1930Year Built
4Stories
C7Building Class
R7DZoning
6,035 sfGross Floor Area
9Units
Rent Stabilized5 Open Violations ▸FDNY Report ↗
Walk-up apt, over six families with stores · Owner of record: 1112 FULTON PARTNERS LLC · 2,184 sf lot · 2.76 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Roof27p · 1 filing · 20 docs
Penthouse30p · 1 filing · 20 docs
Floor 425p · 1 filing · 20 docs
Floor 327p · 1 filing · 20 docs
Floor 226p · 1 filing · 20 docs
Floor 125p · 1 filing · 20 docs
Cellar29p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1112 FULTON PARTNERS LLC103/22/2026
KARL ANTHONY ARCHITECTS303/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/13/2025$2.3M—1112 FULTON HOLDING LLC → 1112 FULTON PARTNERS LLC$377/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOHAMMAD AHEAD, PE502/18/2026
AG ENGINEERING PLLC107/17/2025
VASILIOS ARTEMIOU PE302/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ADVANCED BUILDERS SERVICES803/21/2026
ALLSTATE EXPEDITERS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ADOR BUILDERS LLCGeneral Contractor504/09/2026
ALPHONSE, MICHAELElectrical103/21/2026
PEREIRA, WESLLEYElectrical103/21/2026
AMERICAN STANDARD PLUMBING &Fire Protection107/08/2026
AMERICAN STANDARD P&H CORORP.Plumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616702/18/2026
Building Lifecycle
All (152)Filed (9)Permit Issued (5)Signed Off (5)Violation (60)Inspection (9)Objection (34)Special Inspection (30)
05/04/2026
Signed off — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-I1
03/10/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Air barrier — testing
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
03/10/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
02/25/2026
Objection resolved — Addressed
02/24/2026
Objection raised — Scope
02/18/2026
Signed off — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-S2
02/18/2026
Filed — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-P5
02/18/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Air barrier — testing
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
02/18/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
02/12/2026
Signed off — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-S3
12/24/2025
Objection raised — Scope
12/24/2025
Objection resolved — Addressed
12/24/2025
Objection raised — Scope
12/24/2025
Objection resolved — Addressed
12/22/2025
Filed — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-P3
12/10/2025
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
12/08/2025
Filed — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-P2
12/03/2025
Signed off — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-S1
12/02/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/28/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/20/2025
Violation issued (HPD, closed)
I
10/29/2025
Filed — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-P1
10/28/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
10/28/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/24/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
10/22/2025
Signed off — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-S4
10/22/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/13/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
08/13/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/29/2025
Permit issued — Plumbing
B01157031-S2-PL
07/29/2025
Permit issued — Sprinklers
B01157031-S3-EW-SP
07/21/2025
Permit issued — Construction Fence
B01157031-S4-FN
07/17/2025
Filed — Alteration CO
PROPOSED FULL NEW PLUMBING SYSTEM TO SUPPORT THE RENOVATION OF 4 STORY WITH TOTAL OF 8 RESIDENTIAL UNITS
B01157031-S4
07/07/2025
Permit issued — Mechanical Systems
B01157031-S1-MS
Latest 60 of 152 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offAMERICAN STANDARD P&H CORORP.07/29/2025
DOB NOWSprinklersSigned-offAMERICAN STANDARD PLUMBIN07/29/2025
DOB NOWConstruction FenceSigned-offADOR BUILDERS LLC07/21/2025
DOB NOWMechanical SystemsSigned-offADOR BUILDERS LLC07/07/2025
DOB NOWGeneral ConstructionPermit IssuedADOR BUILDERS LLC07/03/2025
BISPLISSUEDPLUMBING & HTG DOCTOR INC10/07/2016
BISOTISSUEDBINNS CONTRACTING GROUP I06/17/2015
BISPLISSUEDMETROPOLITAN HEAT & POWER CO02/14/2008
BISOTISSUEDJANEN CONSTRUCTION & DEVELOPMENT02/06/2008
1 project · most recent 02/18/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
02/18/2026Signed-offADOR BUILDERS LLCHeating and Air Conditioning Systems
Heat / Cool
Daikin 3MXL24WMVJU9 24,000 BTU · Heat Pump Outdoor ×6
RXF-18AXVJU 21,600 BTU · Heat Pump Outdoor ×2
1 project · most recent 02/18/2026
Sprinkler System
FiledStatusContractorScope
02/18/2026Signed-offAMERICAN STANDARD PLUMBINSprinkler System
1 project · most recent 02/18/2026
Storm Water/Sanitary
FiledStatusContractorScope
02/18/2026Signed-offAMERICAN STANDARD P&H CORStorm, Water/Sanitary
4 projects · most recent 02/19/2026
General Wiring
FiledStatusContractorScope
02/19/2026CompleteSOLAS ELECTRICAL CORP—
07/24/2025CompleteDAVRY ELECTRIC INC—
07/24/2025CompleteDAVRY ELECTRIC INCGeneral Wiring
02/13/2020CompleteV. VASS ELECTRIC CORP—
1 project · most recent 02/18/2026
Fence
FiledStatusContractorScope
02/18/2026Signed-offAMERICAN STANDARD PLUMBINFence
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
12/10/2025Pass-Final SP - Up to 3 Requested FloorsPassView ↗
12/02/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/28/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/28/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/28/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/24/2025Fail-Final CND-Occupancy InspectionFailView ↗
10/22/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/13/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/13/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 88
DateRequirementInspectorRole
03/10/2026Exterior Insulation and Finish Systems (EIFS)SHAHRIAR QUAYYUMspecial
03/10/2026Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
03/10/2026Lighting controlsSHAHRIAR QUAYYUMenergy_progress
03/10/2026Air barrier — testing SHAHRIAR QUAYYUMenergy_progress
03/10/2026Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
03/10/2026HVAC-R and service water piping design and insulationSHAHRIAR QUAYYUMenergy_progress
03/10/2026MeteringSHAHRIAR QUAYYUMenergy_progress
03/10/2026Fenestration areasSHAHRIAR QUAYYUMenergy_progress
03/10/2026Maintenance informationSHAHRIAR QUAYYUMenergy_progress
03/10/2026Lighting in dwelling unitsSHAHRIAR QUAYYUMenergy_progress
03/10/2026Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
03/10/2026Exterior lighting powerSHAHRIAR QUAYYUMenergy_progress
03/10/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
03/10/2026Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
03/10/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
03/10/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
03/10/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
02/18/2026Exterior Insulation and Finish Systems (EIFS)SHAHRIAR QUAYYUMspecial
02/18/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
02/18/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
02/18/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
02/18/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
02/18/2026Fenestration areasSHAHRIAR QUAYYUMenergy_progress
02/18/2026Exterior lighting powerSHAHRIAR QUAYYUMenergy_progress
02/18/2026Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
Latest 25 of 88.
▾Documents — 106 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/19/2026B01157031-P2Request digital key ↗
08/19/2026B01157031-P1Request digital key ↗
08/19/2026B01157031-S4Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits5
▸BISWORK PERMIT APPLICATION3
06/17/2015310066754Open ↗
02/14/2008310066754Open ↗
02/06/2008310066754Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
02/05/2026310066754Open ↗
10/24/2016310066754Open ↗
▸Zoning, Tax Lot & Property Records15
▸DOB NOWHouse Number Verification: TOPO Stamp5
08/19/2026B01157031-P1Open ↗
08/14/2026B01157031-P3Open ↗
08/13/2026B01157031-P5Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram5
08/19/2026B01157031-P1Open ↗
08/14/2026B01157031-P3Open ↗
08/13/2026B01157031-P5Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/19/2026B01157031-P1Open ↗
08/14/2026B01157031-P3Open ↗
08/13/2026B01157031-P2Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications34
▸DOB NOWSpecial Inspector Seal & Signature11
08/29/2026B01157031-P1Open ↗
08/29/2026B01157031-P1Open ↗
08/28/2026B01157031-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
08/29/2026B01157031-P1Open ↗
08/29/2026B01157031-P1Open ↗
08/28/2026B01157031-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/19/2026B01157031-P5Open ↗
08/19/2026B01157031-P3Open ↗
08/19/2026B01157031-P2Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
01/25/2008310066754Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
01/25/2008310066754Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
01/25/2008310066754Open ↗
▸BISPC FULL REPORT1
01/25/2008310066754Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
10/24/2016310066754Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
10/15/2016310066754Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist5
08/19/2026B01157031-P2Open ↗
08/19/2026B01157031-P1Open ↗
08/15/2026B01157031-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01157031-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/19/2026B01157031-P2Open ↗
08/19/2026B01157031-P1Open ↗
08/19/2026B01157031-S4Open ↗
Showing 3 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
01/25/2008310066754Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
01/25/2008310066754Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
02/14/2008310066754Open ↗
02/06/2008310066754Open ↗
▸Filing & Intake Forms1
▸BISADDITIONAL INFORMATION1
10/25/2016310066754Open ↗
▸Other Documents21
▸DOB NOWSite Survey: Initial5
08/19/2026B01157031-P1Open ↗
08/14/2026B01157031-P3Open ↗
08/13/2026B01157031-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/19/2026B01157031-P1Open ↗
08/14/2026B01157031-P3Open ↗
08/13/2026B01157031-P5Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlot Diagram5
08/19/2026B01157031-P1Open ↗
08/14/2026B01157031-P3Open ↗
08/13/2026B01157031-P5Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/19/2026B01157031-P2Open ↗
08/19/2026B01157031-P1Open ↗
08/15/2026B01157031-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWFinal Survey1
08/13/2026B01157031-I1Open ↗