RoofUnder Construction2p · 2 filings · 8 docs
DMStructural
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
Installation of a kitchen exhuast fan.
On file for this project
2 documents · 1 drawing sheet
Floor 418p · 18 filings · 20 docs
ArchitectureElectricalGeneralMechanical
Issued Permit Scope
Mechanical Systems
Installation of a kitchen exhuast fan.
On file for this project
2 documents
No filed description on record for this project.
On file for this project
2 documents · 1 drawing sheet
No filed description on record for this project.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 18 filings on this floor.
Floor 40Under Construction16p · 8 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Minor interior demolition. Removal & disposal of interior partitions, doors, suspended ceilings, flooring and finishes on the 40th Floor as per plans (Hines - Demo.) No change to use, egress or occupancy.
On file for this project
4 documents
Modifications to the existing Sprinkler System: Remove (277) existing sprinkler heads, Install (43) new sprinkler heads and associated sprinkler piping on the 40th Floor as per plans (LL Work - Demo.) No change to use, egress or occupancy.
On file for this project
3 documents
Removal of plumbing fixtures and associated CW/sanitary piping on the 40th Floor as per plans (LL Work - Demo.) No change to use, egress or occupancy. No change to use, egress or occupancy.
On file for this project
2 documents
Latest 3 of 8 filings on this floor.
Floor 3926p · 6 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalOther
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Sprinkler modifications on 39th floor as per plans filed herewith, no changes in use, egress or occupacny.
On file for this project
2 documents
General construction on 39th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Replacement of air conditioning units on the 39th and 40th floor IDF rooms
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 38Under Construction47p · 12 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Project M01452956Permit Issued · 10/02/2026
Install new plumbing fixtures and associated CW/sanitary piping on the 38th Floors as per plans (IMC Buildout Phase.) No change to use, egress or occupancy.
Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 38th Floors as per plans (IMC - Buildout Phase.) No change to use, egress or occupancy.
On file for this project
8 documents · 2 drawing sheets
Modifications to the existing HVAC System: Installation and relocation of ductwork and returns on the 38th Floor as per plans (IMC Buildout Phase.) No change to use, egress or occupancy.
On file for this project
8 documents
Latest 3 of 12 filings on this floor.
Floor 3753p · 8 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Interior removals and modifications to ductwork, associated piping on the 36th & 37th Floors as per plans (Standard Chartered Bank.) No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
New mechanical system throughout 37th Floor, inclusive of new ductwork, piping, air outlets, AC units, as per plans (Standard Chartered Bank.) No change to use, egress or occupancy.
On file for this project
6 documents · 3 drawing sheets
Minor interior demo of interior partitions, doors, suspended ceilings, office front system, flooring and finishes on the 36th & 37th Floors as per plans (SCB-36hth & 37th Floor Interior early demo). No change to use, egress, or occupancy.
On file for this project
4 documents
Latest 3 of 8 filings on this floor.
Floor 36Under Construction105p · 11 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Alt CO filed to increase population and establish PA on the 36th fl.
On file for this project
14 documents · 4 drawing sheets
Furnish and Install New Mechanical System throughout floor - new ductwork, piping, FPBs, air outlets and AC Units on the 36th Floor as per plans (Standard Chartered Bank - Phase 2.) No change to use, egress or occupancy.
On file for this project
12 documents · 3 drawing sheets
Interior removals and modifications to ductwork, associated piping on the 36th & 37th Floors as per plans (Standard Chartered Bank.) No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 11 filings on this floor.
Floor 3578p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Minor interior demo. Installation of new interior drywall partitions, doors, suspended ceilings, office front system, raised flooring and finishes on the 35th Floor as per plans (SCB - Hub, SER, MH and UPS Rooms and entire 35th Floor Fit-out.)
On file for this project
15 documents
Structural Modifications: Installation of New Structural Steel and supports for equipment at HUB Room and miscellaneous steel supports on the 35-36th Floors as per plans (Standard Chartered Bank.) No change to use, egress or occupancy.
On file for this project
8 documents · 2 drawing sheets
Install new Mechanical System throughout: New CAC, WSHPs, PCWPs, HX, SCWP, new ductwork, associated piping, FPBs, air outlets etc on the 35th Floor as per plans (Standard Chartered Bank.) No change to use, egress or occupancy.
On file for this project
12 documents · 3 drawing sheets
Latest 3 of 9 filings on this floor.
Floor 3424p · 3 filings · 15 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Modifications to the existing HVAC System as per plans (Lloyds Banking Group.) No change to use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Modifications to the existing sprinkler system: Install (9) new sprinkler heads, Relocate (13) existing sprinkler heads and Remove (2) existing sprinkler heads and associated piping on the 34th Floor as per plans (Lloyds Banking Group.)
On file for this project
3 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 34th Floor as per plans (Lloyds Banking Group.) No change to use, egress or occupancy.
On file for this project
5 documents · 2 drawing sheets
Floor 33Under Construction103p · 17 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Alt CO filed to increase population and establish PA on the 36th fl.
On file for this project
14 documents
Herewith filing administrative removal of Place of assembly occupancies on the 25th and 33rd office floors. Related Alt-2 application numbers: M00987959 and M01085014. No changes to use or egress.
On file for this project
16 documents · 4 drawing sheets
Modifications to the existing Sprinkler System: Install (134) new sprinkler heads and associated piping on the 33rd Floor as per plans (CDPQ.) No change to use, egress or occupancy.
On file for this project
8 documents · 5 drawing sheets
Latest 3 of 17 filings on this floor.
Floor 3249p · 8 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Herewith filing administrative removal of Place of assembly occupancies on the 25th and 33rd office floors. Related Alt-2 application numbers: M00987959 and M01085014. No changes to use or egress.
On file for this project
16 documents
Modifications to the existing Sprinkler System: Removal of (100) existing sprinkler heads and piping, Install (110) new sprinkler heads and piping on the 32nd Floor as per plans (China Construction Bank.) No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Herewith filing to establish new place of assembly on the 32nd floor, accessory to offices.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 3122p · 4 filings · 19 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 26-27, 29-31st Floors as per plans (Dechert LLP - Demo and Buildout.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modifications to the existing HVAC System: Removal of ductwork, piping, AC units, controls and wiring. Relocate thermostats, extend control wiring, install new BMS controllers on 26-27, 29-31st Floor as per plans (Dechert LLP - Demo & Buildout.)
On file for this project
6 documents
Remove (15) heads, Relocate (44), Install (10) new heads on 26; REL (11) heads, Install (3) new heads on 27; REL (28) heads, Install (3) new on 29; REM (6) heads, REL (31) heads, Install (7) new heads on 30; REL (14) and Install (3) new heads and piping.
On file for this project
4 documents
Latest 3 of 4 filings on this floor.
Floor 3020p · 3 filings · 16 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 26-27, 29-31st Floors as per plans (Dechert LLP - Demo and Buildout.) No change to use, egress or occupancy.
On file for this project
6 documents
Modifications to the existing HVAC System: Removal of ductwork, piping, AC units, controls and wiring. Relocate thermostats, extend control wiring, install new BMS controllers on 26-27, 29-31st Floor as per plans (Dechert LLP - Demo & Buildout.)
On file for this project
6 documents · 1 drawing sheet
Remove (15) heads, Relocate (44), Install (10) new heads on 26; REL (11) heads, Install (3) new heads on 27; REL (28) heads, Install (3) new on 29; REM (6) heads, REL (31) heads, Install (7) new heads on 30; REL (14) and Install (3) new heads and piping.
On file for this project
4 documents
Floor 2920p · 3 filings · 16 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 26-27, 29-31st Floors as per plans (Dechert LLP - Demo and Buildout.) No change to use, egress or occupancy.
On file for this project
6 documents
Modifications to the existing HVAC System: Removal of ductwork, piping, AC units, controls and wiring. Relocate thermostats, extend control wiring, install new BMS controllers on 26-27, 29-31st Floor as per plans (Dechert LLP - Demo & Buildout.)
On file for this project
6 documents · 1 drawing sheet
Remove (15) heads, Relocate (44), Install (10) new heads on 26; REL (11) heads, Install (3) new heads on 27; REL (28) heads, Install (3) new on 29; REM (6) heads, REL (31) heads, Install (7) new heads on 30; REL (14) and Install (3) new heads and piping.
On file for this project
4 documents
Floor 28Under Construction6p · 2 filings · 9 docs
Mechanical
Issued Permit Scope
Mechanical Systems
Modifications to the existing HVAC System: Installation of new supplemental AC Unit, ductwork, controls on the 28th Floor as per plans (Dechert LLP - Supplemental AC Unit.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC System: Installation of new 40-ton AC Unit, ductwork, controls on the 28th Floor as per plans (Dechert LLP - AC Unit.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Floor 2719p · 3 filings · 16 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 26-27, 29-31st Floors as per plans (Dechert LLP - Demo and Buildout.) No change to use, egress or occupancy.
On file for this project
6 documents
Modifications to the existing HVAC System: Removal of ductwork, piping, AC units, controls and wiring. Relocate thermostats, extend control wiring, install new BMS controllers on 26-27, 29-31st Floor as per plans (Dechert LLP - Demo & Buildout.)
On file for this project
6 documents
Remove (15) heads, Relocate (44), Install (10) new heads on 26; REL (11) heads, Install (3) new heads on 27; REL (28) heads, Install (3) new on 29; REM (6) heads, REL (31) heads, Install (7) new heads on 30; REL (14) and Install (3) new heads and piping.
On file for this project
4 documents
Floor 2620p · 4 filings · 19 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 26-27, 29-31st Floors as per plans (Dechert LLP - Demo and Buildout.) No change to use, egress or occupancy.
On file for this project
6 documents
Modifications to the existing HVAC System: Removal of ductwork, piping, AC units, controls and wiring. Relocate thermostats, extend control wiring, install new BMS controllers on 26-27, 29-31st Floor as per plans (Dechert LLP - Demo & Buildout.)
On file for this project
6 documents
Remove (15) heads, Relocate (44), Install (10) new heads on 26; REL (11) heads, Install (3) new heads on 27; REL (28) heads, Install (3) new on 29; REM (6) heads, REL (31) heads, Install (7) new heads on 30; REL (14) and Install (3) new heads and piping.
On file for this project
4 documents
Latest 3 of 4 filings on this floor.
Floor 25Under Construction87p · 15 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Alt CO filed to increase population and establish PA on the 36th fl.
On file for this project
14 documents
Modifications to the existing HVAC System: HVAC demolition, cut back & demolish duck work on the 25th Floor as per plans (Salesforce NY Tower.) No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Modifications to the existing HVAC System: Installation of new Water-Air Heat Pump, ductwork, diffusers and grilles on the 25th Floor as per plans (Salesforce NY Tower.) No change to use, egress or occupancy.
On file for this project
3 documents · 3 drawing sheets
Latest 3 of 15 filings on this floor.
Floor 24Under Construction22p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Install (5) BFPs (secondary), (3) CM, (2) DW, (1) IM, (4) FDs, (1) WC, (1) Lav, (1) HWH, (2) sinks, (1) water dispenser, (1) circulation pump and associated CW/drainage piping on 25th Floor; Install sanitary piping on 24th Floor (Salesforce Tower NY F25.)
On file for this project
4 documents · 1 drawing sheet
Minor interior demolition. Installation of new partitions, flooring, suspended ceilings, doors and finishes as per plans (Partial 24th Floor/ Suites 2400B and 2400C.) No change to use, egress or occupancy.
On file for this project
10 documents
Install new plumbing fixtures: (1) pantry sink, (1) chiller, (1) funnel drain, (1) Hot Water Heater, (1) Coffeemaker and (1) dishwasher and associated san/cw piping on the 24th Floor as per plans (Spec Suites.) No change to use, egress or occupancy.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 239p · 4 filings · 15 docs
ArchitectureDMMechanicalStructural
Issued Permit Scope
Mechanical Systems · Structural
Modifications to the existing HVAC system on the 23rd Floor (Salesforce - AV Room), as per plans. No change to use, egress, or occupancy.
On file for this project
6 documents · 2 drawing sheets
Minor interior structural modifications - installation of structural supports for HVAC equipment on the 23rd floor as per plans (Salesforce). No change to use, egress, occupancy.
On file for this project
5 documents
No filed description on record for this project.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 22
Floor 21
Floor 20Under Construction100p · 13 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Remove plumbing fixtures and associated piping. Install new plumbing fixtures and associated CW/sanitary piping on the 16-20th Floors as per plans (Salesforce Restrooms Refresh.) No change to use, egress or occupancy.
On file for this project
8 documents
Remove (6) head, install (6) new heads on 17; Remove (7) head, install (7) new heads on 18; Remove (7) head, install (7) new heads on 19; Remove (6) head, install (6) new heads on 20th Flr and associated piping as per plans (Salesforce Restroom Refresh.)
On file for this project
4 documents
Modifications to the existing HVAC System: Installation of new ductwork, diffusers and grilles on the 17-20th Floors as per plans (Salesforce Restroom Refresh.) No change to use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 13 filings on this floor.
Floor 19Under Construction42p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove plumbing fixtures and associated piping. Install new plumbing fixtures and associated CW/sanitary piping on the 16-20th Floors as per plans (Salesforce Restrooms Refresh.) No change to use, egress or occupancy.
On file for this project
8 documents
Remove (6) head, install (6) new heads on 17; Remove (7) head, install (7) new heads on 18; Remove (7) head, install (7) new heads on 19; Remove (6) head, install (6) new heads on 20th Flr and associated piping as per plans (Salesforce Restroom Refresh.)
On file for this project
4 documents
Modifications to the existing HVAC System: Installation of new ductwork, diffusers and grilles on the 17-20th Floors as per plans (Salesforce Restroom Refresh.) No change to use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 6 filings on this floor.
Floor 18Under Construction71p · 9 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove plumbing fixtures and associated piping. Install new plumbing fixtures and associated CW/sanitary piping on the 16-20th Floors as per plans (Salesforce Restrooms Refresh.) No change to use, egress or occupancy.
On file for this project
8 documents
Remove (6) head, install (6) new heads on 17; Remove (7) head, install (7) new heads on 18; Remove (7) head, install (7) new heads on 19; Remove (6) head, install (6) new heads on 20th Flr and associated piping as per plans (Salesforce Restroom Refresh.)
On file for this project
4 documents
Modifications to the existing HVAC System: Installation of new ductwork, diffusers and grilles on the 17-20th Floors as per plans (Salesforce Restroom Refresh.) No change to use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 9 filings on this floor.
Floor 17Under Construction80p · 11 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove plumbing fixtures and associated piping. Install new plumbing fixtures and associated CW/sanitary piping on the 16-20th Floors as per plans (Salesforce Restrooms Refresh.) No change to use, egress or occupancy.
On file for this project
8 documents
Remove (6) head, install (6) new heads on 17; Remove (7) head, install (7) new heads on 18; Remove (7) head, install (7) new heads on 19; Remove (6) head, install (6) new heads on 20th Flr and associated piping as per plans (Salesforce Restroom Refresh.)
On file for this project
4 documents
Modifications to the existing HVAC System: Installation of new ductwork, diffusers and grilles on the 17-20th Floors as per plans (Salesforce Restroom Refresh.) No change to use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 11 filings on this floor.
Floor 16Under Construction10p · 2 filings · 12 docs
Fire ProtectionPlumbingStructural
Issued Permit Scope
Plumbing · Standpipe
Remove plumbing fixtures and associated piping. Install new plumbing fixtures and associated CW/sanitary piping on the 16-20th Floors as per plans (Salesforce Restrooms Refresh.) No change to use, egress or occupancy.
On file for this project
8 documents
Modification of Standpipe system. Relocation of hose cabinet. No change of use, occupancy or egress.
On file for this project
4 documents · 1 drawing sheet
Floor 1560p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Removal of plumbing fixtures. Install new fixtures: (2) HWH, (1) FD, (1) sink, (1) Lavatory, (1) water closet and associated CW/sanitary piping on the 15th floor as per plans (US Bank Bryant Park CRE Expansion.) No change in use, egress or occupancy.
On file for this project
36 documents
Floor 1445p · 6 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Installation of new plumbing fixtures: (2) drinking fountains, (2) sinks, (2) water dispensers and (1) HWH with associated waste, vent, and water piping on the 14th Floor as per plans (VTS Office Renovations.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing Sprinkler System: Remove (39) existing sprinkler heads, Relocate (19) existing sprinkler heads and install (12) new sprinkler heads and associated piping on the 14th Floor as per plans (VTS Office Renovations.)
On file for this project
7 documents · 1 drawing sheet
Minor interior demo: Removal and disposal of interior partitions, fixtures, suspended ceilings, floor finishes; Installation of new partitions, doors, floor/wall finishes and suspended ceilings on the 14th Floor as per plans (VTS Office Renovation.)
On file for this project
3 documents · 7 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 13
Floor 1225p · 3 filings · 13 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Hereby filing modification to existing sprinkler system per plans filed herewith.
On file for this project
4 documents · 1 drawing sheet
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
6 documents
Hereby filing general construction for modification to concrete equipment pad and minor wall alterations in support of new mechanical equipment and rigging paths. No change to use, egress or occupancy
On file for this project
3 documents · 1 drawing sheet
Floor 1170p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Hereby filing modification to existing sprinkler system per plans filed herewith.
On file for this project
3 documents · 1 drawing sheet
Hereby filing concrete equipment pad modifications and minor wall alterations in support of new mechanical equipment and rigging paths on floor 7, and 9 thru 11
On file for this project
11 documents · 1 drawing sheet
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 1042p · 4 filings · 20 docs
ArchitectureDMMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Hereby filing concrete equipment pad modifications and minor wall alterations in support of new mechanical equipment and rigging paths on floor 7, and 9 thru 11
On file for this project
11 documents
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
3 documents · 1 drawing sheet
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
6 documents · 4 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 945p · 3 filings · 17 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Hereby filing modification to existing sprinkler system per plans filed herewith.
On file for this project
3 documents · 1 drawing sheet
Hereby filing concrete equipment pad modifications and minor wall alterations in support of new mechanical equipment and rigging paths on floor 7, and 9 thru 11
On file for this project
11 documents · 6 drawing sheets
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
3 documents · 2 drawing sheets
Floor 828p · 3 filings · 13 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Hereby filing modification to existing sprinkler system per plans filed herewith.
On file for this project
4 documents · 1 drawing sheet
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
6 documents · 2 drawing sheets
Hereby filing general construction for modification to concrete equipment pad and minor wall alterations in support of new mechanical equipment and rigging paths. No change to use, egress or occupancy
On file for this project
3 documents · 2 drawing sheets
Floor 735p · 2 filings · 14 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Hereby filing concrete equipment pad modifications and minor wall alterations in support of new mechanical equipment and rigging paths on floor 7, and 9 thru 11
On file for this project
11 documents · 1 drawing sheet
Hereby filing modifications to existing mechanical system and related duct & piping per plans filed herewith.
On file for this project
3 documents · 3 drawing sheets
Floor 6
Floor 572p · 9 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Minor interior demolition. Installation of new interior partitions, office fronts, folding partitions, flooring, suspended ceilings, conference rooms, closets and finishes as per plans (RenRe - Tenant Renovations.) No change to use, egress or occupancy.
On file for this project
12 documents · 6 drawing sheets
Installation of new Structural Steel beam and supports for for sliding modernfold partition and movable partition tracks on the 5th Floor as per plans (RenRe - Tenant Renovations.) No change to use, egress or occupancy.
On file for this project
10 documents · 1 drawing sheet
Modifications to the existing HVAC System: Install new ductwork, new pipework distribution, new FPB's, FCU's, (2) CRAC's and BMS controls on the 5th Floor as per plans (RenRe - Tenant Renovation.) No change to use, egress or occupancy.
On file for this project
13 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 4117p · 22 filings · 20 docs
ArchitectureCivilFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers · Standpipe
Remove (32) sprinkler heads, Install (33) new sprinkler heads, Relocate (1) sprinkler head and (1) FHC and associated SP/SD piping on the 3rd Floor; Relocate (2) sprinkler heads on the 4th Floor as per plans (Stifel - New Offices & Conference Rooms.)
On file for this project
4 documents · 1 drawing sheet
Minor interior demo: remove and discard walls, ceilings, flooring. Install new drywall partitions, office front system, millwork, suspended ceiling, flooring and finishes on the 3-4th Floors as per plans (Stifel - Offices & Conference Rooms.)
On file for this project
5 documents
Modifications to the existing HVAC System: Installation of new ductwork, insulation, air outlets, relocate FPB and controls on the 3-4th Floors as per plans (Stifel - New Offices & Conference Rooms.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 22 filings on this floor.
Floor 384p · 20 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers · Standpipe · Structural
Remove (32) sprinkler heads, Install (33) new sprinkler heads, Relocate (1) sprinkler head and (1) FHC and associated SP/SD piping on the 3rd Floor; Relocate (2) sprinkler heads on the 4th Floor as per plans (Stifel - New Offices & Conference Rooms.)
On file for this project
4 documents · 2 drawing sheets
Minor interior demo: remove and discard walls, ceilings, flooring. Install new drywall partitions, office front system, millwork, suspended ceiling, flooring and finishes on the 3-4th Floors as per plans (Stifel - Offices & Conference Rooms.)
On file for this project
5 documents
Modifications to the existing HVAC System: Installation of new ductwork, insulation, air outlets, relocate FPB and controls on the 3-4th Floors as per plans (Stifel - New Offices & Conference Rooms.) No change to use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Latest 3 of 20 filings on this floor.
Floor 236p · 5 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sign · Structural
Modifications to the existing HVAC, Install new ductwork, exhaust flue, dampers and controls in relation to new Life Safety Generator as per plans. No change to use, egress or occupancy.
On file for this project
22 documents · 2 drawing sheets
Structural Modifications and reinforcement of existing beams as per plans (Life Safety Generator Project.) No change to use, egress or occupancy.
On file for this project
10 documents
Minor interior demolition. Installation of new sheetrock partitions, suspended ceilings, lighting, doors, flooring and finishes as per plans (Life Safety Generator Project.) No change to use, egress or occupancy.
On file for this project
7 documents
Latest 3 of 5 filings on this floor.
Floor 1Under Construction85p · 20 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Modifications to the existing Sprinkler System: Remove (48) existing sprinkler heads, Install (41) new sprinkler heads and associated sprinkler piping on the 1st Floor as per plans (LL Work - Retail Demo.) No change to use, egress or occupancy.
On file for this project
3 documents
Removal of two (2) sinks, one (1) WC and associated CW/sanitary piping on the 1st Floor as per plans (LL Work - Retail Demo.) No change to use, egress or occupancy. No change to use, egress or occupancy.
On file for this project
2 documents
Minor interior demolition. Removal & disposal of interior partitions, doors, suspended ceilings, flooring and finishes on the 1st Floor as per plans (Hines - Demo.) No change to use, egress or occupancy.
On file for this project
4 documents
Latest 3 of 20 filings on this floor.
Mezzanine4p · 1 filing · 10 docs
Structural
Issued Permit Scope
Structural
Structural Modifications and reinforcement of existing beams as per plans (Life Safety Generator Project.) No change to use, egress or occupancy.
On file for this project
10 documents · 1 drawing sheet
Cellar72p · 6 filings · 20 docs
ArchitectureGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
Minor demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the Cellar & 1st Floor as per plans (Pandora Evoke 2.0.) No change to use, egress or occupancy.
On file for this project
12 documents · 6 drawing sheets
Modifications to the existing HVAC System on the Cellar & 1st Floors as per plans (Pandora - Evoke 2.0.) No change to use, egress or occupancy.
On file for this project
6 documents
Install (1) Drinking fountain and relocate (1) existing sink and associated CW/sanitary piping on the cellar level as per plans (Pandora.) No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Sub-Cellar58p · 5 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanical
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Sprinklers
Modifications to the existing HVAC, Install new ductwork, exhaust flue, dampers and controls in relation to new Life Safety Generator as per plans. No change to use, egress or occupancy.
On file for this project
22 documents · 2 drawing sheets
Minor interior demolition. Installation of new sheetrock partitions, suspended ceilings, lighting, doors, flooring and finishes as per plans (Life Safety Generator Project.) No change to use, egress or occupancy.
On file for this project
7 documents
Remove (12) existing sprinkler heads, Relocate (6) sprinkler heads and install (27) new sprinkler heads and associated piping on the Sub Cellar Level as per plans (Life Safety Generator.) No change to use, egress or occupancy.
On file for this project
28 documents · 4 drawing sheets
Latest 3 of 5 filings on this floor.
Site & exteriorUnder Construction20p · 7 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sidewalk Shed · Sign · Supported Scaffold
ERECT ILLUMINATED ACCESSORY BUSINESS WALL SIGN FOR PANDORA
On file for this project
3 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 5 drawing sheets
Installation of temporary tents, no alt to exist structures for Catapult -USA Productions. A TPA permit is not required. Producer is responsible to monitor site safety & implement HWAP.
On file for this project
3 documents · 3 drawing sheets
Latest 3 of 7 filings on this floor.
Filed — no permit issued103p · 19 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructuralOther
Modifications to the existing HVAC System: Demolition of mechanical equipment, ductwork and accessories on the 7th Floor as per plans (Verizon Demo Phase.) No change to use, egress or occupancy.
On file for this project
2 documents · 3 drawing sheets
Removal of plumbing fixtures and associated CW/sanitary piping on the 10th Floors as per plans (Verizon Demo Phase.) No change to use, egress or occupancy.
On file for this project
2 documents · 1 drawing sheet
Removal of plumbing fixtures and associated CW/sanitary piping on the 11th Floor as per plans (Verizon Demo Phase.) No change to use, egress or occupancy.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 19 filings on this floor.