| Owner | Filings | Most Recent |
|---|---|---|
| 130 W 67TH ST | 2 | 07/08/2026 |
| 130 W 67TH LLC | 5 | 03/22/2026 |
| YORK RESTORATION CORP. | 5 | 03/22/2026 |
| TOULANE OWNERS CORP | 97 | 03/22/2026 |
| JOULAINE OWNERS CORP. | 1 | 03/22/2026 |
| HOFFMAN MANAGEMENT | 23 | 03/22/2026 |
| 130 WEST 67 ST. TOULAINE | 1 | 03/22/2026 |
| 130 W 67 ST TOULAINE | 2 | 03/22/2026 |
| GALICIA CONTRACTING RESTORATIO | 4 | 03/21/2026 |
| TULAINE OWNERS | 10 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AJT ARCHITECTURE, PLLC | 3 | 04/23/2025 |
| ADS&Y INC. | 6 | 03/29/2024 |
| KRISTIN LUKS ARCHITECTURE, PLLC | 4 | 11/10/2023 |
| HERO ARCHITECTS | 3 | 05/25/2022 |
| ROBERT GERMAIN JR. PE | 3 | 03/02/2022 |
| STONE ARCHITECTURE & ENERGY DPC | 2 | 08/13/2020 |
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 07/25/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 14 | 03/21/2026 |
| STONE ENGINEERING & ARCHITECTURE DP | 2 | 03/21/2026 |
| JME BUILDING CONSULTING, LLC | 1 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J & M STRONGWATER LLC | General Contractor | 4 | 03/21/2026 |
| LCS RESTORATION CORP | General Contractor | 4 | 07/08/2026 |
| E&E GENERAL CONTRACTORS | General Contractor | 3 | 03/21/2026 |
| NYC REMOLDERS INC | General Contractor | 3 | 03/21/2026 |
| GEO CREATE SOLUTIONS INC | General Contractor | 2 | 03/21/2026 |
| YORK RESTORATION CORP | General Contractor | 2 | 03/21/2026 |
| WHITE HALL RESTORATION | Electrical | 1 | 03/21/2026 |
| AMERIFLO PLUMBING AND HEA | Plumbing | 1 | 07/08/2026 |
| EZ RUNER CONSTRUCTION CORP | Plumbing | 1 | 07/08/2026 |
| FRED SMITH P&H CO INC | Plumbing | 1 | 07/08/2026 |
| HI-TECH PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| NY CITY PLUMBER CORP | Plumbing | 1 | 07/08/2026 |
| BRANDL ELECTRIC INC. | Electrical | 1 | 03/22/2026 |
| TESTERMAN PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| COSIMO CURCIO | Electrical | 1 | 03/21/2026 |
| CURCIO COSIMO | Electrical | 1 | 03/21/2026 |
| DAIDONE, S | Electrical | 1 | 03/21/2026 |
| GLEICH, BERNARD | Electrical | 1 | 03/21/2026 |
| TODARO JOSEPH | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ADS & Y INC | 3783 | 2 | 11/30/2023 |
| WINTON GROUP ARCHITECTURE | 4343 | 4 | 11/10/2023 |
| ROBERT F. GERMAIN JR. PE | 5100 | 3 | 03/02/2022 |
| STONE ENGINEERING & ARCHI | 1362 | 1 | 12/26/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | AMERIFLO PLUMBING AND HEA | 03/27/2025 |
| DOB NOW | General Construction | Signed-off | E&E GENERAL CONTRACTORS | 03/25/2025 |
| DOB NOW | Plumbing | Signed-off | HI-TECH PLUMBING & HEATIN | 12/26/2023 |
| DOB NOW | General Construction | Signed-off | NYC REMOLDERS INC | 09/19/2023 |
| DOB NOW | Plumbing | Signed-off | EZ RUNER CONSTRUCTION COR | 01/30/2023 |
| DOB NOW | General Construction | Signed-off | GEO CREATE SOLUTIONS INC | 01/26/2023 |
| DOB NOW | General Construction | Signed-off | J M STRONGWATER | 01/27/2022 |
| DOB NOW | Plumbing | Signed-off | TESTERMAN PLBG & HTG INC | 12/28/2021 |
| DOB NOW | General Construction | Signed-off | J M STRONGWATER | 12/03/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | LCS RESTORATION CORP | 11/06/2021 |
| DOB NOW | Plumbing | Signed-off | NY CITY PLUMBER CORP | 09/14/2021 |
| DOB NOW | Boiler Equipment | Signed-off | ABILENE, INC | 09/13/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | LCS RESTORATION CORP | 08/17/2020 |
| DOB NOW | Plumbing | Permit Issued | FRED SMITH P&H CO INC | 03/20/2020 |
| DOB NOW | Construction Fence | Permit Issued | YORK RESTORATION CORP | 07/26/2018 |
| BIS | PL | ISSUED | MCMANUS MECH MAINT P&H INC | 09/29/2025 |
| BIS | OT | ISSUED | LCS RESTORATION CORP | 03/17/2021 |
| BIS | OT | ISSUED | LCS RESTORATION CORP | 11/19/2020 |
| BIS | OT | ISSUED | YORK RESTORATION CORP | 06/17/2019 |
| BIS | PL | ISSUED | WYNNE PLBG & HEATING CORP | 12/20/2018 |
| BIS | OT | ISSUED | ATLAS & DESIGN CONTRACTORS | 12/18/2018 |
| BIS | OT | ISSUED | YORK RESTORATION CORP | 06/25/2018 |
| BIS | PL | ISSUED | IDEAL PLUMBING CORP | 01/29/2018 |
| BIS | OT | ISSUED | A.G.C CONTRACTORS INC | 01/17/2018 |
| BIS | PL | ISSUED | SUPERIOR PLUMBING & HEATING | 12/26/2017 |
| BIS | OT | ISSUED | DR CARDINAL INC | 12/13/2017 |
| BIS | OT | ISSUED | KORNEL DESIGN INC | 09/15/2017 |
| BIS | OT | ISSUED | AMERICAN C CONST INC | 09/21/2016 |
| BIS | OT | ISSUED | AMERICAN INDUSTRIES LLC | 02/23/2016 |
| BIS | OT | ISSUED | KORNEL DESIGN INC | 02/02/2016 |
| BIS | OT | ISSUED | GALICIA CONTRACTING & REST. | 11/13/2015 |
| BIS | PL | ISSUED | ULTIMATE PLBG AND HTG COR | 11/02/2015 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 10/07/2015 |
| BIS | PL | ISSUED | FLYTIGER P & H LTD | 06/19/2015 |
| BIS | MH | ISSUED | AMERICAN C CONST INC | 06/08/2015 |
| BIS | OT | ISSUED | AMERICAN C CONST INC | 06/08/2015 |
| BIS | PL | ISSUED | EVERYDAY MECHANICAL CORP | 01/26/2015 |
| BIS | OT | ISSUED | AMERICAN INDUSTRIES LLC | 01/20/2015 |
| BIS | MH | ISSUED | DUTCHMAN CONTRACTING INC | 12/19/2014 |
| BIS | OT | ISSUED | DUTCHMAN CONTRACTING INC | 12/19/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/26/2019 | Permit Issued | FRED SMITH P&H CO INC | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/11/2025 | Complete | ELECTRIC A/C INC | General Wiring |
| 12/23/2024 | Complete | ELECTRIC A/C INC | — |
| 07/30/2024 | Complete | RAL-BAR ELECTRIC INC | General Wiring |
| 03/09/2024 | Complete | KINGS ELECTRIC CO., INC. | — |
| 11/08/2023 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 10/29/2023 | Complete | SEABRAVE ELECTRIC CORP | General Wiring |
| 08/18/2023 | Complete | VERTEX ELECTRIC CORP. | General Wiring |
| 09/02/2022 | Complete | ABILENE ELECTRIC INC | Boiler Controls |
| 01/12/2022 | Complete | MONFORTE ELECTIRC CORP | General Wiring |
| 07/09/2021 | Complete | ABILENE ELECTRIC INC | — |
| 01/30/2021 | Permit Issued | JOSEPH SGROI & SONS, INC. | General Wiring |
| 11/30/2020 | Complete | ALL CITY ELECTRICAL INC | General Wiring |
| 11/06/2020 | Complete | ALL WAYS ELECTRIC CORP.W | General Wiring |
| 10/08/2020 | Complete | NASH ELECTRIC SERVICES IN | — |
| 04/27/2020 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2020 | Signed-off | LCS RESTORATION CORP | Sidewalk Shed |
| 07/25/2018 | Permit Issued | YORK RESTORATION CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/09/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/20/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/15/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/08/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/03/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/29/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/14/2023 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 07/26/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/10/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/06/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/08/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/18/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/09/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/15/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/02/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/20/2021 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/06/2025 | Final | Anthony Tavella | progress |
| 12/01/2023 | Final | SIDERIS CARAMINTZOS | progress |
| 12/01/2023 | Energy Code Compliance Inspections | SIDERIS CARAMINTZOS | progress |
| 12/01/2023 | Fire-Resistant Penetrations and Joints | SIDERIS CARAMINTZOS | special |
| 11/25/2023 | Energy Code Compliance Inspections | SIDERIS CARAMINTZOS | progress |
| 11/20/2023 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 11/16/2023 | Fire-Resistant Penetrations and Joints | SIDERIS CARAMINTZOS | special |
| 11/16/2023 | Final | SIDERIS CARAMINTZOS | progress |
| 10/31/2023 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 07/26/2023 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 05/16/2022 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 05/16/2022 | Lighting in dwelling units | KRISTIN LUKS | energy_progress |
| 05/16/2022 | Final | KRISTIN LUKS | progress |
| 03/02/2022 | Fire-Resistant Penetrations and Joints | Robert Germain Jr. | special |
| 08/23/2021 | Insulation placement and R values | martin hero | energy_progress |
| 08/10/2021 | Fire-Resistance Rated Construction | martin hero | progress |
| 08/10/2021 | Energy Code Compliance Inspections | martin hero | progress |
| 08/09/2021 | Final | martin hero | progress |
| 05/25/2021 | Fire-Resistant Penetrations and Joints | Robert Germain Jr. | special |
| 08/13/2020 | Final | MUHAMMAD MUHAYSIN | progress |
| 12/23/2019 | Fire-Resistant Penetrations and Joints | MUHAMMAD MUHAYSIN | special |
| 12/23/2019 | Energy Code Compliance Inspections | MUHAMMAD MUHAYSIN | progress |