Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofChimney support installation1p · 1 filing · 3 docs
ArchitectureMechanical
Issued Permit Scope
General Construction
INSTALL BRACKET SUPPORTS FOR CHIMNEY EXTENSION ON NEIGHBORING BUILDING.
On file for this project
3 documents · 1 drawing sheet
Floor 25NewYork-Presbyterian19p · 3 filings · 11 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 2 drawing sheets
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
No filed description on record for this project.
On file for this project
4 documents
Floor 24
Floor 23
Floor 22Demolition and renovation, 22nd floor22p · 1 filing · 12 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
IT IS PROPOSED TO RENOVATE THE 22FL (23FL MARKETING) OF EXISTING BUILDING FOR A BUILT-OUT AS SHOWN ON PLANS. APPLICATION FILED IN CONJUNCTION WITH S1 (MS), S2(PL/SP).
On file for this project
12 documents · 1 drawing sheet
Floor 21Cushman & Wakefield U.S., INC11p · 2 filings · 7 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing
MODIFICATION TO EXISTING PLUMBING AND SPRINKLER FIXTURES AS PER PLANS FILED HEREWITH. NO CHANGE IN USE EGRESS OR OCCUPANCY. APPLICATION FILED IN CONJUNCTION TO NEW BUILDING #123057538
On file for this project
5 documents · 2 drawing sheets
MODIFICATION TO EXISTING MECHANICAL SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE EGRESS OR OCCUPANCY. APPLICATION FILED IN CONJUNCTION TO NEW BUILDING #123057538
On file for this project
2 documents · 1 drawing sheet
Floor 20Renovation of floor 20 for build-out23p · 1 filing · 16 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
IT IS PROPOSED TO RENOVATE 20FL (MARKETING 21) OF EXISTING B UILDING FOR A BUILD-OUT AS SHOWN ON PLANS. NO CHANGE OF USE, EGRESS OF OCCUPANCY. APPLICATION FILED IN CONJUNCTION W/ M01182059-S12 (MS) AND M01182059-S2 (PL/SP)
On file for this project
16 documents · 10 drawing sheets
Floor 19THE SIX mechanical systems43p · 3 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 2 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 4 drawing sheets
Floor 18THE SIX mechanical system30p · 3 filings · 14 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 3 drawing sheets
INSTALLATION OF NON LOAD BEARING PARTITIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 4 drawing sheets
Floor 17THE SIX plumbing and sprinkler systems27p · 3 filings · 14 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 3 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 4 drawing sheets
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
Floor 16Savanna29p · 3 filings · 12 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 7 drawing sheets
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
Floor 15Mechanical system modification and inspection11p · 2 filings · 10 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Sprinklers
MODIFICATION TO EXISTING MECHANICAL SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. APPLICATION FILED IN CONJUNCTION TO NEW BUILDING #123057538.
On file for this project
6 documents · 1 drawing sheet
modifications to existing plumbing and sprinkler fixtures as per plans filed herewith.no change in use, egress occupancy. application filed in conjunction to new building #123057538.
On file for this project
4 documents · 2 drawing sheets
Floor 14Fitzwalter Fitou19p · 1 filing · 15 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
It is proposed to renovate 14FL for new tenant build-out as shown on plans. No Change of Use, Egress or occupancy. Application filed in conjunction with M00986083-S1 (MS), M00986083-S2 (PL), M00986083-S3 (SP)
On file for this project
15 documents · 6 drawing sheets
Floor 13THE SIX mechanical systems40p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 2 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
Floor 12Sprinkler system modification for tenant build-out25p · 1 filing · 15 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
IT IS PROPOSED TO RENOVATE 12FL OF EXISTING BUILDING FOR NEW TENANT BUILD-OUT AS SHOWN ON PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
On file for this project
15 documents · 10 drawing sheets
Floor 11
Floor 10The Six plumbing and sprinkler systems53p · 3 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MODIFICATION TO PLUMBING AND SPRINKLER PLANS. REMOVING THE 20TH FLOOR FROM THE PLANS
On file for this project
8 documents · 6 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 3 drawing sheets
MODIFICATION TO MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USSE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
Floor 9NewYork-Presbyterian19p · 3 filings · 11 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 2 drawing sheets
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
No filed description on record for this project.
On file for this project
4 documents
Floor 8THE SIX mechanical systems46p · 3 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
FILING MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 5 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 4 drawing sheets
Floor 7Mechanical equipment and ductwork installation for tenant bu49p · 1 filing · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MODIFICATION OF PLUMBING AND SPRINKLER SYSTEMS ON 7FL AS SHOWN ON PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY. APPLICATION FILED IN CONJUNCTION W/ M01195452-I1 (GC) & M01195452-S1 (MS)
On file for this project
34 documents · 23 drawing sheets
Floor 6Mechanical system modification and inspection11p · 2 filings · 10 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Sprinklers
MODIFICATION TO EXISTING MECHANICAL SYSTEM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. APPLICATION FILED IN CONJUNCTION TO NEW BUILDING #123057538.
On file for this project
6 documents · 1 drawing sheet
modifications to existing plumbing and sprinkler fixtures as per plans filed herewith.no change in use, egress occupancy. application filed in conjunction to new building #123057538.
On file for this project
4 documents · 2 drawing sheets
Floor 5
Floor 4The Six Interior Renovation 4th FloorUnder Construction51p · 4 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
APPLICATION FILED FOR INTERIOR RENOVATION OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 4TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
1 document · 2 drawing sheets
PLUMBING/SPRINKLER SYSTEM AS PER PLANS. NO CHANGE INUSE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 2 drawing sheets
INSTALLATION OF NON LOAD BEARINGPARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 7 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 3The Six plumbing and sprinkler work21p · 3 filings · 19 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MODIFICATION TO PLUMBING/SPRINKLER AS PER PLANS. NO CHANGE IN USSE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 2 drawing sheets
MODIFICATION TO MECHANICAL SYSTEM AS PER PLANS. NO CHANGE IN USSE, EGRESS OR OCCUPANCY.
On file for this project
11 documents · 1 drawing sheet
INSTALLATION OF NON-LOAD BEARING PARTITIONAS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Floor 2Second floor renovation and build-outUnder Construction36p · 1 filing · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MODIFICATION OF PLUMBING AND SPRINKLER SYSTEMS ON 2FL AS SHOWN ON PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY. APPLICATION FILED IN CONJUNCTION WITH M01231906-I1 (GC) AND M01231906-S1 (MS)
On file for this project
27 documents · 20 drawing sheets
Floor 1
CellarNewYork-Presbyterian2p · 1 filing · 4 docs
Fire ProtectionPlumbing
No filed description on record for this project.
On file for this project
4 documents · 2 drawing sheets
BasementNewYork-Presbyterian2p · 1 filing · 4 docs
Fire ProtectionPlumbing
No filed description on record for this project.
On file for this project
4 documents · 2 drawing sheets
Site & exteriorChimney support installation8p · 3 filings · 9 docs
ArchitectureElectricalEquipmentGeneralStructuralOther
Issued Permit Scope
Construction Fence · General Construction · Sidewalk Shed
INSTALL BRACKET SUPPORTS FOR CHIMNEY EXTENSION ON NEIGHBORING BUILDING.
On file for this project
3 documents · 5 drawing sheets
INSTALLATION OF FENCE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 4 drawing sheets
INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2014 CHAPTER 33 . NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
3 documents · 4 drawing sheets