| Owner | Filings | Most Recent |
|---|---|---|
| 1065 ATLANTIC AVENUE | 93 | 07/08/2026 |
| BEB CAPITAL | 31 | 07/10/2026 |
| BIG SKY CONSTRUCTION | 12 | 04/09/2026 |
| PLATINUM SERVICES NY | 5 | 03/22/2026 |
| 1061 ATLANTIC ASSOCIATION | 2 | 03/21/2026 |
| 1061 ATLANTIC ASSOCIATES | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/26/2023 | $65.0M | — | ATLANTIC BROOKLYN, LLC → 1065 ATLANTIC AVENUE LLC | $141/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| COSENTINI ASSOCIATES | 10 | 12/08/2025 |
| DENCITYWORKS ARCHITECTURE PLLC. | 7 | 12/08/2025 |
| ZELJKO STEVANOVIC | 1 | 07/31/2025 |
| KONOSKI ENGINEERING PLLC | 2 | 04/22/2025 |
| GGA STUDIOS, DPC | 2 | 03/24/2025 |
| ROSENWASSER/GROSSMAN CONSULTING ENG | 6 | 02/12/2025 |
| ASHRAF CORP | 6 | 12/17/2024 |
| PATUXENT ENGINEERING LLC | 3 | 09/17/2024 |
| TOHFAZ UDDIN PE PC | 2 | 05/01/2024 |
| VALJATO ENGINEERING PC | 2 | 11/16/2023 |
| RAEL AUTOMATIC SPRINKLER CO., INC. | 1 | 08/04/2023 |
| PHILIP HABIB & ASSOCIATES | 2 | 12/01/2021 |
| LANGAN ENGINEERING, ENVIRONMENTAL, | 1 | 10/27/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 24 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 2 | 03/21/2026 |
| KUSHNER STUDIOS | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 6 | 03/21/2026 |
| VALJATO ENGINEERING P C | 4 | 03/21/2026 |
| KD DESIGNS | 7 | 03/21/2026 |
| JMG CONSULTANTS | 2 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| DOMANI CONSULTING | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J.E. LEVINE BUILDER INC | General Contractor | 28 | 07/08/2026 |
| RAEL AUTOMATIC SPR.CO INC | Fire Protection | 9 | 07/08/2026 |
| BIG SKY CONSTRUCTION CO | General Contractor | 7 | 07/08/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 6 | 07/08/2026 |
| FORWARD MECHANICAL CORP | Plumbing | 4 | 07/10/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 3 | 03/21/2026 |
| NEW LINE STRUCTURES & DEV | General Contractor | 2 | 03/21/2026 |
| RAEL AUTOMATIC SPR | Plumbing | 1 | 03/22/2026 |
| NEWBRIDGE ELECTL CONTNG | Electrical | 1 | 03/22/2026 |
| RELIANT ELEC'L CONT'G INC | Electrical | 1 | 03/22/2026 |
| DORIA SCAFFOLDING LLC | General Contractor | 1 | 04/09/2026 |
| BROOK PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DELTA TESTING LABS | 687 | 21 | 12/08/2025 |
| GILSANZ MURRAY STEFICEK | 240 | 7 | 12/08/2025 |
| SKYLINE RIGGING | 7880 | 1 | 07/31/2025 |
| KONOSKI ENGINEERING PLLC | 9111 | 2 | 04/22/2025 |
| LANGAN ENG, ENV, SURVEYIN | 1265 | 3 | 02/12/2025 |
| ROSENWASSER/GROSSMAN | 111 | 4 | 02/12/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | FORWARD MECHANICAL CORP | 07/09/2026 |
| DOB NOW | General Construction | Permit Issued | J.E. LEVINE BUILDER INC | 11/20/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | J.E. LEVINE BUILDER INC | 11/12/2025 |
| DOB NOW | Standpipe | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 09/10/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | DORIA SCAFFOLDING | 08/01/2025 |
| DOB NOW | Standpipe | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 07/16/2025 |
| DOB NOW | Sprinklers | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 07/15/2025 |
| DOB NOW | Curb Cut | Signed-off | BIG SKY CONSTRUCTION | 06/11/2025 |
| DOB NOW | Curb Cut | Signed-off | BIG SKY CONSTRUCTION | 06/10/2025 |
| DOB NOW | Boiler Equipment | Signed-off | BROOK PLUMBING & HTG CORP | 05/28/2025 |
| DOB NOW | General Construction | Signed-off | J.E. LEVINE BUILDER INC | 04/29/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | BIG SKY CONSTRUCTION | 04/01/2025 |
| DOB NOW | Plumbing | Permit Issued | FORWARD HEATING CORP | 03/13/2025 |
| DOB NOW | Foundation | Signed-off | J.E. LEVINE BUILDER INC | 11/19/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | J.E. LEVINE BUILDER INC | 11/19/2024 |
| DOB NOW | Mechanical Systems | Signed-off | J.E. LEVINE BUILDER INC | 11/19/2024 |
| DOB NOW | General Construction | Permit Issued | J.E. LEVINE BUILDER INC | 11/19/2024 |
| DOB NOW | Support of Excavation | Signed-off | J.E. LEVINE BUILDER INC | 11/19/2024 |
| DOB NOW | Foundation | Signed-off | J.E. LEVINE BUILDER INC | 10/10/2024 |
| DOB NOW | Standpipe | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 09/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | J.E. LEVINE BUILDER INC | 08/30/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | BIG SKY CONSTRUCTION | 08/20/2024 |
| DOB NOW | General Construction | Permit Issued | J.E. LEVINE BUILDER INC | 08/14/2024 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 07/31/2024 |
| DOB NOW | Standpipe | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 07/22/2024 |
| DOB NOW | Sprinklers | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 07/17/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ARSENAL SCAFFOLD INC | 07/17/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | BIG SKY CONSTRUCTION | 07/16/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | J.E. LEVINE BUILDER INC | 07/10/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 06/21/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | BIG SKY CONSTRUCTION | 06/03/2024 |
| DOB NOW | Support of Excavation | Signed-off | J.E. LEVINE BUILDER INC | 03/16/2024 |
| DOB NOW | Foundation | Signed-off | J.E. LEVINE BUILDER INC | 03/15/2024 |
| DOB NOW | Plumbing | Permit Issued | FORWARD HEATING CORP | 03/11/2024 |
| DOB NOW | Structural | Signed-off | J.E. LEVINE BUILDER INC | 09/28/2023 |
| DOB NOW | Mechanical Systems | Signed-off | J.E. LEVINE BUILDER INC | 09/06/2023 |
| DOB NOW | Standpipe | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 08/29/2023 |
| DOB NOW | General Construction | Permit Issued | J.E. LEVINE BUILDER INC | 08/21/2023 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 08/08/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ARSENAL SCAFFOLD INC | 07/26/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/08/2025 | Permit Issued | J.E. LEVINE BUILDER INC | Air Conditioning Systems, Associated Ducts and Piping, Cooling Towers, Heating Systems | Cooling Cgc Group SKV036 32,024 BTU ×4 SKV180 192,476 BTU · Boiler ×4 SKH012 11,933 BTU ×2 SKH030 29,000 BTU · Wshp ×2 SKH048 47,384 BTU ×2 SKH070 72,199 BTU ×2 SKH100 88,239 BTU ×2 SKV060 58,800 BTU · Wshp ×2 SKV150 126,262 BTU ×2 Aaon RN-016-8-0-H70E-EJN:ZELE-U0H-DPF-HHC-EDCB5Y1-00-D0A000JV1 177,000 BTU · Rooftop Unit ×4 RQ-004-8-H-EB09-12A 48,800 BTU ×2 Heating Ventilation N/A n/a 1 BTU · Exhaust Fan ×2 Cooling Tower Baltimore Aircoil S15E-1212-12MN-2/W 158 tons · Cooling Tower ×4 Ducts & Piping N/A n/a 1 BTU · Ductwork ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Permit Issued | RAEL AUTOMATIC SPR.CO INC | Sprinkler System |
| 08/04/2023 | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Permit Issued | FORWARD MECHANICAL CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/04/2026 | Complete | ALLBRIGHT ELECTRIC, INC | — |
| 11/12/2024 | Permit Issued | RELIANT ELEC'L CONT'G INC | General Wiring, Lighting |
| 04/09/2024 | Complete | NEWBRIDGE ELECTL CONTNG | — |
| 03/25/2024 | Complete | RELIANT ELEC'L CONT'G INC | — |
| 01/26/2024 | Complete | NEWBRIDGE ELECTL CONTNG | — |
| 08/17/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| 07/11/2023 | Complete | RELIANT ELEC'L CONT'G INC | 1 meters, 1 new_meters |
| 04/25/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| 11/28/2022 | Permit Issued | ILLUMINOUS ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Permit Issued | FORWARD MECHANICAL CORP | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/30/2022 | Permit Issued | PLATINUM SERVICES NY LLC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/29/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/25/2026 | Certified Storm Drainage-ST-Piping-Water Test | Certified | View ↗ |
| 04/01/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/24/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/25/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 11/21/2025 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 11/21/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 11/13/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/01/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/05/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/05/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/29/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 07/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/16/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/11/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 07/08/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 10/29/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/15/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/10/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/08/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/19/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/08/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/04/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/17/2025 | Energy Code Compliance Inspections | RICHARD GREENWALD | progress |
| 12/17/2025 | Sprinkler Systems | RICHARD GREENWALD | special |
| 12/17/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | RICHARD GREENWALD | special |
| 12/17/2025 | HVAC-R and service water piping design and insulation | RICHARD GREENWALD | energy_progress |
| 12/17/2025 | Standpipe Systems | RICHARD GREENWALD | special |
| 11/18/2025 | Energy Code Compliance Inspections | RICHARD GREENWALD | progress |
| 11/18/2025 | HVAC-R and service water piping design and insulation | RICHARD GREENWALD | energy_progress |
| 11/18/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | RICHARD GREENWALD | special |
| 11/06/2025 | Fenestration air leakage | ACHIM HERMES | energy_progress |
| 11/06/2025 | Fenestration areas | ACHIM HERMES | energy_progress |
| 11/06/2025 | Air barrier - visual inspection | ACHIM HERMES | energy_progress |
| 11/06/2025 | Insulation placement and R values | RICHARD GREENWALD | energy_progress |
| 11/06/2025 | Fenestration and door U-factor and product ratings | ACHIM HERMES | energy_progress |
| 11/06/2025 | Protection of exposed foundation insulation | RICHARD GREENWALD | energy_progress |
| 11/06/2025 | Fire-Resistance Rated Construction | RICHARD GREENWALD | progress |
| 11/06/2025 | Energy Code Compliance Inspections | RICHARD GREENWALD | progress |
| 11/06/2025 | Wall Panels, Curtain Walls, and Veneers | ACHIM HERMES | special |
| 11/06/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Solomon Rosenzweig | special |
| 11/06/2025 | Fire-Resistant Penetrations and Joints | RICHARD GREENWALD | special |
| 10/24/2025 | Wall Panels, Curtain Walls, and Veneers | ACHIM HERMES | special |
| 10/24/2025 | Fire-Resistant Penetrations and Joints | RICHARD GREENWALD | special |
| 10/24/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Solomon Rosenzweig | special |
| 10/24/2025 | Protection of exposed foundation insulation | RICHARD GREENWALD | energy_progress |
| 10/24/2025 | Fenestration and door U-factor and product ratings | ACHIM HERMES | energy_progress |
| 10/24/2025 | Insulation placement and R values | RICHARD GREENWALD | energy_progress |