| Owner | Filings | Most Recent |
|---|---|---|
| COLUMBIA UNIVERSITY | 73 | 07/08/2026 |
| HENRY RESTORATION LIMITED | 6 | 03/22/2026 |
| TRUSTEES OF COLUMBIA UNIVERSITY | 8 | 03/21/2026 |
| COLUMBIA UNIVERSITY FACILITIES | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ABCO-PEERLESS ENGINEERING, P.C. | 1 | 09/24/2025 |
| HOFFMANN ARCHITECTS, INC. | 3 | 07/15/2025 |
| ASHRAF CORP | 1 | 06/12/2025 |
| CES ENGINEERING LLC | 6 | 12/23/2024 |
| POLISE CONSULTING ENGINEERS DPC | 4 | 07/01/2024 |
| INTEGRATED DESIGN GROUP | 1 | 11/08/2023 |
| ENTHINK ENGINEERS LLC | 2 | 05/10/2023 |
| SUPERSTRUCTURES ENG. + ARCH. | 1 | 04/17/2023 |
| BAILEYS ENGINEERING PC | 1 | 12/18/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| OUTSOURCE CONSULTANTS, INC. | 17 | 03/21/2026 |
| RIZZO GROUP | 2 | 03/21/2026 |
| HOFFMANN ARCHITECTS | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPRING SCAFFOLDING LLC | General Contractor | 8 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 7 | 07/08/2026 |
| HENRY RESTORATION LTD | General Contractor | 7 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 4 | 07/08/2026 |
| SITEWORKS CONTRACTING CO* | General Contractor | 4 | 07/08/2026 |
| WESBUILT CONSTRUCTION MAN | General Contractor | 4 | 07/08/2026 |
| BRENNAN OPERATING INC | General Contractor | 2 | 03/21/2026 |
| LAZO, DARWIN | Electrical | 2 | 03/21/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 2 | 03/21/2026 |
| ROTHOWSKI, EDWARD | Electrical | 2 | 03/21/2026 |
| M & J MECHANICAL CORP | General Contractor | 2 | 03/21/2026 |
| FLAG ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| CARLOS DE ARMAS | Electrical | 1 | 03/21/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 1 | 07/08/2026 |
| SCALA, JR., ANTHONY | Electrical | 1 | 03/21/2026 |
| ASHLAR MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| MOORE, KEVIN | Electrical | 1 | 03/21/2026 |
| KAY WATERPROOFING CORP | General Contractor | 1 | 04/09/2026 |
| ALLIANCE PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CROSSCHECK INSPECTION SER | 544 | 8 | 09/24/2025 |
| COLE TECHNOLOGIES/CONTROL | 1290 | 3 | 07/15/2025 |
| SUPERSTRUCTURES ENGINEERI | 374 | 1 | 04/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 04/14/2026 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 04/14/2026 |
| DOB NOW | General Construction | Permit Issued | WESBUILT CONSTRUCTION MAN | 10/06/2025 |
| DOB NOW | Sprinklers | Signed-off | ABCO-PEERLESS SPRKLR CORP | 09/26/2025 |
| DOB NOW | General Construction | Signed-off | KAY WATERPROOFING CORP | 07/16/2025 |
| DOB NOW | General Construction | Signed-off | HENRY RESTORATION LTD | 06/18/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 06/13/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | WESBUILT CONSTRUCTION MAN | 05/14/2025 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 05/14/2025 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 05/14/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | WESBUILT CONSTRUCTION MAN | 05/13/2025 |
| DOB NOW | General Construction | Signed-off | WESBUILT CONSTRUCTION MAN | 05/13/2025 |
| DOB NOW | Sprinklers | Signed-off | ASHLAR MECHANICAL CORP | 04/09/2024 |
| DOB NOW | General Construction | Signed-off | HENRY RESTORATION LTD | 12/04/2023 |
| DOB NOW | Mechanical Systems | Signed-off | M & J MECHANICAL CORP | 12/04/2023 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING WMBE | 11/28/2023 |
| DOB NOW | General Construction | Signed-off | BRENNAN OPERATING | 11/09/2023 |
| DOB NOW | General Construction | Signed-off | HENRY RESTORATION LTD | 09/29/2023 |
| DOB NOW | General Construction | Signed-off | HENRY RESTORATION LTD | 06/06/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 05/10/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 05/10/2023 |
| DOB NOW | Structural | Signed-off | SITEWORKS CONTRACTING CO* | 10/21/2022 |
| DOB NOW | Structural | Signed-off | SITEWORKS CONTRACTING CO* | 03/25/2022 |
| DOB NOW | Structural | Signed-off | SITEWORKS CONTRACTING CO* | 02/18/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 02/28/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 02/06/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 01/08/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 12/19/2017 |
| BIS | MH | ISSUED | BRENNAN OPERATING INC | 07/22/2019 |
| BIS | MH | ISSUED | BRENNAN OPERATING INC | 06/26/2019 |
| BIS | OT | ISSUED | BRENNAN OPERATING INC | 06/26/2019 |
| BIS | MH | ISSUED | MANHATTAN BUSINESS INTERIORS | 05/23/2019 |
| BIS | OT | ISSUED | MANHATTAN BUSINESS INTERIORS | 05/23/2019 |
| BIS | OT | ISSUED | MANHATTAN BUSINESS INTERIORS | 04/26/2019 |
| BIS | MH | ISSUED | MANHATTAN BUSINESS INTERIORS | 04/26/2019 |
| BIS | OT | ISSUED | CENTRAL CONSULTING & CONT | 08/30/2018 |
| BIS | MH | ISSUED | BRENNAN OPERATING INC | 07/26/2018 |
| BIS | MH | ISSUED | BRENNAN OPERATING INC | 07/26/2018 |
| BIS | OT | ISSUED | BRENNAN OPERATING INC | 07/26/2018 |
| BIS | OT | ISSUED | BRENNAN OPERATING INC | 07/26/2018 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/23/2024 | Permit Issued | WESBUILT CONSTRUCTION MAN | Ventilation Systems | Ventilation Carrier ×1 |
| 12/23/2024 | Permit Issued | WESBUILT CONSTRUCTION MAN | Ventilation Systems | Ventilation Carrier 39LB08 131,500 BTU · Ahu ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2025 | Signed-off | ABCO-PEERLESS SPRKLR CORP | 50 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2025 | — | — | — |
| 12/23/2024 | Permit Issued | PAR PLUMBING CO., INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2026 | Permit Issued | FLAG ELECTRIC INC | General Wiring |
| 10/21/2025 | Permit Issued | FLAG ELECTRIC INC | General Wiring |
| 06/16/2025 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 08/07/2024 | Complete | MATROS AUTOMATED ELEC'L C | General Wiring |
| 05/16/2023 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 01/10/2020 | Complete | MATROS AUTOMATED ELEC'L C | General Wiring |
| 12/08/2017 | Complete | TOP SHELF ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/18/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/11/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/07/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/01/2026 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 01/23/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/16/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/15/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/15/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/03/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/17/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/14/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/15/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/18/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/28/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/03/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2025 | Sprinkler Systems | EUGENE BIFULCO | special |
| 07/02/2025 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 07/01/2025 | Final | Juan Kuriyama | progress |
| 07/01/2025 | Masonry | GEORGE ANDERSEN | special |
| 12/11/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 12/11/2024 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 12/05/2024 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 12/05/2024 | Final | EUGENE BIFULCO | progress |
| 12/04/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 11/26/2024 | HVAC-R and service water piping design and insulation | EUGENE BIFULCO | energy_progress |
| 11/26/2024 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 11/26/2024 | Shutoff dampers | EUGENE BIFULCO | energy_progress |
| 11/26/2024 | Interior lighting power | EUGENE BIFULCO | energy_progress |
| 11/26/2024 | Permanent certificate | EUGENE BIFULCO | energy_progress |
| 11/26/2024 | Lighting controls | EUGENE BIFULCO | energy_progress |
| 11/26/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 11/26/2024 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | Interior lighting power | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | HVAC-R and service water piping design and insulation | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | Lighting controls | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | Permanent certificate | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | Shutoff dampers | EUGENE BIFULCO | energy_progress |
| 11/25/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |