RoofUnder Construction11p · 6 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
Mechanical Systems · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS SEE ATTACHED PLANS Designated Primary Site supervisor: Jesus Decola
On file for this project
2 documents · 1 drawing sheet
VARIOUS ALTERATIONS TO PLUMBING/SPRINKLER SYSTEMS ON 19TH FLOOR
On file for this project
41 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 213 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
VARIOUS ALTERATIONS TO PLUMBING/SPRINKLER SYSTEMS ON 19TH FLOOR
On file for this project
41 documents
ConEd Exterior Roof repairs at 20th & 21st Fl per plans: Repairs, Removal and replacement of the existing roof membrane, flashing, scupper, leader, gutter, masonry, concrete, stone spall & dutchman. Install new pavers & plant tray.
On file for this project
7 documents
Replace existing wall mounted AC units.
On file for this project
16 documents
Floor 202 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
VARIOUS ALTERATIONS TO PLUMBING/SPRINKLER SYSTEMS ON 19TH FLOOR
On file for this project
41 documents
ConEd Exterior Roof repairs at 20th & 21st Fl per plans: Repairs, Removal and replacement of the existing roof membrane, flashing, scupper, leader, gutter, masonry, concrete, stone spall & dutchman. Install new pavers & plant tray.
On file for this project
7 documents
Floor 195p · 2 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
VARIOUS ALTERATIONS TO PLUMBING/SPRINKLER SYSTEMS ON 19TH FLOOR
On file for this project
41 documents · 3 drawing sheets
ConEd Exterior Roof repairs at 20th & 21st Fl per plans: Repairs, Removal and replacement of the existing roof membrane, flashing, scupper, leader, gutter, masonry, concrete, stone spall & dutchman. Install new pavers & plant tray.
On file for this project
7 documents · 2 drawing sheets
Floor 18
Floor 171 filing · 8 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Replace existing wall mounted AC units.
On file for this project
16 documents
Floor 163p · 2 filings · 12 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Modification to sprinkler system on 16th floor
On file for this project
13 documents · 3 drawing sheets
Replace existing wall mounted AC units.
On file for this project
16 documents
Floor 15
Floor 14
Floor 13
Floor 12Under Construction1 filing · 6 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Demo existing condensing unit, air handler and all associated ductwork and install new 5 ton split system units and ductwork.. No new penetrations.
On file for this project
6 documents
Floor 11
Floor 102 filings · 8 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Modification to existing sprinkler system
On file for this project
4 documents
Modifications to existing mechanical system.
On file for this project
6 documents
Floor 9
Floor 8
Floor 7
Floor 6Under Construction1 filing · 2 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 5Under Construction1 filing · 2 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 4Under Construction2 filings · 6 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
ConEd Exterior Facade & Cornice repairs at 4th floor (Top of 3rd Floor Southwest Roof) as per plans filed including: Limestone cleaning, joint re-pointing and dentil replacement.
On file for this project
4 documents
Floor 3Under Construction1 filing · 2 docs
ArchitectureGeneralMechanicalStructural
Issued Permit Scope
General Construction · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Floor 2Under Construction6p · 5 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Modifications to existing sprinkler system on second floor
On file for this project
12 documents · 4 drawing sheets
FILING FOR STRUCTURAL WORK ASSOCIATED WITH 2nd FLOOR PA4 MECHANICAL ROOM AS PER PLANS SUBMITTED HEREWITH.
On file for this project
15 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 1Under Construction2 filings · 9 docs
MechanicalStructural
Issued Permit Scope
Mechanical Systems · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
FILING FOR MECHANICAL UPGRADE AHU OF 2ND FLOOR 'PA4 MECHANICAL ROOM AS PER PLANS SUBMITTED HEREWITH.
On file for this project
7 documents
Cellar1 filing · 20 docs
Plumbing
Issued Permit Scope
Plumbing
VARIOUS ALTERATIONS TO PLUMBING/SPRINKLER SYSTEMS ON 19TH FLOOR
On file for this project
41 documents
Site & exteriorUnder Construction6 filings · 20 docs
ArchitectureCivilEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 3 drawing sheets
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
11 documents · 7 drawing sheets
Voluntary installation of new EV Charge Station. No change in use egress or occupancy under this application
On file for this project
4 documents · 12 drawing sheets
Latest 3 of 6 filings on this floor.
Filed — no permit issued2 filings · 20 docs
ArchitectureCivilDMElectricalGeneralMechanicalPlumbingStructural
No filed description on record for this project.
On file for this project
6 documents · 12 drawing sheets
STRUCTURAL WORK IN CONJUNCTION WITH CHILLER REPLACEMENT AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
19 documents · 12 drawing sheets