1930Year Built
2Stories
F5Building Class
M1-2A/R6AZoning
44,923 sfGross Floor Area
14Units
LL97 Covered0 Open ViolationsFDNY Report ↗
Factory, light manufacturing · Owner of record: GMDC ATLANTIC AVENUE LLC · 26,365 sf lot · 1.7 FAR built · Flood zone X
Locations of Work
Mechanical
Roof1p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
D&B ENGINEERS AND ARCHITECTS, P.C.501/10/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
D&B ENGINEERS AND ARCHITECTS1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SCHWEITZER AND CROSSONGeneral Contractor303/21/2026
IRWIN FRIEDMAN & SON INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
D&B ENGINEERS AND ARCHITE2461501/10/2025
Building Lifecycle
All (33)Filed (5)Permit Issued (2)Signed Off (2)Violation (1)Inspection (3)Objection (8)Special Inspection (12)
02/06/2025
Signed off — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-I1
02/05/2025
Signed off — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-S1
02/05/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
01/17/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/14/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/13/2025
Special inspection requirement — Sprinkler Systems
Christopher Desmond
01/10/2025
Filed — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-P3
01/09/2025
Permit issued — Sprinklers
B01073118-S1-EW-SP
01/03/2025
Objection resolved — Addressed
12/31/2024
Objection raised — Scope
12/30/2024
Filed — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-P2
12/23/2024
Special inspection requirement — Sprinkler Systems
Christopher Desmond
11/26/2024
Special inspection requirement — Mechanical Systems
Christopher Desmond
11/26/2024
Special inspection requirement — Final
Christopher Desmond
11/26/2024
Special inspection requirement — Fire-Resistance Rated Construction
Christopher Desmond
11/26/2024
Special inspection requirement — Energy Code Compliance Inspections
Christopher Desmond
11/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Desmond
11/20/2024
Filed — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-P1
11/18/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Desmond
11/18/2024
Special inspection requirement — Mechanical Systems
Christopher Desmond
11/18/2024
Special inspection requirement — Energy Code Compliance Inspections
Christopher Desmond
11/18/2024
Special inspection requirement — Final
Christopher Desmond
11/18/2024
Special inspection requirement — Fire-Resistance Rated Construction
Christopher Desmond
11/01/2024
Filed — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-S1
10/15/2024
Permit issued — General Construction
B01073118-I1-GC-CX
08/02/2024
Objection resolved — Addressed
07/26/2024
Objection resolved — Addressed
07/17/2024
Objection resolved — Addressed
07/16/2024
Objection raised — Other
07/16/2024
Objection raised — Admin
07/15/2024
Objection raised — Other
07/10/2024
Filed — Alteration
Project is associated with the installation of a spray booth to conduct surface coating operations. 2 sprinkler heads being added to existing approved sprinkler system
B01073118-I1
12/01/2021
Violation issued (FDNY_NOV, closed)
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offIRWIN FRIEDMAN & SON INC01/09/2025
DOB NOWGeneral ConstructionSigned-offSCHWEITZER AND CROSSON10/15/2024
BISSPISSUEDJ. CAIAZZO PLBG & HTG CORP12/16/2016
BISSPISSUEDJ. CAIAZZO PLBG & HTG CORP11/04/2015
BISMHISSUEDFIRE VIOLATIONS SERVICES08/18/2015
2 jobs · most recent 11/07/2024
General Wiring
FiledStatusContractorScope
11/07/2024CompleteREDLINE ELECTRIC INC—
12/06/2018CompleteOHM PRO ELECTL CONST CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
02/05/2025Pass-Final General Construction Non-Directive 14PassView ↗
01/17/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/14/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
01/13/2025Sprinkler SystemsChristopher Desmondspecial
12/23/2024Sprinkler SystemsChristopher Desmondspecial
11/26/2024Mechanical SystemsChristopher Desmondspecial
11/26/2024FinalChristopher Desmondprogress
11/26/2024Fire-Resistance Rated ConstructionChristopher Desmondprogress
11/26/2024Energy Code Compliance InspectionsChristopher Desmondprogress
11/26/2024Fire-Resistant Penetrations and JointsChristopher Desmondspecial
11/18/2024Fire-Resistant Penetrations and JointsChristopher Desmondspecial
11/18/2024Mechanical SystemsChristopher Desmondspecial
11/18/2024Energy Code Compliance InspectionsChristopher Desmondprogress
11/18/2024FinalChristopher Desmondprogress
11/18/2024Fire-Resistance Rated ConstructionChristopher Desmondprogress
▾Documents — 51 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/23/2026B01073118-S1Request digital key ↗
08/23/2026B01073118-I1Request digital key ↗
08/23/2026B01073118-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION3
11/17/2015321166368Open ↗
09/02/2015321166368Open ↗
09/02/2015321166368Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
07/25/2016321166368Open ↗
08/19/2015321166368Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
07/21/2016321166368Open ↗
▸Seals & Professional Certifications22
▸DOB NOWProgress Inspector Seal & Signature6
08/24/2026B01073118-I1Open ↗
08/24/2026B01073118-I1Open ↗
08/24/2026B01073118-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/30/2026B01073118-S1Open ↗
08/24/2026B01073118-I1Open ↗
08/24/2026B01073118-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/23/2026B01073118-P1Open ↗
08/23/2026B01073118-S1Open ↗
08/23/2026B01073118-P3Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
08/08/2017321166368Open ↗
01/11/2017321166368Open ↗
08/19/2015321166368Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
08/19/2015321166368Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
08/19/2015321166368Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
08/19/2015321166368Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/23/2026B01073118-P1Open ↗
08/23/2026B01073118-S1Open ↗
08/23/2026B01073118-P2Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
08/19/2015321166368Open ↗
08/19/2015321166368Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
08/08/2017321166368Open ↗
08/19/2015321166368Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
08/08/2017321166368Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/08/2017321166368Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
08/08/2017321166368Open ↗
08/19/2015321166368Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION3
08/08/2017321166368Open ↗
08/08/2017321166368Open ↗
07/25/2016321166368Open ↗
▸BISEFILING COVER SHEET1