| Owner | Filings | Most Recent |
|---|---|---|
| Gramaercy Five Associates | 231 | 03/22/2026 |
| Gva Williams | 14 | 03/21/2026 |
| 304 East 45th LLC C/O Gva Willia | 6 | 03/21/2026 |
| 11 Park Place LLC/Gva Williams | 6 | 03/21/2026 |
| Gramacy 5 Associates | 4 | 03/21/2026 |
| Williams Real Estate Co | 3 | 03/21/2026 |
| HBO Studio Productions | 3 | 03/21/2026 |
| Zec Enterprises | 2 | 08/05/2026 |
| 23rd St Properties | 2 | 03/21/2026 |
| Time Warner Cable Co | 1 | 03/21/2026 |
| Titan Outdoor | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Callisonrtkl Architects | 6 | 09/22/2026 |
| Lombardo Professional Engineering | 2 | 08/04/2026 |
| Method Design Architecture and Urba | 13 | 04/23/2026 |
| Desimone Consulting Engineers | 2 | 04/02/2026 |
| Highland Associates | 4 | 03/27/2026 |
| Asda Architecture + Design | 2 | 11/19/2025 |
| AMA Consulting Engineers | 6 | 09/18/2025 |
| Cosentini Associates | 3 | 07/02/2025 |
| Nelson Architecture & Interiors | 1 | 07/02/2025 |
| The Eipel Engineering Group | 3 | 05/01/2025 |
| Tohfaz Uddin PE | 1 | 02/28/2025 |
| Abco-Peerless Engineering | 1 | 12/20/2024 |
| Piro Studio | 1 | 10/11/2024 |
| Gensler | 7 | 10/30/2023 |
| Syska Hennessy Group | 13 | 06/12/2023 |
| MG Engineering | 9 | 05/22/2023 |
| Art of Form, Architects | 4 | 10/25/2022 |
| Green Design | 2 | 03/04/2021 |
| Conrad Trust | 1 | 05/21/2020 |
| Scalar Architecture | 1 | 12/29/2019 |
| Island Associates | 1 | 10/08/2019 |
| Bronzino Engineering | 1 | 03/28/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| William Vitacco Associates | 7 | 03/21/2026 |
| DVA Advisors | 19 | 03/21/2026 |
| Milrose Consultants | 42 | 03/21/2026 |
| Walter T. Gorman, PE | 1 | 03/21/2026 |
| Art of Form Architects | 26 | 03/21/2026 |
| AE Design Solution | 2 | 03/21/2026 |
| Abco-Peerless Sprinkler | 2 | 03/21/2026 |
| DI Dio Architecture | 2 | 03/21/2026 |
| Carl A Sulfaro | 1 | 03/21/2026 |
| Walter T Gorman PE | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Clune Construction Co | General Contractor | 40 | 07/08/2026 |
| L&K Partners | General Contractor | 9 | 07/08/2026 |
| A.W. & S. Construction Co | General Contractor | 6 | 09/16/2026 |
| Everest Scaffolding | Scaffold | 5 | 07/08/2026 |
| Ashlar Mechanical | Fire Protection | 5 | 07/08/2026 |
| Enobrac Plumbing | Plumbing | 4 | 07/08/2026 |
| RMT Electric | Electrical | 4 | 03/21/2026 |
| William Reynolds | General Contractor | 3 | 03/21/2026 |
| William C. Gerakaris P&H | Plumbing | 2 | 08/30/2026 |
| Corcoran John | Electrical | 2 | 03/21/2026 |
| Capitol Electric | Electrical | 2 | 03/21/2026 |
| Optimus Construction & Development* | General Contractor | 2 | 04/09/2026 |
| Andamio Scaffolding | Scaffold | 2 | 07/08/2026 |
| L&K Partners | Scaffold | 2 | 07/08/2026 |
| Zec Enterprises | Scaffold | 2 | 08/05/2026 |
| Service Sign Erectors Co | Sign hanger | 2 | 07/08/2026 |
| A Plus Plumbing | Fire Protection | 2 | 08/21/2026 |
| Corporate Electric Group | Electrical | 1 | 03/21/2026 |
| Epic Electric | Electrical | 1 | 03/22/2026 |
| Inner City Electrical Contractors | Electrical | 1 | 03/21/2026 |
| King Hoist & Scaffolding | Scaffold | 1 | 07/08/2026 |
| Full Capacity Fire | Fire Protection | 1 | 07/08/2026 |
| Mac Felder | Plumbing | 1 | 07/08/2026 |
| Steve Belsito Sons | Fire Protection | 1 | 07/08/2026 |
| A&A Plumbing | Plumbing | 1 | 07/08/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Borowide Elect'l Contractors | Electrical | 1 | 03/22/2026 |
| Etricity Electrical Co | Electrical | 1 | 03/22/2026 |
| DDS Mechanical FPS | Fire Protection | 1 | 07/08/2026 |
| Ainsworth | General Contractor | 1 | 07/08/2026 |
| Walton Electrical Construction | Electrical | 1 | 03/21/2026 |
| Volt Electric NYC | Electrical | 1 | 03/22/2026 |
| Thompson Michael | Electrical | 1 | 03/21/2026 |
| Midre Contracting | General Contractor | 1 | 07/08/2026 |
| D.D.S. Mechanical PBG & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Coastal Construction Service | 3827 | 6 | 04/02/2026 |
| JS Building Consulting | 4959 | 9 | 09/18/2025 |
| Outsource Special Inspection | 2827 | 5 | 07/02/2025 |
| The Eipel Engineering Group | 2714 | 5 | 05/01/2025 |
| Piro Studio | 7503 | 1 | 10/11/2024 |
| AK Engineering | 678 | 15 | 06/12/2023 |
| Tan Engineering | 1291 | 8 | 05/22/2023 |
| Walter T. Gorman, P.E., P | 268 | 1 | 10/08/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | A.W. & S. Construction Co | 09/15/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 08/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | A Plus Plumbing | 08/20/2026 |
| DOB NOW | Construction Fence | Permit Issued | Zec Enterprises | 08/04/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Zec Enterprises | 07/28/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | JC Contracting Management | 06/17/2026 |
| DOB NOW | Sprinklers | Permit Issued | A Plus Plumbing | 06/12/2026 |
| DOB NOW | Structural | Permit Issued | A.W. & S. Construction Co | 06/10/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 06/02/2026 |
| DOB NOW | Structural | Permit Issued | A.W. & S. Construction Co | 05/29/2026 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. Construction Co | 05/29/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | A.W. & S. Construction Co | 05/29/2026 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. Construction Co | 05/28/2026 |
| DOB NOW | Sign | Permit Issued | Service Sign Erectors Co | 11/26/2025 |
| DOB NOW | Sign | Permit Issued | Service Sign Erectors Co | 11/25/2025 |
| DOB NOW | Plumbing | Signed-off | D.D.S. Mechanical PBG & Heating | 07/18/2025 |
| DOB NOW | Sprinklers | Signed-off | DDS Mechanical FPS | 07/18/2025 |
| DOB NOW | General Construction | Signed-off | Optimus Construction & Development* | 07/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Optimus Construction & Development* | 07/17/2025 |
| DOB NOW | Construction Fence | Signed-off | L&K Partners | 03/14/2025 |
| DOB NOW | General Construction | Permit Issued | L&K Partners | 03/10/2025 |
| DOB NOW | General Construction | Signed-off | L&K Partners | 03/10/2025 |
| DOB NOW | General Construction | Signed-off | L&K Partners | 03/07/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | King Hoist & Scaffolding | 02/28/2025 |
| DOB NOW | Structural | Signed-off | L&K Partners | 01/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | L&K Partners | 01/02/2025 |
| DOB NOW | General Construction | Signed-off | L&K Partners | 01/02/2025 |
| DOB NOW | Sprinklers | Signed-off | Full Capacity Fire | 01/02/2025 |
| DOB NOW | Construction Fence | Signed-off | L&K Partners | 01/02/2025 |
| DOB NOW | Plumbing | Signed-off | A&A Plumbing | 12/31/2024 |
| DOB NOW | Sprinklers | Signed-off | Abco-Peerless Sprinkler | 12/23/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | Ainsworth | 11/01/2024 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 08/22/2024 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 08/22/2024 |
| DOB NOW | Sprinklers | Signed-off | Ashlar Mechanical | 09/06/2023 |
| DOB NOW | Plumbing | Signed-off | Mac Felder | 08/15/2023 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 06/21/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Clune Construction Co | 06/21/2023 |
| DOB NOW | Structural | Signed-off | Clune Construction Co | 06/21/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Clune Construction Co | 05/23/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/02/2026 | Permit Issued | A.W. & S. Construction Co | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric TPEFYP054MA1M0A 54,000 BTU · Vrf Indoor ×19 TPEFYP036MA1M0A 36,000 BTU · Vrf Indoor ×6 TURYH2403BMM0AN 240,000 BTU · Vrf Outdoor ×5 TPEFYP012MA1M0A 12,000 BTU · Vrf Indoor ×4 PKA-A36NL 36,000 BTU · Condensing Unit ×2 PUY-A36NL 36,000 BTU · Condensing Unit ×2 TPEFYP027MA1M0A 27,000 BTU · Vrf Indoor ×2 TPEFYP030MA1M0A 30,000 BTU · Vrf Indoor ×2 TPEFYP015MA1M0A 15,000 BTU · Vrf Indoor ×1 TPEFYP024MA1M0A 24,000 BTU · Vrf Indoor ×1 TURYH1203AMM0AN 120,000 BTU · Vrf Outdoor ×1 Ventilation Greenheck BSQ-360HP 11,000 CFM · Exhaust Fan ×1 SQ-100-VG 650 CFM · Exhaust Fan ×1 SQ-160HP-VG 1,000 CFM · Exhaust Fan ×1 SQ-90-VG 400 CFM · Exhaust Fan ×1 |
| 05/21/2020 | Signed-off | Midre Contracting | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2026 | Permit Issued | A Plus Plumbing | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2026 | Permit Issued | William C. Gerakaris P&H | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Permit Issued | Mer Electric | General Wiring |
| 01/28/2026 | Complete | Epic Electric | General Wiring |
| 07/17/2025 | Complete | Etricity Electrical Co | General Wiring |
| 01/30/2024 | Complete | Epic Electric | HVAC Wiring |
| 09/12/2023 | Permit Issued | Capitol Electric | General Wiring |
| 04/25/2022 | Complete | Epic Electric | General Wiring |
| 04/01/2022 | Complete | Epic Electric | — |
| 12/02/2021 | Complete | Jim Electric | General Wiring |
| 07/22/2021 | Permit Issued | Volt Electric NYC | General Wiring |
| 12/24/2019 | Complete | Borowide Elect'l Contractors | — |
| 12/13/2019 | Permit Issued | Jim Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2026 | Permit Issued | William C. Gerakaris P&H | Steel |
| 03/24/2026 | Permit Issued | A.W. & S. Construction Co | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | Zec Enterprises | Fence |
| 07/28/2026 | Permit Issued | Zec Enterprises | Scaffold |
| 02/28/2025 | Permit Issued | King Hoist & Scaffolding | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/24/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/11/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/09/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/09/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/10/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/13/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/06/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/30/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 01/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/08/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/02/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/02/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/19/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/02/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/23/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/15/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/14/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/09/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/10/2026 | Public Assembly Emergency Lighting | JOSEPH FREGLETTE | progress |
| 08/11/2026 | Public Assembly Emergency Lighting | JOSEPH FREGLETTE | progress |
| 04/27/2026 | Fenestration and door U-factor and product ratings | Julian Saavedra | energy_progress |
| 04/27/2026 | Final | Julian Saavedra | progress |
| 04/27/2026 | Energy Code Compliance Inspections | Julian Saavedra | progress |
| 04/27/2026 | Insulation placement and R values | Julian Saavedra | energy_progress |
| 04/27/2026 | Fenestration areas | Julian Saavedra | energy_progress |
| 04/27/2026 | Fenestration air leakage | Julian Saavedra | energy_progress |
| 04/27/2026 | Air barrier - visual inspection | Julian Saavedra | energy_progress |
| 03/24/2026 | Maintenance information | JOSEPH FREGLETTE | energy_progress |
| 03/24/2026 | Duct leakage testing, insulation and design | JOSEPH FREGLETTE | energy_progress |
| 03/24/2026 | HVAC-R and service water heating system controls | JOSEPH FREGLETTE | energy_progress |
| 03/24/2026 | HVAC-R and service water heating equipment | JOSEPH FREGLETTE | energy_progress |
| 03/24/2026 | HVAC-R and service water piping design and insulation | JOSEPH FREGLETTE | energy_progress |
| 03/24/2026 | Fire-Resistant Penetrations and Joints | JOSEPH FREGLETTE | special |
| 03/24/2026 | Post-installed Anchors | JOSEPH FREGLETTE | special |
| 03/19/2026 | Structural Steel - Details | JOSEPH FREGLETTE | special |
| 03/19/2026 | Final | JOSEPH FREGLETTE | progress |
| 03/19/2026 | Mechanical Systems | JOSEPH FREGLETTE | special |
| 03/19/2026 | Final | JOSEPH FREGLETTE | progress |
| 03/19/2026 | Structural Steel - Welding | JOSEPH FREGLETTE | special |
| 03/19/2026 | Structural Steel - High Strength Bolting | JOSEPH FREGLETTE | special |
| 03/19/2026 | Fire-Resistant Penetrations and Joints | JOSEPH FREGLETTE | special |
| 03/19/2026 | Post-installed Anchors | JOSEPH FREGLETTE | special |
| 03/19/2026 | Sprinkler Systems | JOSEPH FREGLETTE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Convene | Events & gatherings | Cellar, Floor 1, Roof | Project M01351744 Project M01357243 Project M01373819 Project M01344105 |
| Charter Communications | Office | Cellar, Floors 7–12, Roof | Project M01158744 Project M00862971 Project M00877595 Project M00877597 Project M00877602 Project M00862928 Project M00729089 Project M00741010 Project M00792404 Project M00629676 Project M00690036 Project M00690039 |
| the Ecole School | Education | Cellar, Floors 1–3, Roof | Project M01107687 Project M01143077 Project M01107627 Project M01107593 |
| K&LGroup | Office | Floors 9, 11, 12 | Project M00540017 Project M00540041 |