMERICAN BUILDERS GROUP203/22/2026
GW LORIMER PROJECT LLC203/22/2026
BRUKLYN BUILDERS403/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/17/2025$5.9M—GW LORIMER PROJECT LLC → THIRDWAVE CORP., FICTITIOUS NAME, THIRDWAVE JAPAN$1,967/sf building
05/03/2021$2.1M—Private party → GW LORIMER PROJECT LLC$700/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAOBAB ARCHITECTS P.C.811/13/2023
MOHAMMAD AHEAD, PE204/20/2022
CHOSEN MEP, CORP.107/22/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ELLIPSES DESIGN503/21/2026
BMG GROUP USA403/21/2026
ADVANCED BUILDERS SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BERKOWITS REALTY LLCGeneral Contractor603/21/2026
MPI PLUMBING CORPPlumbing507/08/2026
AMERICAN BUILDERS GROUPGeneral Contractor407/08/2026
TOPLINE NYC CONTRACTINGGeneral Contractor407/08/2026
YG SERVICESGeneral Contractor303/22/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616311/13/2023
AR-TECH ENGINEERING, P.C.6659207/26/2022
SHAHRISH SHUVO ENGINEERIN8524104/15/2021
Building Lifecycle
All (113)Filed (11)Permit Issued (8)Signed Off (4)Violation (35)Inspection (9)Objection (16)Special Inspection (30)
03/11/2024
Signed off — Alteration
SPRINKLER APPLICATION HEREBY FILED IN CONJUNTION TO JOB # B00501030-I1.
B00501030-I1
03/07/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/20/2024
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/11/2024
Permit issued — General Construction
B00501030-I1-MS
01/11/2024
Permit issued — General Construction
B00501030-I1-ST
01/11/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Shahrish Shuvo
01/11/2024
Special inspection requirement — Interior lighting power
Shahrish Shuvo
01/11/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
01/11/2024
Special inspection requirement — Structural Cold-Formed Steel
Shahrish Shuvo
01/11/2024
Special inspection requirement — HVAC-R and service water heating system controls
Shahrish Shuvo
01/11/2024
Special inspection requirement — Mechanical Systems
Shahrish Shuvo
01/11/2024
Special inspection requirement — Metering
Shahrish Shuvo
01/11/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Shahrish Shuvo
01/11/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Shahrish Shuvo
01/11/2024
Special inspection requirement — Heating Systems
Shahrish Shuvo
01/11/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
01/11/2024
Special inspection requirement — Final
Shahrish Shuvo
01/11/2024
Special inspection requirement — HVAC-R and service water heating equipment
Shahrish Shuvo
01/11/2024
Special inspection requirement — Air barrier - visual inspection
Shahrish Shuvo
01/11/2024
Special inspection requirement — Lighting controls
Shahrish Shuvo
01/11/2024
Special inspection requirement — Ventilation and air distribution system
Shahrish Shuvo
01/11/2024
Special inspection requirement — Lighting in dwelling units
Shahrish Shuvo
01/11/2024
Special inspection requirement — Maintenance information
Shahrish Shuvo
01/11/2024
Special inspection requirement — Air barrier — testing
Shahrish Shuvo
01/11/2024
Special inspection requirement — Fenestration air leakage
Shahrish Shuvo
01/11/2024
Special inspection requirement — Insulation placement and R values
Shahrish Shuvo
01/11/2024
Special inspection requirement — Permanent certificate
Shahrish Shuvo
01/04/2024
Objection resolved — Addressed
11/27/2023
Objection raised — Other
11/21/2023
Violation issued (HPD, closed)
I
11/20/2023
Signed off — Alteration
SPRINKLER APPLICATION HEREBY FILED IN CONJUNTION TO JOB # B00501030-I1.
B00501030-S2
11/20/2023
Objection resolved — Addressed
11/20/2023
Objection resolved — Addressed
11/16/2023
Objection raised — Other
11/16/2023
Objection raised — Other
11/13/2023
Filed — Alteration
SPRINKLER APPLICATION HEREBY FILED IN CONJUNTION TO JOB # B00501030-I1.
B00501030-P4
11/02/2023
Filed — Alteration
SPRINKLER APPLICATION HEREBY FILED IN CONJUNTION TO JOB # B00501030-I1.
B00501030-P6
09/05/2023
Inspection — Pass-Final SP Permit Withdrawal
Pass
View inspection ↗
08/29/2023
Violation issued (ECB, closed)
Construction
07/20/2023
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00721090-I1
07/20/2023
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00721093-I1
07/01/2023
Permit issued — Plumbing
B00501030-S2-PL
06/23/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
06/23/2023
Special inspection requirement — Structural Cold-Formed Steel
FAHAD FATEH
06/23/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
06/23/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
06/23/2023
Special inspection requirement — Heating Systems
FAHAD FATEH
06/23/2023
Special inspection requirement — Mechanical Systems
FAHAD FATEH
06/23/2023
Special inspection requirement — Final
JAMES MOORE
06/23/2023
Special inspection requirement — Lighting controls
FAHAD FATEH
06/21/2023
Objection resolved — Addressed
06/20/2023
Objection raised — Other
06/19/2023
Filed — Alteration
SPRINKLER APPLICATION HEREBY FILED IN CONJUNTION TO JOB # B00501030-I1.
B00501030-P3
06/19/2023
Objection resolved — Addressed
06/15/2023
Filed — Alteration
SPRINKLER APPLICATION HEREBY FILED IN CONJUNTION TO JOB # B00501030-I1.
B00501030-P5
06/15/2023
Objection raised — Scope
05/29/2023
Violation issued (ECB, closed)
Construction
05/29/2023
Violation issued (ECB, closed)
Construction
04/28/2023
Permit issued — General Construction
B00501030-I1-GC
04/14/2023
Violation issued (ECB, closed)
Construction
Latest 60 of 113 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offBERKOWITS REALTY LLC01/11/2024
DOB NOWGeneral ConstructionSigned-offBERKOWITS REALTY LLC01/11/2024
DOB NOWPlumbingSigned-offYG SERVICES INC07/01/2023
DOB NOWGeneral ConstructionSigned-offAMERICAN BUILDERS GROUP04/28/2023
DOB NOWSupported ScaffoldSigned-offTOPLINE NYC CONTRACTING11/21/2022
DOB NOWPlumbingSigned-offYG SERVICES INC06/30/2022
DOB NOWSidewalk ShedSigned-offTOPLINE NYC CONTRACTING04/21/2022
DOB NOWSprinklersPermit IssuedA M B MECHANICAL INC03/28/2022
1 job · most recent 11/13/2023
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/13/2023Signed-offBERKOWITS REALTY LLCAir Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
American Standard SILVER 13 48,000 BTU · Condensing Unit ×12
Goodman Goodman- GSX130601 48,000 BTU · Condensing Unit ×3
Heating
American Standard Silver S9X1 60,000 BTU · Furnace ×12
Goodman Goodman- GSX130601 60,000 BTU · Furnace ×3
Ventilation
Greenheck SQ-97-VG 100 CFM · Exhaust Fan ×13
Ducts & Piping
American Standard AMERICAN STANDARD 1 CFM · Ductwork ×1
1 job · most recent 11/13/2023
Sprinkler System
FiledStatusContractorScope
11/13/2023Permit IssuedPRIME PIPING & HEATING INSprinkler System
1 job · most recent 11/13/2023
Gas Storm Water/Sanitary
FiledStatusContractorScope
11/13/2023Signed-offYG SERVICES INCGas, Storm, Water/Sanitary
2 jobs · most recent 08/14/2023
General Wiring
FiledStatusContractorScope
08/14/2023CompleteS&R ELECTRICAL & MECHANICGeneral Wiring
04/19/2022CompleteRICHARD NEU—
1 job · most recent 11/13/2023
Wood
FiledStatusContractorScope
11/13/2023Signed-offBERKOWITS REALTY LLCWood
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
03/07/2024Pass-Final General Construction Non-Directive 14PassView ↗
02/20/2024Fail-Final General Construction Non-Directive 14FailView ↗
09/05/2023Pass-Final SP Permit WithdrawalPassView ↗
09/02/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/02/2022Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
07/15/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/15/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/13/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/16/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 92
DateRequirementInspectorRole
01/11/2024Exterior Insulation and Finish Systems (EIFS)Shahrish Shuvospecial
01/11/2024Structural Cold-Formed SteelShahrish Shuvospecial
01/11/2024Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
01/11/2024Fire-Resistant Penetrations and JointsShahrish Shuvospecial
01/11/2024Heating SystemsShahrish Shuvospecial
01/11/2024Mechanical SystemsShahrish Shuvospecial
01/11/2024FinalShahrish Shuvoprogress
01/11/2024MeteringShahrish Shuvoenergy_progress
01/11/2024Fenestration and door U-factor and product ratingsShahrish Shuvoenergy_progress
01/11/2024HVAC-R and service water piping design and insulationShahrish Shuvoenergy_progress
01/11/2024Permanent certificateShahrish Shuvoenergy_progress
01/11/2024Interior lighting powerShahrish Shuvoenergy_progress
01/11/2024Air barrier - visual inspectionShahrish Shuvoenergy_progress
01/11/2024HVAC-R and service water heating system controlsShahrish Shuvoenergy_progress
01/11/2024HVAC-R and service water heating equipmentShahrish Shuvoenergy_progress
01/11/2024Lighting controlsShahrish Shuvoenergy_progress
01/11/2024Ventilation and air distribution systemShahrish Shuvoenergy_progress
01/11/2024Lighting in dwelling unitsShahrish Shuvoenergy_progress
01/11/2024Maintenance informationShahrish Shuvoenergy_progress
01/11/2024Air barrier — testing Shahrish Shuvoenergy_progress
01/11/2024Fenestration air leakageShahrish Shuvoenergy_progress
01/11/2024Insulation placement and R valuesShahrish Shuvoenergy_progress
06/23/2023Structural Cold-Formed SteelFAHAD FATEHspecial
06/23/2023Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
06/23/2023Heating SystemsFAHAD FATEHspecial
Latest 25 of 92.
▾Documents — 102 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
09/01/2026B00501030-P6Request digital key ↗
09/01/2026B00501030-S1Request digital key ↗
09/01/2026B00501030-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸Seals & Professional Certifications85
▸DOB NOWProgress Inspector Seal & Signature51
09/30/2026B00501030-P4Open ↗
09/30/2026B00501030-P4Open ↗
09/30/2026B00501030-P4Open ↗
Showing 3 of 51 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature23
09/30/2026B00501030-P4Open ↗
09/30/2026B00501030-P4Open ↗
09/30/2026B00501030-P4Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
09/01/2026B00501030-P6Open ↗
09/01/2026B00501030-P5Open ↗
09/01/2026B00501030-P4Open ↗
Showing 3 of 11 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
09/01/2026B00501030-P6Open ↗
09/01/2026B00501030-S2Open ↗
09/01/2026B00501030-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
09/01/2026B00501030-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00501030-I1Open ↗