1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
General warehouse · Owner of record: BEIGE VAN WYCK LLC · 41,939 sf lot · 0.82 FAR built · Flood zone X
Locations of Work
MechanicalPlumbingFire Protection
Roof3p · 2 filings · 20 docs
Floor 12p · 1 filing · 20 docs
Cellar1p · 1 filing · 11 docs
Basement3p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BEIGE VAN WYCK LLC103/22/2026
SANYO S CONSTRUCTION203/21/2026
YASH B CONSTRUCTION203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HIGH POINT ENGINEERING107/30/2026
TROLYDIA ENGINEERING PLLC908/28/2025
YAKER ENGINEERING, P.C.106/01/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J. CALIENDO R.A., P.C.903/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RFP CONSTRUCTION INCGeneral Contractor303/21/2026
GENMAR ELECT. CONT'G CORPElectrical103/22/2026
ROOPCHAND SINGHElectrical103/21/2026
PRACTICAL PLBG & HTG INCFire Protection107/08/2026
AMSCOAIR LLCGeneral Contractor107/08/2026
PRACTICAL PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TROLYDIA TESTING & INSPEC4422408/28/2025
Building Lifecycle
All (63)Filed (11)Permit Issued (4)Signed Off (3)Violation (8)Inspection (7)Special Inspection (30)
07/30/2026
Filed — Alteration
INSTALLATION OF (1) 1,000 GAL. WASTE OIL, (1) 275 GAL. ANTIFREEZE & (1) 1,500 GAL. COMPARTMENT (750 GAL. OW16 MOTOR OIL/ 750 GAL. OW20 MOTOR OIL) ABOVEGROUND STORAGE TANKS WITH ASSOCIATED PIPING. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01423528-I1
06/26/2026
Special inspection requirement — Final
04/13/2026
Signed off — Alteration
Application is being filed for 8' inch high construction fence.
Q00883445-I1
02/02/2026
Violation issued (ECB, open)
Construction
08/28/2025
Filed — Alteration
Q00875899-P2
08/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
JAIME MOYA
08/28/2025
Special inspection requirement — Lighting in dwelling units
JAIME MOYA
08/28/2025
Special inspection requirement — Exterior lighting power
JAIME MOYA
08/28/2025
Special inspection requirement — Permanent certificate
JAIME MOYA
08/28/2025
Special inspection requirement — Duct leakage testing, insulation and design
JAIME MOYA
08/28/2025
Special inspection requirement — Interior lighting power
JAIME MOYA
08/28/2025
Special inspection requirement — Ventilation and air distribution system
JAIME MOYA
08/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
JAIME MOYA
08/28/2025
Special inspection requirement — Shutoff dampers
JAIME MOYA
08/28/2025
Special inspection requirement — Lighting controls
JAIME MOYA
08/28/2025
Special inspection requirement — Maintenance information
JAIME MOYA
08/28/2025
Special inspection requirement — Fireplaces
JAIME MOYA
08/28/2025
Special inspection requirement — Metering
JAIME MOYA
08/28/2025
Special inspection requirement — Electrical motors and elevators
JAIME MOYA
08/28/2025
Special inspection requirement — Final
JAIME MOYA
08/28/2025
Special inspection requirement — Mechanical Systems
JAIME MOYA
08/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
JAIME MOYA
07/03/2025
Special inspection requirement — Shutoff dampers
JAIME MOYA
07/03/2025
Special inspection requirement — Final
JAIME MOYA
07/03/2025
Special inspection requirement — Ventilation and air distribution system
JAIME MOYA
07/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
JAIME MOYA
07/03/2025
Special inspection requirement — Lighting in dwelling units
JAIME MOYA
07/03/2025
Special inspection requirement — Metering
JAIME MOYA
07/03/2025
Special inspection requirement — Electrical motors and elevators
JAIME MOYA
07/03/2025
Special inspection requirement — Exterior lighting power
JAIME MOYA
07/03/2025
Special inspection requirement — Maintenance information
JAIME MOYA
07/03/2025
Special inspection requirement — Interior lighting power
JAIME MOYA
07/03/2025
Special inspection requirement — Fireplaces
JAIME MOYA
07/03/2025
Special inspection requirement — HVAC-R and service water heating equipment
JAIME MOYA
05/23/2025
Filed — Alteration
Q00875899-P1
03/18/2025
Violation issued (FDNY_NOV, closed)
02/09/2024
Signed off — Alteration
HEREWITH FILED FOR SPRINKLER WORK, AS PER PLANS. FILED IN CONJUNCTION WITH ALT.I 421757851
Q00875919-I1
02/09/2024
Signed off — Alteration
Herewith filed for plumbing work, filed in conjunction with ALT.I 421757851. Work as per plans.
Q00875910-I1
11/29/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/27/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/27/2023
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
11/20/2023
Filed — Alteration
Herewith filed for plumbing work, filed in conjunction with ALT.I 421757851. Work as per plans.
Q00875910-P4
11/10/2023
Filed — Alteration
Herewith filed for plumbing work, filed in conjunction with ALT.I 421757851. Work as per plans.
Q00875910-P3
10/24/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/13/2023
Filed — Alteration
Herewith filed for plumbing work, filed in conjunction with ALT.I 421757851. Work as per plans.
Q00875910-P2
09/25/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/28/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/26/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/21/2023
Filed — Alteration
Herewith filed for plumbing work, filed in conjunction with ALT.I 421757851. Work as per plans.
Q00875910-P1
07/01/2023
Permit issued — Mechanical Systems
Q00875899-I1-MS
06/15/2023
Permit issued — Sprinklers
Q00875919-I1-EW-SP
06/15/2023
Permit issued — Plumbing
Q00875910-I1-PL
06/13/2023
Filed — Alteration
HEREWITH FILED FOR SPRINKLER WORK, AS PER PLANS. FILED IN CONJUNCTION WITH ALT.I 421757851
Q00875919-I1
06/13/2023
Filed — Alteration
Herewith filed for plumbing work, filed in conjunction with ALT.I 421757851. Work as per plans.
Q00875910-I1
06/13/2023
Filed — Alteration
Q00875899-I1
06/05/2023
Permit issued — Construction Fence
Q00883445-I1-FN
06/01/2023
Filed — Alteration
Application is being filed for 8' inch high construction fence.
Q00883445-I1
03/30/2017
Violation issued (ECB, closed)
Construction
12/04/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/15/1997
Violation issued (DOB, closed)
VP*-VIOLATION UNSERVED ECB- DISMISSED
Latest 60 of 63 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offAMSCOAIR07/01/2023
DOB NOWSprinklersSigned-offPRACTICAL PLBG & HTG INC06/15/2023
DOB NOWPlumbingSigned-offPRACTICAL PLBG & HTG INC06/15/2023
DOB NOWConstruction FenceSigned-offRFP CONSTRUCTION INC06/05/2023
BIS—ISSUEDRFP CONSTRUCTION INC06/26/2025
BIS—ISSUEDRFP CONSTRUCTION INC07/07/2023
BIS—ISSUEDRFP CONSTRUCTION INC04/28/2023
BISOTISSUEDEAST COAST USA CONST INC03/13/2018
BISOTISSUEDMORELL BUILDERS INC09/23/2016
BISEQISSUEDYASH & B CONSTRUCTION COR12/21/2012
BISOTISSUEDSANYO S CONSTRUCTION CORP12/12/2012
3 projects · most recent 02/15/2024
General Wiring
FiledStatusContractorScope
02/15/2024CompleteGENMAR ELECT. CONT'G CORPGeneral Wiring
08/13/2023CompleteGENMAR ELECT. CONT'G CORPGeneral Wiring
06/19/2023CompleteGENMAR ELECT. CONT'G CORP—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
11/29/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/27/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/27/2023Certified Sprinkler - SP - RoughingCertifiedView ↗
10/24/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/25/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/28/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/26/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
06/26/2026Final—progress
08/28/2025HVAC-R and service water heating equipmentJAIME MOYAenergy_progress
08/28/2025Lighting in dwelling unitsJAIME MOYAenergy_progress
08/28/2025Exterior lighting powerJAIME MOYAenergy_progress
08/28/2025Permanent certificateJAIME MOYAenergy_progress
08/28/2025Duct leakage testing, insulation and designJAIME MOYAenergy_progress
08/28/2025Interior lighting powerJAIME MOYAenergy_progress
08/28/2025Ventilation and air distribution systemJAIME MOYAenergy_progress
08/28/2025HVAC-R and service water piping design and insulationJAIME MOYAenergy_progress
08/28/2025Shutoff dampersJAIME MOYAenergy_progress
08/28/2025Lighting controlsJAIME MOYAenergy_progress
08/28/2025Maintenance informationJAIME MOYAenergy_progress
08/28/2025FireplacesJAIME MOYAenergy_progress
08/28/2025MeteringJAIME MOYAenergy_progress
08/28/2025Electrical motors and elevatorsJAIME MOYAenergy_progress
08/28/2025FinalJAIME MOYAprogress
08/28/2025Mechanical SystemsJAIME MOYAspecial
08/28/2025HVAC-R and service water heating system controlsJAIME MOYAenergy_progress
07/03/2025Shutoff dampersJAIME MOYAenergy_progress
07/03/2025FinalJAIME MOYAprogress
07/03/2025Ventilation and air distribution systemJAIME MOYAenergy_progress
07/03/2025HVAC-R and service water piping design and insulationJAIME MOYAenergy_progress
07/03/2025Lighting in dwelling unitsJAIME MOYAenergy_progress
07/03/2025MeteringJAIME MOYAenergy_progress
07/03/2025Electrical motors and elevatorsJAIME MOYAenergy_progress
Latest 25 of 52.
▾Documents — 162 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/24/2026Q00883445-I1Request digital key ↗
08/24/2026Q00875899-P1Request digital key ↗
08/24/2026Q00875899-P2Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits27
▸BISPLAN / WORK APPROVAL APPLICATION21
02/23/2026421757851Open ↗
02/11/2026421757851Open ↗
06/02/2025421757851Open ↗
Showing 3 of 21 on file for this type
▸BISWORK PERMIT APPLICATION5
04/28/2023421757851Open ↗
03/20/2018421610787Open ↗
09/24/2016420794359Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
03/25/2024421757851Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISZONING RESOLUTION DETERMINATION1
08/16/2023421757851Open ↗
▸Seals & Professional Certifications77
▸DOB NOWProgress Inspector Seal & Signature48
09/12/2026Q00875899-I1Open ↗
09/12/2026Q00875899-I1Open ↗
09/12/2026Q00875899-I1Open ↗
Showing 3 of 48 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/24/2026Q00883445-I1Open ↗
08/24/2026Q00875899-P2Open ↗
08/24/2026Q00875899-P1Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
03/07/2020421757851Open ↗
04/05/2018421610787Open ↗
03/20/2018421610787Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
03/07/2020421757851Open ↗
03/20/2018421610787Open ↗
12/27/2012420797043Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/12/2026Q00875899-I1Open ↗
08/23/2026Q00875899-P2Open ↗
08/23/2026Q00875899-P1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
03/07/2020421757851Open ↗
03/20/2018421610787Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
12/27/2012420797043Open ↗
12/13/2012420794359Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST1
03/07/2020421757851Open ↗
▸BISTenant Protection Plan and Notes1
03/20/2018421610787Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/24/2026Q00875899-I1Open ↗
08/24/2026Q00875910-I1Open ↗
08/13/2026Q00875919-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
03/20/2018421610787Open ↗
12/13/2012420794359Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
08/16/2023421757851Open ↗
04/25/2023421757851Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
03/07/2020421757851Open ↗
04/05/2018421610787Open ↗
03/20/2018421610787Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
04/05/2018421610787Open ↗
03/15/2017420794359Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q00875899-I1Open ↗
▸Approvals, Objections & Sign-offs9
▸BISSCHEDULE A - OCCUPANCY / USE3
05/01/2023421757851Open ↗
06/21/2022421757851Open ↗
03/07/2020421757851Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
04/18/2018421610787Open ↗
03/21/2017420794359Open ↗
03/15/2017420794359Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
12/27/2012420797043Open ↗
12/13/2012420794359Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/24/2016420794359Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT5
03/07/2020421757851Open ↗
04/05/2018421610787Open ↗
03/20/2018421610787Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms14
▸BISBOROUGH INTAKE FORM5
06/16/2023421757851Open ↗
05/01/2023421757851Open ↗
11/02/2022421757851Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION5
08/15/2023421757851Open ↗
01/11/2023421757851Open ↗
11/09/2016420794359Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
03/07/2020421757851Open ↗
03/22/2018421610787Open ↗
12/27/2012420797043Open ↗
Showing 3 of 4 on file for this type