← Back
Office with commercial, 7-19 stories
114 WEST 26 STREET
MANHATTAN · BIN 1015020
💬 Discuss this project
1911Year Built
12Stories
O6Building Class
M1-8A/R11Zoning
97,005 sfGross Floor Area
9Units
LL97 Covered6 Open Violations ▸FISP: SAFE
Office with commercial, 7-19 stories · Owner of record: JAL COLIN PROPERTIES · 8,465 sf lot · 11.46 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction11p · 3 filings · 13 docs
Floor 91p · 1 filing · 14 docs
Floor 8
Floor 7Under Construction3p · 1 filing · 14 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 21p · 1 filing · 3 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SJ SHAMIE REALTY5609/22/2026
JAL COLIN PROPERTIES1003/22/2026
DELTA ENTERPRISES CORP.203/22/2026
WILLIAMS REAL ESTATES803/22/2026
G.VA WILLIAMS REAL ESTATE103/22/2026
GREY BLOCK CORP103/22/2026
114 W 26 ST ASSOC LP203/22/2026
WILLIAMS & CO303/22/2026
CASPOL CORP203/22/2026
CARPOL CORP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ROBERT DERECTOR ASSOCIATES208/21/2026
GENSLER108/18/2026
JACK GREEN ASSOCIATES207/30/2026
BRICK CITY RECONSTRUCTION101/30/2025
ROJAS AP211/26/2024
THE EIPEL ENGINEERING GROUP, D.P.C.111/21/2024
HC PEC110/09/2024
RIGID STRUCTURAL DESIGN, LLC203/12/2024
CARL GUINTA ASSOCIATES110/21/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SEAY-YARBROUGH203/21/2026
Rigid Structural Design, LLC203/21/2026
MUNICIPAL BUILDING CONSULTANTS103/21/2026
ARCHETYPE CONSULTANTS403/21/2026
A1 EXPEDITING SERVICE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEPRINE CONSTRUCTION INCGeneral Contractor303/21/2026
RAINIER RESTORATION LLCGeneral Contractor303/21/2026
IDK COOLING CORPGeneral Contractor209/22/2026
GREGORY PAPANTONIOUElectrical203/21/2026
ROCKLEDGE SCAFFOLD CORPGeneral Contractor203/21/2026
STRUCTURE TONE, LLCGeneral Contractor208/30/2026
GIRASAN PLBG & HTG CORPElectrical103/21/2026
HINKE, WILLIAMElectrical103/21/2026
ASCHENDORF, JACKElectrical103/21/2026
KRSLOVIC, ANTEElectrical103/21/2026
ABCO-PEERLESS SPRKLR CORPFire Protection109/01/2026
PASQUALE QUARATINO INCFire Protection107/08/2026
NPF CONSTRUCTION CORPGeneral Contractor107/08/2026
JACKUS, STEVEElectrical103/21/2026
CASTILLO JR, JORGEElectrical103/21/2026
CHIARAMONTE, SALVATOREElectrical103/21/2026
C SCHLOSBERG INCElectrical103/21/2026
D&D ELECTL CONST CO INCElectrical103/22/2026
FELIZ, GABRIELElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CODEGREEN510208/21/2026
JACK GREEN ASSOCIATES422207/30/2026
THE EIPEL ENGINEERING GRO2714111/21/2024
GEORGE J. XERAKIAS, PE1658102/20/2024
G&G SPRINKLER SERVICES LL2782110/21/2020
Building Lifecycle
All (137)Filed (14)Permit Issued (12)Signed Off (7)Facade (FISP) (17)Violation (60)Objection (2)Special Inspection (25)
09/21/2026
Permit issued — Mechanical Systems
M01257393-I1-MS
08/31/2026
Permit issued — Sprinklers
M01417944-S3-EW-SP
08/27/2026
Permit issued — Mechanical Systems
M01417944-S1-MS
08/21/2026
Filed — Alteration
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 7TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01417944-S1
08/21/2026
Filed — Alteration
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 7TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01417944-S3
08/20/2026
Permit issued — General Construction
M01417944-I1-GC
08/20/2026
Special inspection requirement — Post-installed Anchors
James Sullivan Jr
08/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
James Sullivan Jr
08/20/2026
Special inspection requirement — HVAC-R and service water heating equipment
James Sullivan Jr
08/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
James Sullivan Jr
08/20/2026
Special inspection requirement — Post-installed Anchors
James Sullivan Jr
08/20/2026
Special inspection requirement — Maintenance information
James Sullivan Jr
08/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
James Sullivan Jr
08/18/2026
Filed — Alteration
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 7TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01417944-I1
08/10/2026
Special inspection requirement — Final
James Sullivan Jr
07/30/2026
Filed — Alteration
Mechanical filing to obtain Equipment Use Permits (COC) for existing AC units on the roof as indicated on drawings to comply with FDNY summons 014165612M & 014259875L
M01257393-I1
06/17/2026
Special inspection requirement — Mechanical Systems
James Sullivan Jr
06/17/2026
Special inspection requirement — Sprinkler Systems
James Sullivan Jr
06/17/2026
Special inspection requirement — Final
James Sullivan Jr
02/14/2025
Signed off — Alteration
INSTALLATION OF OUTRIGGERS FOR FACADE REPAIR AND INSPECTION
M01003713-I1
02/14/2025
Permit issued — Suspended Scaffold
M01003713-I1-SC
01/30/2025
Filed — Alteration
PARTIAL REMOVAL OF NON-BEARING PARTITIONS, FINISHES, AND DOORS. REMOVAL OF EXISTING ELECTRICAL WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01167138-I1
01/28/2025
Signed off — Alteration
M01141809-I1
01/24/2025
Signed off — Alteration
REPAIRS TO EXTERIOR FACADES. NO CHANGE TO EGRESS, USE OR OCCUPANCY.
M00944407-I1
01/21/2025
Objection resolved — Addressed
01/07/2025
Cycle 9 facade report signed — SAFE
12/06/2024
Objection raised — Scope
12/04/2024
Permit issued — Structural
M01141809-I1-ST
12/03/2024
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01009337-I1
12/03/2024
Violation issued (ECB, closed)
Construction
11/26/2024
Filed — Alteration
REPAIRS TO EXTERIOR FACADES. NO CHANGE TO EGRESS, USE OR OCCUPANCY.
M00944407-P1
11/26/2024
Cycle 9 facade report submitted
11/23/2024
Signed off — Alteration
M01113544-I1
11/21/2024
Filed — Alteration
M01141809-I1
11/21/2024
Cycle 9 facade inspection completed
10/25/2024
Special inspection requirement — Final
Deborah Rojas De Leon
10/09/2024
Filed — Alteration
M01113544-I1
10/09/2024
Permit issued — Supported Scaffold
M01113544-I1-SF
08/01/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/04/2024
Cycle 9 facade report signed — UNSAFE
06/03/2024
Cycle 9 facade report submitted
06/03/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/25/2024
Cycle 9 facade inspection completed
03/12/2024
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01009337-P1
02/27/2024
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01009337-I1
02/27/2024
Permit issued — Sidewalk Shed
M01009337-I1-SH
02/27/2024
Permit issued — General Construction
M00944407-I1-GC
02/26/2024
Permit issued — Suspended Scaffold
M01003713-I1-SC
02/22/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/20/2024
Filed — Alteration
INSTALLATION OF OUTRIGGERS FOR FACADE REPAIR AND INSPECTION
M01003713-I1
02/09/2024
Special inspection requirement — Post-installed Anchors
George Xerakias
02/09/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
George Xerakias
12/01/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/19/2023
Filed — Alteration
REPAIRS TO EXTERIOR FACADES. NO CHANGE TO EGRESS, USE OR OCCUPANCY.
M00944407-I1
10/03/2023
Cycle 8 facade report submitted
09/27/2023
Cycle 8 facade inspection completed
12/17/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/19/2021
Signed off — Alteration
INSTALLATION OF VRF HVAC SYSTEM ON THE 9TH FLOOR & ROOF. NO CHANGE IN USE EGRESS OR OCCUPANCY.
M00203938-I1
03/08/2021
Signed off — Alteration
Sprinkler changes on the 6th floor as indicated on drawings. No change in use, egress or occupancy. This work will supercede work filed under application # 102820048.
M00402239-I1
10/22/2020
Permit issued — Sprinklers
M00402239-I1-EW-SP
Latest 60 of 137 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedIDK COOLING CORP09/21/2026
DOB NOWSprinklersPermit IssuedABCO-PEERLESS SPRKLR CORP08/31/2026
DOB NOWMechanical SystemsPermit IssuedSTRUCTURE TONE, LLC08/27/2026
DOB NOWGeneral ConstructionPermit IssuedSTRUCTURE TONE, LLC08/20/2026
DOB NOWSuspended ScaffoldSigned-offHONEYBEE SERVICES INC02/14/2025
DOB NOWStructuralSigned-offNPF CONSTRUCTION CORP12/04/2024
DOB NOWSupported ScaffoldSigned-offROCKLEDGE SCAFFOLD CORP10/09/2024
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC02/27/2024
DOB NOWGeneral ConstructionSigned-offRAINIER RESTORATION LLC02/27/2024
DOB NOWSuspended ScaffoldSigned-offHONEYBEE SERVICES INC02/26/2024
DOB NOWSprinklersSigned-offPASQUALE QUARATINO INC10/22/2020
DOB NOWMechanical SystemsSigned-offIDK COOLING CORP10/23/2019
BISSPISSUEDPEAK FIRE PROTECTION LLC01/22/2020
BISSPISSUEDPEAK FIRE PROTECTION LLC03/07/2018
BISPLISSUEDA & E PLUMBING CORP09/15/2017
BISMHISSUEDPEAK MECHANICAL SOLUTION*09/01/2017
BISOTISSUEDPEAK MECHANICAL SOLUTION*09/01/2017
BISOTISSUEDCARDONE CONCRETE INC07/14/2017
BISOTISSUEDGJNY.CORP05/30/2017
BISMHISSUEDIDK COOLING CORP01/12/2017
BISMHISSUEDIDK COOLING CORP04/15/2016
BISMHISSUEDAB NY MECHANICAL CORP06/09/2014
BISOTISSUEDJEFFERSON GROUP LLC03/19/2014
BISOTISSUEDJEFFERSON GROUP LLC11/27/2013
BIS—ISSUEDL.S. SIGN CO., INC08/09/2013
BIS—ISSUEDL.S. SIGN CO., INC08/09/2013
BISSPISSUEDTMS PLUMBING & HTG CORP07/18/2013
BISPLISSUEDJTP PLBING CONTRACTOR, LT05/16/2013
BISOTISSUEDDUN DOIRE DESIGN INC05/02/2013
BISOTISSUEDLIBERTY DESIGN-BUILD CORP04/09/2013
BISOTISSUEDDNP BUILDERS LLC01/29/2013
BISOTISSUEDDNP BUILDERS LLC01/23/2013
BISMHISSUEDHONG FENG CONSTRUCTION IN12/06/2012
BISOTISSUEDHONG FENG CONSTRUCTION IN12/06/2012
BISOTISSUEDDNP BUILDERS LLC04/23/2012
BISOTISSUEDL & Z RESTORATION CORP06/23/2011
BISOTISSUEDPEGASUS REALTY SOLUTIONS06/13/2011
BISOTISSUEDPEGASUS REALTY SOLUTIONS06/13/2011
BISEQISSUEDROCK SCAFFOLDING CORP05/25/2011
BISEQISSUEDROCK SCAFFOLDING CORP02/04/2011
+ 22 more permits on file
1 project · most recent 07/30/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/30/2026Permit IssuedIDK COOLING CORPAir Conditioning Systems
Cooling
Mitsubishi Electric PUHY-P96TLMU-A 96,000 BTU · Vrf Outdoor ×1
York TCGD60S1S1A 60,000 BTU · Condensing Unit ×1
1 project · most recent 08/21/2026
FiledStatusContractorScope
08/21/2026Permit IssuedABCO-PEERLESS SPRKLR CORP—
5 projects · most recent 08/15/2025
General Wiring
FiledStatusContractorScope
08/15/2025Permit IssuedD&D ELECTL CONST CO INCGeneral Wiring
03/04/2025Permit IssuedD&D ELECTL CONST CO INC—
03/07/2024CompleteBOROWIDE ELECT'L CONTR'S—
02/21/2024CompleteBOROWIDE ELECT'L CONTR'S—
09/27/2019Permit IssuedSTAR ELEC'L CONTRACTORS C—
1 project · most recent 08/21/2026
FiledStatusContractorScope
08/21/2026Permit IssuedABCO-PEERLESS SPRKLR CORP1 scope_items
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
08/20/2026Post-installed AnchorsJames Sullivan Jrspecial
08/20/2026HVAC-R and service water heating system controlsJames Sullivan Jrenergy_progress
08/20/2026HVAC-R and service water heating equipmentJames Sullivan Jrenergy_progress
08/20/2026Fire-Resistant Penetrations and JointsJames Sullivan Jrspecial
08/20/2026Post-installed AnchorsJames Sullivan Jrspecial
08/20/2026Maintenance informationJames Sullivan Jrenergy_progress
08/20/2026HVAC-R and service water piping design and insulationJames Sullivan Jrenergy_progress
08/10/2026FinalJames Sullivan Jrprogress
06/17/2026Mechanical SystemsJames Sullivan Jrspecial
06/17/2026Sprinkler SystemsJames Sullivan Jrspecial
06/17/2026FinalJames Sullivan Jrprogress
10/25/2024FinalDeborah Rojas De Leonprogress
02/09/2024Post-installed AnchorsGeorge Xerakiasspecial
02/09/2024Alternative Materials - OTCR Buildings Bulletin NumberGeorge Xerakiasspecial
08/01/2019Maintenance informationJACK GREENenergy_progress
08/01/2019HVAC and service water heating system controls JACK GREENenergy_progress
08/01/2019Electrical motorsJACK GREENenergy_progress
08/01/2019Shutoff dampersJACK GREENenergy_progress
08/01/2019Permanent certificateJACK GREENenergy_progress
08/01/2019Duct leakage testing JACK GREENenergy_progress
08/01/2019Mechanical SystemsJACK GREENspecial
08/01/2019Smoke Control Systems TestingJACK GREENspecial
08/01/2019FinalJACK GREENprogress
08/01/2019HVAC and service water heating equipment JACK GREENenergy_progress
08/01/2019HVAC insulation and sealing JACK GREENenergy_progress
▾Documents — 405 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch10
08/28/2026M00944407-I1Request digital key ↗
08/28/2026M01003713-I1Request digital key ↗
08/27/2026M01009337-P1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/05/2026M00203938-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/04/2026M00402239-I1Request digital key ↗
▸Applications & Permits63
▸BISPLAN / WORK APPROVAL APPLICATION33
05/27/2021102820048Open ↗
07/14/2020140910192Open ↗
03/13/2020102820048Open ↗
Showing 3 of 33 on file for this type
▸BISWORK PERMIT APPLICATION30
01/23/2020123110338Open ↗
03/12/2018123110338Open ↗
09/20/2017123110338Open ↗
Showing 3 of 30 on file for this type
▸Seals & Professional Certifications121
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION48
02/26/2020123110338Open ↗
02/26/2020123110338Open ↗
06/06/2019123009617Open ↗
Showing 3 of 48 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST17
09/05/2017123110338Open ↗
09/05/2017123110338Open ↗
06/13/2017123009617Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/02/2026M00203938-I1Open ↗
09/02/2026M00203938-I1Open ↗
09/02/2026M00203938-I1Open ↗
Showing 3 of 16 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM11
07/25/2013121630529Open ↗
07/17/2013121550295Open ↗
Showing 2 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
09/05/2026M00203938-I1Open ↗
08/28/2026M00944407-P1Open ↗
08/28/2026M00944407-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/25/2026M01003713-I1Open ↗
09/25/2026M01003713-I1Open ↗
09/02/2026M00203938-I1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT6
09/05/2017123110338Open ↗
09/05/2017123110338Open ↗
06/13/2017123009617Open ↗
Showing 3 of 6 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
07/14/2020140910192Open ↗
07/14/2020140910192Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/14/2020140910192Open ↗
▸Trade Schedules & Equipment35
▸BISEQUIPMENT USE APPLICATION/PERMIT14
06/15/2017122947204Open ↗
06/15/2017122947204Open ↗
05/22/2017122947204Open ↗
Showing 3 of 14 on file for this type
▸BISEQUIPMENT USE PERMITS7
06/15/2017122947204Open ↗
06/15/2017122947204Open ↗
06/15/2017122947204Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE B - PLUMBING5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE4
01/29/2014121639940Open ↗
01/07/2014121639940Open ↗
Showing 2 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
09/05/2017123110338Open ↗
09/05/2017123110338Open ↗
▸BISSIGN HANGER CERTIFICATE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMITEQUIPMENT USE PERMITS1
06/29/2016122558865Open ↗
▸Environmental & Asbestos32
▸BISASBESTOS: CERTIFICATION (DEP ACP5)14
07/14/2020140910192Open ↗
09/05/2017123110338Open ↗
09/05/2017123138489Open ↗
Showing 3 of 14 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/05/2026M00203938-I1Open ↗
08/25/2026M01167138-I1Open ↗
08/19/2026M01417944-S3Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance31
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS17
09/05/2017123110338Open ↗
09/05/2017123110338Open ↗
06/14/2017123009617Open ↗
Showing 3 of 17 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
06/06/2019123009617Open ↗
05/26/2017121726098Open ↗
05/22/2017122947204Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
10/21/2020140910192Open ↗
10/19/2020140910192Open ↗
08/04/2020123831041Open ↗
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/14/2020140910192Open ↗
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
07/14/2020140910192Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
07/26/2017122785085Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
06/25/2020123831041Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
07/14/2020140910192Open ↗
▸Approvals, Objections & Sign-offs33
▸BISADMINISTRATIVE OBJECTIONS14
07/25/2013121630529Open ↗
07/17/2013121550295Open ↗
Showing 2 of 14 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
06/06/2019123009617Open ↗
05/26/2017122947204Open ↗
05/26/2017121726098Open ↗
Showing 3 of 13 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION6
06/25/2020123831041Open ↗
05/26/2017121726098Open ↗
05/22/2017122947204Open ↗
Showing 3 of 6 on file for this type
▸Cost, Insurance & Ownership37
▸BISCOST AFFIDAVIT36
07/14/2020140910192Open ↗
06/06/2019123009617Open ↗
09/05/2017123110338Open ↗
Showing 3 of 36 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
06/25/2020123831041Open ↗
▸Filing & Intake Forms36
▸BISEFILING COVER SHEET27
04/06/2020123831041Open ↗
09/05/2017123110338Open ↗
09/05/2017123110338Open ↗
Showing 3 of 27 on file for this type
▸BISBOROUGH INTAKE FORM4
02/26/2020103304354Open ↗
02/26/2020101352411Open ↗
06/06/2019123009617Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION4
10/21/2020140910192Open ↗
10/19/2020140910192Open ↗
10/12/2016122785085Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
07/14/2020140910192Open ↗
▸Other Documents2
▸DOB NOWCalculations1
08/13/2026M01003713-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01003713-I1Open ↗