← Back
Telephone utility
1106 HOE AVENUE
BRONX · BIN 2006150
💬 Discuss this project
0Year Built
—Stories
U4Building Class
R7-1Zoning
0 sfGross Floor Area
0Units
2 Open Violations 0 unresolved · 2 paperwork only ▸FISP: SAFE
Telephone utility · Owner of record: NEW YORK TELEPHONE CO · 10,931 sf lot · 0 FAR built · Flood zone X
Locations of Work
MechanicalGeneral
Roof1p · 1 filing · 6 docs
Penthouse2p · 1 filing · 5 docs
Basement1p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VANTAGETOP507/08/2026
VERIZON4407/08/2026
NEW YORK TELEPHONE CO403/22/2026
NY TELEPHONE CO303/22/2026
NEW YORK TEL. CO.803/22/2026
NYNEX303/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JOEL PHAGOO P.E. PLLC103/21/2026
A1 EXPEDITING SERVICE203/21/2026
JAM CONSULTANTS, INC.403/21/2026
MERRITT ENGINEERING CONSULTANT DPC203/21/2026
PREEMPTIVE SOLUTIONS & CONSULTING L203/21/2026
JOEL PHAGOO P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TISHMAN INTERIORS CORPGeneral Contractor1307/08/2026
VANTAGETOP LLCGeneral Contractor507/08/2026
SAFWAY ATLANTIC, LLCGeneral Contractor307/08/2026
NEW YORK PLBG-HTG-COOLINGPlumbing203/22/2026
SPRING SCAFFOLDING LLCGeneral Contractor107/08/2026
STEPHEN KOPECElectrical103/21/2026
H.M. HUGHES CO. INCGeneral Contractor107/08/2026
PINTO & TEGER ELEC. CORP.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER544312/12/2023
MERRITT ENGINEERING CONSU460105/04/2023
Building Lifecycle
All (128)Filed (7)Permit Issued (15)Signed Off (7)Facade (FISP) (15)Violation (58)Special Inspection (26)
08/07/2026
Signed off — Alteration
Removal and replacement of all Mechanical control devices, valves and related minor piping shown on drawings filed herewith. No change in use, egress or occupancy. All MH units and system will be remaining and not in scope.
X00942924-I1
09/03/2025
Signed off — Alteration
GENERAL CONSTRUCTION IN RELATION TO REMOVAL OF COOLING TOWER, WITH REPLACEMENT OF NEW ADIABATIC FLUID COOLER. SCOPE INCLUDES SUPPORT OF EQUIPMENT, NEW CONCRETE PAD, AND FLOORING.
X00878052-I1
08/29/2025
Signed off — Alteration
REMOVAL OF COOLING TOWER AND ASSOCIATED PIPING, WITH REPLACEMENT OF NEW ADIABATIC FLUID COOLER & ASSOCIATED PIPING.
X00830081-I1
11/13/2024
Permit issued — Mechanical Systems
X00942924-I1-MS
11/12/2024
Permit issued — Mechanical Systems
X00830081-I1-MS
11/12/2024
Permit issued — General Construction
X00878052-I1-GC-CX
06/24/2024
Cycle 9 facade report signed — SAFE
02/29/2024
Signed off — Alteration
X00820995-I1
02/21/2024
Cycle 9 facade report submitted
02/08/2024
Cycle 9 facade inspection completed
01/16/2024
Signed off — Alteration
Installation of sidewalk shed as indicated on the attached drawings. There are no changes in use, egress or occupancy.
X00886332-I1
12/19/2023
Permit issued — Mechanical Systems
X00942924-I1-MS
12/15/2023
Permit issued — General Construction
X00878052-I1-GC-CX
12/15/2023
Permit issued — Mechanical Systems
X00830081-I1-MS
12/12/2023
Filed — Alteration
Removal and replacement of all Mechanical control devices, valves and related minor piping shown on drawings filed herewith. No change in use, egress or occupancy. All MH units and system will be remaining and not in scope.
X00942924-I1
11/08/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
EUGENE BIFULCO
11/08/2023
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
11/08/2023
Special inspection requirement — Maintenance information
EUGENE BIFULCO
11/08/2023
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
11/08/2023
Special inspection requirement — Post-installed Anchors
EUGENE BIFULCO
11/08/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
11/08/2023
Special inspection requirement — Shutoff dampers
EUGENE BIFULCO
10/03/2023
Special inspection requirement — Final
EUGENE BIFULCO
10/03/2023
Special inspection requirement — Mechanical Systems
EUGENE BIFULCO
09/21/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00125119-I1
07/12/2023
Permit issued — Structural
X00878052-I1-GC-CX
07/10/2023
Permit issued — Mechanical Systems
X00830081-I1-MS
06/22/2023
Filed — Alteration
GENERAL CONSTRUCTION IN RELATION TO REMOVAL OF COOLING TOWER, WITH REPLACEMENT OF NEW ADIABATIC FLUID COOLER. SCOPE INCLUDES SUPPORT OF EQUIPMENT, NEW CONCRETE PAD, AND FLOORING.
X00878052-I1
06/22/2023
Filed — Alteration
REMOVAL OF COOLING TOWER AND ASSOCIATED PIPING, WITH REPLACEMENT OF NEW ADIABATIC FLUID COOLER & ASSOCIATED PIPING.
X00830081-I1
06/07/2023
Filed — Alteration
Installation of sidewalk shed as indicated on the attached drawings. There are no changes in use, egress or occupancy.
X00886332-I1
06/07/2023
Permit issued — Sidewalk Shed
X00886332-I1-SH
05/19/2023
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
05/19/2023
Special inspection requirement — Structural Steel - Details
EUGENE BIFULCO
05/19/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
05/19/2023
Special inspection requirement — Structural Steel - High Strength Bolting
EUGENE BIFULCO
05/19/2023
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
05/19/2023
Special inspection requirement — Final
EUGENE BIFULCO
05/19/2023
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
05/19/2023
Special inspection requirement — Maintenance information
EUGENE BIFULCO
05/19/2023
Special inspection requirement — HVAC-R and service water heating equipment
EUGENE BIFULCO
05/18/2023
Permit issued — General Construction
X00820995-I1-GC
05/04/2023
Filed — Alteration
X00820995-I1
02/15/2023
Special inspection requirement — Mechanical Systems
EUGENE BIFULCO
02/15/2023
Special inspection requirement — Final
EUGENE BIFULCO
01/30/2023
Special inspection requirement — Air barrier - visual inspection
Christopher Krepcio
01/30/2023
Special inspection requirement — Energy Code Compliance Inspections
Christopher Krepcio
01/30/2023
Special inspection requirement — Final
Christopher Krepcio
01/30/2023
Special inspection requirement — Masonry
Christopher Krepcio
01/30/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Christopher Krepcio
01/30/2023
Special inspection requirement — Fenestration air leakage
Christopher Krepcio
12/19/2022
Signed off — Alteration
X00082441-I1
07/13/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/13/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
05/02/2020
Cycle 8 facade report signed — SAFE
03/14/2020
Cycle 8 facade inspection completed
12/19/2019
Cycle 8 facade report submitted
12/02/2019
Permit issued — Sidewalk Shed
X00125119-I1-SH
06/07/2019
Permit issued — Sidewalk Shed
X00125119-I1-SH
05/20/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/16/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 128 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP11/13/2024
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP11/12/2024
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP11/12/2024
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP12/19/2023
DOB NOWGeneral ConstructionSigned-offTISHMAN INTERIORS CORP12/15/2023
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP12/15/2023
DOB NOWStructuralSigned-offTISHMAN INTERIORS CORP07/12/2023
DOB NOWMechanical SystemsSigned-offTISHMAN INTERIORS CORP07/10/2023
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/07/2023
DOB NOWGeneral ConstructionSigned-offHM HUGHES CO INC05/18/2023
DOB NOWSidewalk ShedSigned-offVANTAGETOP LLC12/02/2019
DOB NOWSidewalk ShedSigned-offVANTAGETOP LLC06/07/2019
DOB NOWSidewalk ShedSigned-offVANTAGETOP LLC01/31/2019
DOB NOWSupported ScaffoldSigned-offSAFWAY ATLANTIC, LLC12/14/2018
DOB NOWSupported ScaffoldSigned-offSAFWAY ATLANTIC, LLC09/27/2018
BISOTISSUEDH.M. HUGHES CO. INC12/18/2019
BISMHISSUEDTISHMAN INTERIORS CORP09/24/2019
BISOTISSUEDTISHMAN INTERIORS CORP09/24/2019
BISOTISSUEDH.M. HUGHES CO. INC07/12/2019
BISOTISSUEDTISHMAN CONSTRUCTION CORP09/27/2018
BISMHISSUEDTISHMAN CONSTRUCTION CORP09/27/2018
BISOTRE-ISSUEDTISHMAN CONSTRUCTION CORP09/27/2018
BISMHISSUEDTISHMAN INTERIORS CORP09/26/2018
BISOTISSUEDTISHMAN INTERIORS CORP09/26/2018
BISOTISSUEDTISHMAN INTERIORS CORP09/26/2018
BISSPISSUEDASHLAR MECHANICAL CORP09/17/2018
BISFSISSUEDCHAMPION COMBUSTION CORP08/23/2018
BISSPISSUEDASHLAR MECHANICAL CORP08/15/2018
BISOTRE-ISSUEDTISHMAN CONSTRUCTION CORP07/30/2018
BISMHISSUEDTISHMAN CONSTRUCTION CORP07/30/2018
BISOTISSUEDTISHMAN CONSTRUCTION CORP07/30/2018
BISMHISSUEDON-TRAC CONSTRUCTION ASSO02/28/2018
BISOTISSUEDON-TRAC CONSTRUCTION ASSO02/28/2018
BISPLISSUEDPAR PLUMBING CO., INC01/22/2018
BISOTISSUEDTISHMAN INTERIORS CORP09/28/2017
BISMHISSUEDTISHMAN INTERIORS CORP09/28/2017
BISOTRE-ISSUEDTISHMAN INTERIORS CORP09/28/2017
BISSPISSUEDASHLAR MECHANICAL CORP08/17/2017
BISOTISSUEDTISHMAN INTERIORS CORP08/16/2017
BISMHISSUEDTISHMAN INTERIORS CORP08/16/2017
+ 25 more permits on file
1 project · most recent 12/12/2023
Associated Ducts and Piping Others
FiledStatusContractorScopeMake / Model / Capacity
12/12/2023Signed-offTISHMAN INTERIORS CORPAssociated Ducts and Piping, Others
Ducts & Piping
N/A N/A 1 BTU · Ductwork ×1
Other
N/A N/A 1 BTU ×1
8 projects · most recent 03/11/2026
General Wiring
FiledStatusContractorScope
03/11/2026Permit IssuedJAMES F. VOLPE ELEC'LGeneral Wiring
01/24/2025CompletePINTO & TEGER ELEC. CORP.General Wiring
12/14/2023CompleteHATZEL AND BUEHLER, INCGeneral Wiring
06/05/2023CompleteTOP SHELF ELECTRIC CORP—
04/04/2019CompleteCARUSO & SONS ELECTL CONTGeneral Wiring
01/25/2019Permit IssuedJOSEPH WEINSTEIN ELECTRIC—
08/24/2018CompleteCARUSO & SONS ELECTL CONTGeneral Wiring
05/23/2018CompleteGMA ELECTRICAL CORP.2 meters, 1 new_meters
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
11/08/2023HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
11/08/2023Energy Code Compliance InspectionsEUGENE BIFULCOprogress
11/08/2023Maintenance informationEUGENE BIFULCOenergy_progress
11/08/2023HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
11/08/2023Post-installed AnchorsEUGENE BIFULCOspecial
11/08/2023Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
11/08/2023Shutoff dampersEUGENE BIFULCOenergy_progress
10/03/2023FinalEUGENE BIFULCOprogress
10/03/2023Mechanical SystemsEUGENE BIFULCOspecial
05/19/2023Energy Code Compliance InspectionsEUGENE BIFULCOprogress
05/19/2023Structural Steel - DetailsEUGENE BIFULCOspecial
05/19/2023Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
05/19/2023Structural Steel - High Strength BoltingEUGENE BIFULCOspecial
05/19/2023Energy Code Compliance InspectionsEUGENE BIFULCOprogress
05/19/2023FinalEUGENE BIFULCOprogress
05/19/2023HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
05/19/2023Maintenance informationEUGENE BIFULCOenergy_progress
05/19/2023HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
02/15/2023Mechanical SystemsEUGENE BIFULCOspecial
02/15/2023FinalEUGENE BIFULCOprogress
01/30/2023Air barrier - visual inspectionChristopher Krepcioenergy_progress
01/30/2023Energy Code Compliance InspectionsChristopher Krepcioprogress
01/30/2023FinalChristopher Krepcioprogress
01/30/2023MasonryChristopher Krepciospecial
01/30/2023Structural Stability – Alterations of existing buildingsChristopher Krepciospecial
Latest 25 of 26.
▾Documents — 298 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch5
08/26/2026X00082441-I1Request digital key ↗
08/23/2026X00820995-I1Request digital key ↗
08/23/2026X00886332-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/26/2026X00125119-I1Request digital key ↗
▸Applications & Permits77
▸BISPLAN / WORK APPROVAL APPLICATION45
02/03/2020220645620Open ↗
12/02/2019220645648Open ↗
11/20/2019220577800Open ↗
Showing 3 of 45 on file for this type
▸BISWORK PERMIT APPLICATION31
12/19/2019220694167Open ↗
09/25/2019220577560Open ↗
09/25/2019220577560Open ↗
Showing 3 of 31 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications58
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION30
03/10/2020220577560Open ↗
02/20/2020220694167Open ↗
12/18/2019220645648Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/02/2026X00878052-I1Open ↗
08/28/2026X00830081-I1Open ↗
08/28/2026X00830081-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
12/02/2019220645648Open ↗
03/25/2019220694167Open ↗
04/26/2018220645648Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/26/2026X00125119-I1Open ↗
08/23/2026X00886332-I1Open ↗
08/23/2026X00830081-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
03/25/2019220694167Open ↗
04/26/2018220645648Open ↗
04/26/2018220645648Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026X00878052-I1Open ↗
08/28/2026X00830081-I1Open ↗
08/26/2026X00942924-I1Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment25
▸BISFA - FDNY APPROVAL : FD-FAA9
08/17/2020220577800Open ↗
05/18/2020220577739Open ↗
01/27/2020220645620Open ↗
Showing 3 of 9 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
04/25/2019220577560Open ↗
04/26/2018220644729Open ↗
01/09/2018220577560Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS5
01/07/2020220645648Open ↗
01/07/2020220645648Open ↗
01/07/2020220645648Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
01/07/2020220645648Open ↗
10/20/2017220559483Open ↗
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
02/03/2020220645620Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
04/26/2018220645648Open ↗
▸Environmental & Asbestos17
▸BISASBESTOS: CERTIFICATION (DEP ACP5)9
08/17/2020220577800Open ↗
05/19/2020220577739Open ↗
02/03/2020220645620Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/23/2026X00830081-I1Open ↗
08/13/2026X00820995-I1Open ↗
08/13/2026X00878052-I1Open ↗
Showing 3 of 4 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM3
08/17/2020220577800Open ↗
07/15/2019220694167Open ↗
08/28/2018220644729Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
08/16/2017220577560Open ↗
▸Energy Compliance16
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS10
02/20/2020220694167Open ↗
03/25/2019220694167Open ↗
09/07/2018220596246Open ↗
Showing 3 of 10 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
03/10/2020220577560Open ↗
02/20/2020220694167Open ↗
12/18/2019220645648Open ↗
Showing 3 of 6 on file for this type
▸Inspections & Test Reports2
▸BISHYDRO FLOW TEST LETTER1
08/18/2017220577560Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
08/18/2017220577560Open ↗
▸Approvals, Objections & Sign-offs19
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST16
08/17/2020220577800Open ↗
05/28/2020220577739Open ↗
03/10/2020220577560Open ↗
Showing 3 of 16 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION1
02/20/2020220694167Open ↗
▸BISSUPERSEDING LETTER1
09/28/2017220577560Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/13/2026X00886332-I1Open ↗
▸Cost, Insurance & Ownership27
▸BISCOST AFFIDAVIT27
08/17/2020220577800Open ↗
05/19/2020220577739Open ↗
03/10/2020220577560Open ↗
Showing 3 of 27 on file for this type
▸Filing & Intake Forms48
▸BISEFILING COVER SHEET21
03/25/2019220694167Open ↗
04/26/2018220645648Open ↗
04/26/2018220645648Open ↗
Showing 3 of 21 on file for this type
▸BISBOROUGH INTAKE FORM21
03/10/2020220577560Open ↗
02/20/2020220694167Open ↗
02/11/2020220645620Open ↗
Showing 3 of 21 on file for this type
▸BISADDITIONAL INFORMATION6
06/26/2019220645648Open ↗
06/26/2019220644729Open ↗
06/25/2019220645648Open ↗
Showing 3 of 6 on file for this type
▸Other Documents3
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
05/28/2020220577739Open ↗
05/28/2020220577739Open ↗
05/28/2020220577739Open ↗