Activity
Projects by first filing month34 projects all-time
0134Jul '19 · 1Nov '19 · 2Jan '20 · 1Feb '20 · 2Jun '20 · 1Sep '20 · 2Oct '20 · 2Mar '21 · 1Jun '21 · 1Jul '21 · 1Oct '21 · 2Nov '21 · 1Jan '22 · 2May '23 · 1Sep '23 · 3Oct '23 · 1Nov '23 · 1Jan '24 · 1Feb '24 · 1Aug '24 · 1Apr '25 · 1May '25 · 2Mar '26 · 1Jul '26 · 1Aug '26 · 12020202120222023202420252026
bars = month · line = 3-mo average
Portfolio status
Browse projects →
Open permit618%
Signed off2471%
Filed only412%
By project type
Alteration34
Most active buildings
All buildings →
1238 2 AVENUEMANHATTAN · latest 08/21/2026
2 projects
509 WEST 140 STREETMANHATTAN · latest 11/08/2021
2 projects
38-03 BROADWAYQUEENS · latest 09/17/2024
2 projects
9 CHATHAM SQUAREMANHATTAN · latest 11/02/2020
1 projects
235 CANAL STREETMANHATTAN · latest 10/12/2023
1 projects
130 WEST 67 STREETMANHATTAN · latest 12/26/2023
1 projects
Key relationships
Everyone →
Most recent projects
All projects →
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
M01448776 ↗1238 2 AVENUE
MANHATTAN
AlterationFiled — no permit on record08/21/2026—
Design ADS&Y INC.
—
Q01427392 ↗21-39 36 STREET
QUEENS
AlterationFiled — no permit on record07/14/2026—
Design ADS&Y INC.
—
B01359565 ↗715 LORIMER STREET
BROOKLYN
AlterationPermit Issued03/02/202606/12/2026
Design ADS&Y INC.
REMOVE THREE UNREGISTERD BOILERS AND INSTALL TO REGISTER THREE NEW BOILERS AT 715 LORIMER STREET FOR FOUR OF THE SIX DWELING UNITS. THE OTH…
M01206858 ↗1261 5 AVENUE
MANHATTAN
AlterationPermit Issued04/11/202505/18/2026
Design ADS&Y INC.
REPLACE GAS PIPING FROM THE LADWIG VALVE TO THE (NEW) REPLACED BOILER 3 (B3). BOILER WORK TYPE FOR B3 WAS FILED UNDER JOB # M01206858-I1. …
Q01228304 ↗147-34 3 AVENUE
QUEENS
AlterationPermit Issued05/30/202503/05/2026
Design ADS&Y INC.
Contractor TERRA PETRA LLC
FILING FOR 2ND FLOOR EXTENSION PLAN APPROVAL, RESCIND THE STOP WORK ORDER, AND COMPLETE THE WORK. NO CHANGE IN USAGE OCCUPANCY OR EGRESS.
Q00166015 ↗33-14 23 AVENUE
QUEENS
AlterationSigned-off07/29/201911/07/2025
Design ADS&Y INC.
Contractor THOMAS FAY
PROPOSED TO INSTALL SPRINKLERS SYSTEM FOR CLOTHES COMMERCIAL GAS DRYER AT EXISTING, UNDER CO # 14928, LAUNDROMAT, RESOLVE ECB VIOLATIONS # 3…
Counts cover all 34 projects (34 DOB NOW). Dated by first filing; BIS projects by first permit issuance.
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
ADS&Y INC.3308/21/2026
GEORGIOS G GEORGOPOULOS, R.A.110/21/2020
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
J.A. MECH. PLBG. & HTG IN808/09/2026
NYC REMOLDERS INC404/15/2024
PEGASUS P & H CORP307/15/2022
HI-TECH PLUMBING & HEATIN204/15/2024
IPS PLUMBING CORP210/14/2021
AMPC CARPENTRY CORP106/29/2020
BYPASS MECHANICAL CORP109/02/2020
C JAMES PLBG & HTG INC101/08/2020
CLIMATE SOLUTIONS INC111/22/2019
EVERYDAY MECHANICAL CORP104/04/2022
GULLY HEATING & COOLING I106/22/2024
HYDROTAC SERVICES LLC106/15/2026
KCM PLUMBING & HEATING CO109/05/2024
KODRA NYC CONTRACTING INC106/11/2026
METRO MECHANICAL LLC109/05/2024
N & D PLBG & HTG CORP110/21/2020
N & D PLBG.AND HTG CORP110/21/2020
NEW YORK DISTRIBUTORS HEA110/12/2021
NY BUILDING ASSOCIATES IN103/04/2024
PROCORE MECHANICAL CORP104/06/2022
R&A HEATING & CONTRG CO.I110/12/2021
ROLANDO MECHANICAL OF NY111/02/2023
SPACE AIR CONDITIONING CO105/02/2025
SYSTEMS 2000 PLBG SVCS LL109/01/2021
TERRA PETRA LLC106/11/2026
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
DELMAR MANAGEMENT SERVICES210/14/2021
PALATI REALTY208/30/2024
421-429 FAILE ST LLC106/22/2024
82ND STREET TENANTS CORP104/04/2022
ALEXANDER WOLF & CO.109/01/2021
GPG MANAGEMENT108/21/2026
KODRA NYC CONTRACTING, INC106/11/2026
MAXX PROPERTIES107/08/2021
METROPOLIS INTERNATIONAL REALTY107/14/2026
VISTA ON 5TH CORP.106/15/2026
WESTSIDE MARKET108/09/2026
ZOHIOS REALTY ASSOCIATES LLC105/02/2025
34 DOB NOW projects, anchored the same way as Buildings Worked. Status is the project's permit state today: open = at least one permit currently issued. BIS projects show their raw permit status and are not counted as open.
All 34Open permit 6Signed off 24Filed only 4
34 projects
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
M01448776 ↗1238 2 AVENUE
MANHATTAN
AlterationFiled — no permit on record08/21/2026—
Design ADS&Y INC.
—
Q01427392 ↗21-39 36 STREET
QUEENS
AlterationFiled — no permit on record07/14/2026—
Design ADS&Y INC.
—
B01359565 ↗715 LORIMER STREET
BROOKLYN
AlterationPermit Issued03/02/202606/12/2026
Design ADS&Y INC.
REMOVE THREE UNREGISTERD BOILERS AND INSTALL TO REGISTER THREE NEW BOILERS AT 715 LORIMER STREET FOR FOUR OF THE SIX DWELING UNITS. THE OTH…
M01206858 ↗1261 5 AVENUE
MANHATTAN
AlterationPermit Issued04/11/202505/18/2026
Design ADS&Y INC.
REPLACE GAS PIPING FROM THE LADWIG VALVE TO THE (NEW) REPLACED BOILER 3 (B3). BOILER WORK TYPE FOR B3 WAS FILED UNDER JOB # M01206858-I1. …
Q01228304 ↗147-34 3 AVENUE
QUEENS
AlterationPermit Issued05/30/202503/05/2026
Design ADS&Y INC.
Contractor TERRA PETRA LLC
FILING FOR 2ND FLOOR EXTENSION PLAN APPROVAL, RESCIND THE STOP WORK ORDER, AND COMPLETE THE WORK. NO CHANGE IN USAGE OCCUPANCY OR EGRESS.
Q00166015 ↗33-14 23 AVENUE
QUEENS
AlterationSigned-off07/29/201911/07/2025
Design ADS&Y INC.
Contractor THOMAS FAY
PROPOSED TO INSTALL SPRINKLERS SYSTEM FOR CLOTHES COMMERCIAL GAS DRYER AT EXISTING, UNDER CO # 14928, LAUNDROMAT, RESOLVE ECB VIOLATIONS # 3…
M01216743 ↗1238 2 AVENUE
MANHATTAN
AlterationSigned-off05/02/202505/29/2025
Design ADS&Y INC.
OM THE ROOF, REMOVE EXISTING 10-TON YORK CONDENSER, RELOCATE TO ITS LOCATION 3-TON MITSUBISHI UNIT AND IN MITSUBISHI LOCATION INSTALL TWO NE…
Q00968524 ↗38-03 BROADWAY
QUEENS
AlterationSigned-off01/30/202409/17/2024
Design ADS&Y INC.
LEGALIZE TWO BATHROOMS (WCs (2), LAVs (2)) AND A NON-RESIDENTIAL SINK. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01098350 ↗38-03 BROADWAY
QUEENS
AlterationSigned-off08/26/202408/29/2024
Design ADS&Y INC.
INSTALLATION OF FOUR IDENTICAL WEIL MAcLAIN BOILERS, MODEL CGa 25/3, GAS FIRED WITH HEAT INPUT 38,000 BTU/HR FOR HEATING THE FOUR RESIDENTIA…
Q00955623 ↗31-01 BROADWAY
QUEENS
AlterationSigned-off11/02/202305/13/2024
Design ADS&Y INC.
PLUMBING WORK TYPE FOR LEGALIZATION & REGISTRATION OF GAS FIRED CADET BOILER, MODEL CDN100 WITH MAXIMUM HEAT INPUT OF 100 MBTU/HR & RESOLVE …
M00906296 ↗1076 1 AVENUE
MANHATTAN
AlterationSigned-off09/01/202303/13/2024
Design ADS&Y INC.
PLUMBING WORK ASSOCIATED WITH INTERIOR RENOVATION TO EXISTING APARTMENT #7E. REMOVAL AND REEPLACEMENT OF TWO BATHROOMS PLUMBING FIXTURES. …
M00871905 ↗223 EAST 78 STREET
MANHATTAN
AlterationPermit Issued05/19/202303/12/2024
Design ADS&Y INC.
Interior renovations to existing apartment 1B, removal and installation of interior nonbearing partitions, fixtures and finishes. no change…
Q00997866 ↗18-38 131 STREET
QUEENS
AlterationSigned-off02/01/202403/01/2024
Design ADS&Y INC.
REPLACE TWO ROOFTOP HVAC UNITS ORIGINALLY FILED UNDER BIS JOB # 400481769. NO CHANGE IS USE EGRESS OR OCCUPANCY.
M00894993 ↗130 WEST 67 STREET
MANHATTAN
AlterationSigned-off09/07/202312/26/2023
Design ADS&Y INC.
REPLACE BATHROOM FIXTURES (LAV, WC,), REMOVE AND REPLACE EXISITNG BATHTUB WITH NEW SHOWER. RELOCATE KITCHEN FIXTURES (SINK, DISHWASHER AND …
S00932312 ↗370 DARLINGTON AVENUE
STATEN ISLAND
AlterationSigned-off09/12/202312/01/2023
Design ADS&Y INC.
PROPOSED INSTALLATION IN REAR YARD OF ONE 20/18 kW EMERGENCY GENERATOR, MAKE: GENERAC, MODEL: 7038, FOR ONE FAMILY RESIDENTIAL HOUSE. NO CH…
M00946814 ↗235 CANAL STREET
MANHATTAN
AlterationFiled — no permit on record10/12/2023—
Design ADS&Y INC.
—
Q00623109 ↗35-40 82 STREET
QUEENS
AlterationSigned-off11/05/202104/28/2022
Design ADS&Y INC.
LEGALIZE LAUNDRY ROOM WITH ASSOCIATED PLUMBING WORK FOR GAS, WATER AND SANITARY PIPING. REPLACE ILLEGAL GAS PIPING AS SHOWN IN THE PLANS. …
Q00656720 ↗142-30 SANFORD AVENUE
QUEENS
AlterationSigned-off01/06/202202/16/2022
Design ADS&Y INC.
Remove gas lines to the dryers and cap lines to the source. Legalize and make necessary adjustments as per code the washers.
B00271992 ↗1326 DEAN STREET
BROOKLYN
AlterationSigned-off11/27/201902/15/2022
Design ADS&Y INC.
PLUMBING WORK TYPE FOR BATHROOMS AND KITCHENS AT BASEMENT, 1ST 2ND AND 3RD FLOORS. NO CHANGE IN USE EGRESS OR OCCUPANCY.
B00657290 ↗8829 FT HAMILTON PARKWAY
BROOKLYN
AlterationSigned-off01/07/202201/17/2022
Design ADS&Y INC.
REPAIR FIRE DAMAGED APARTMENT D3.
Q00489430 ↗87-04 UNION TURNPIKE
QUEENS
AlterationPermit Issued03/23/202111/23/2021
Design ADS&Y INC.
REPLACE GAS PIPING THROUGHOUTTHIS 1-FAMILY HOUSE. NO CHANGE IN USE EGRESS OR OCCUPANCY.
M00601401 ↗509 WEST 140 STREET
MANHATTAN
AlterationSigned-off10/14/202111/08/2021
Design ADS&Y INC.
REPLACEMENT OF OIL FIRED HWH WITH GAS FIRED WATER HEATER. INSTALLATION OF HOLDING TANK, AND ASSOCIATED GAS PIPING AND GAS PLUMBING WORK FOR …
M00596476 ↗509 WEST 140 STREET
MANHATTAN
AlterationSigned-off10/14/202111/03/2021
Design ADS&Y INC.
Filing as built conditions to obtain DOB Boiler Approval. Replace oil filed boiler and burner and convert from oil to gas. Resolve DOB ins…
Q00545972 ↗22-49 80 STREET
QUEENS
AlterationSigned-off06/28/202111/03/2021
Design ADS&Y INC.
INTERIOR RENOVATIONS OF EXISITNG ONE-FAMILY HOUSE AS SHOWN ON THE DRAWINGS. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00253400 ↗21-51 31 STREET
QUEENS
AlterationSigned-off11/22/201910/28/2021
Design ADS&Y INC.
REPLACE EXISITNG TWO TRANE PACKAGED ROOFTOP HVAC UNITS ON EXISITNG DUNNAGE WITH NEW AND INSTALL THREE NEW LG HEAT PUMPS ON EXISITNG DUNNAGE.…
Q00396909 ↗37-01 30 AVENUE
QUEENS
AlterationSigned-off10/20/202009/14/2021
Design ADS&Y INC.
Remove and replace kitchen plumbing fixtures (stove and sink) and bathroom plumbing fixtures in apartments 2, 7, 8, 12, and 14 on existing r…
M00320438 ↗321 WEST 90 STREET
MANHATTAN
AlterationSigned-off02/27/202008/30/2021
Design ADS&Y INC.
LEGALIZE ACCESSORY LAUNDRY ROOM FOR BUILDING'S RESIDENTS AS SHOWN ON THE PLANS AND RESOLVE ECB VIOLATIONS. NO CHANGE IN USE EGRESS OR OCCUP…
Q00550720 ↗79-01 35 AVENUE
QUEENS
AlterationFiled — no permit on record07/08/2021—
Design ADS&Y INC.
—
X00273970 ↗1960 ANTHONY AVE
BRONX
AlterationSigned-off01/08/202002/08/2021
Design ADS&Y INC.
AT CELLAR LEVEL LEGALIZE GAS LINE INSTALLED FOR A DRYER, AND WATER & WASTE LINES FOR WASHER. NO CHANGE IN USE EGREES OR OCCUPANCY.
Q00363184 ↗31-02 30 AVENUE
QUEENS
AlterationSigned-off06/29/202012/09/2020
Design ADS&Y INC.
REPLACEMENT OF ROOFTOP 5 TON CONDENSER ON EXISTING DUNN. NO CHANGE OF USE EGRESS OR OCCUPANCY.
M00292744 ↗164 WEST 88 STREET
MANHATTAN
AlterationPermit Issued02/03/202011/06/2020
Design ADS&Y INC.
Subsequent filing is made to satisfy DOB plumbing inspector's comment, to list HVAC & Dryer for Gas Usage under Other Gas Appliances Equipm…
Q00407213 ↗32-10 30 AVENUE
QUEENS
AlterationSigned-off10/21/202011/05/2020INSTALLATION OF NEW SPRINKLER SYSTEM OF 7-SPRINKLER HEADS AT 1ST FLOOR STORE (DRY CLEANERS) ONLY, WITH A NEW 2 WATER SERVICE FOR SPRINKLER S…
M00401610 ↗9 CHATHAM SQUARE
MANHATTAN
AlterationSigned-off09/23/202011/02/2020
Design ADS&Y INC.
DUE TO SHUT DOWN (GOING OUT OF BUSSINESS) OF EXISITNG RESTAURANT, REMOVE ALL ASSOCIATED PLUMBING FIXTURES AND GAS FIRED EQUIPMENTS. ONLY BA…
Q00379384 ↗31-11 BROADWAY
QUEENS
AlterationSigned-off09/02/202009/14/2020
Design ADS&Y INC.
INSTALL SLOP SINK ON THE SECOND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY.
Click a row for this entity's own projects, plans and documents at that building.
BuildingFilingsMost Recent
1238 2 AVENUE ↗208/21/2026
715 LORIMER STREET ↗508/09/2026
21-39 36 STREET ↗207/14/2026
1261 5 AVENUE ↗306/15/2026
147-34 3 AVENUE ↗306/11/2026
38-03 BROADWAY ↗408/30/2024
18-38 131 STREET ↗306/22/2024
370 DARLINGTON AVENUE ↗206/04/2024
1076 1 AVENUE ↗604/15/2024
130 WEST 67 STREET ↗211/30/2023
31-01 BROADWAY ↗211/02/2023
235 CANAL STREET ↗110/12/2023
223 EAST 78 STREET ↗105/19/2023
33-14 23 AVENUE ↗307/15/2022
1326 DEAN STREET ↗604/06/2022
35-40 82 STREET ↗204/04/2022
37-01 30 AVENUE ↗302/02/2022
8829 FT HAMILTON PARKWAY ↗101/07/2022
142-30 SANFORD AVENUE ↗101/06/2022
509 WEST 140 STREET ↗210/14/2021
22-49 80 STREET ↗410/12/2021
321 WEST 90 STREET ↗409/01/2021
87-04 UNION TURNPIKE ↗307/08/2021
79-01 35 AVENUE ↗107/08/2021
164 WEST 88 STREET ↗311/30/2020
32-10 30 AVENUE ↗110/21/2020
9 CHATHAM SQUARE ↗109/23/2020
31-11 BROADWAY ↗109/02/2020
31-02 30 AVENUE ↗106/29/2020
1960 ANTHONY AVE ↗101/08/2020
21-51 31 STREET ↗111/22/2019
▾Special Inspection Requirements — 150
DateRequirementBuildingInspectorRole
08/20/2026Mechanical Systems1238 2 AVENUESIDERIS CARAMINTZOSspecial
08/20/2026Tenant Protection Plan Compliance1238 2 AVENUESIDERIS CARAMINTZOSspecial
08/20/2026Final1238 2 AVENUESIDERIS CARAMINTZOSprogress
08/20/2026HVAC-R and service water piping design and insulation1238 2 AVENUESIDERIS CARAMINTZOSenergy_progress
08/20/2026HVAC-R and service water heating equipment1238 2 AVENUESIDERIS CARAMINTZOSenergy_progress
08/20/2026Maintenance information1238 2 AVENUESIDERIS CARAMINTZOSenergy_progress
08/20/2026HVAC-R and service water heating system controls1238 2 AVENUESIDERIS CARAMINTZOSenergy_progress
08/11/2026Tenant Protection Plan Compliance715 LORIMER STREET—special
08/11/2026Fire-Resistant Penetrations and Joints715 LORIMER STREETSIDERIS CARAMINTZOSspecial
08/11/2026Heating Systems715 LORIMER STREETSIDERIS CARAMINTZOSspecial
08/11/2026Lowest Floor Elevation715 LORIMER STREETSIDERIS CARAMINTZOSprogress
08/11/2026HVAC-R and service water piping design and insulation715 LORIMER STREETSIDERIS CARAMINTZOSenergy_progress
08/11/2026HVAC-R and service water heating equipment715 LORIMER STREETSIDERIS CARAMINTZOSenergy_progress
08/11/2026HVAC-R and service water heating system controls715 LORIMER STREETSIDERIS CARAMINTZOSenergy_progress
08/10/2026Fire-Resistant Penetrations and Joints715 LORIMER STREETSIDERIS CARAMINTZOSspecial
08/10/2026Tenant Protection Plan Compliance715 LORIMER STREET—special
07/22/2026Fire-Resistant Penetrations and Joints715 LORIMER STREETSIDERIS CARAMINTZOSspecial
07/22/2026Tenant Protection Plan Compliance715 LORIMER STREETSIDERIS CARAMINTZOSspecial
07/22/2026Fire-Resistance Rated Construction715 LORIMER STREETSIDERIS CARAMINTZOSprogress
07/22/2026Final715 LORIMER STREETSIDERIS CARAMINTZOSprogress
07/08/2026Fire-Resistant Penetrations and Joints21-39 36 STREETSIDERIS CARAMINTZOSspecial
07/07/2026Final21-39 36 STREETSIDERIS CARAMINTZOSprogress
07/07/2026Fire-Resistant Penetrations and Joints21-39 36 STREETSIDERIS CARAMINTZOSspecial
06/15/2026Tenant Protection Plan Compliance1261 5 AVENUESIDERIS CARAMINTZOSspecial
06/15/2026Heating Systems1261 5 AVENUESIDERIS CARAMINTZOSspecial
06/15/2026Fire-Resistant Penetrations and Joints1261 5 AVENUESIDERIS CARAMINTZOSspecial
06/15/2026Maintenance information1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/15/2026HVAC-R and service water piping design and insulation1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/15/2026HVAC-R and service water heating system controls1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/15/2026HVAC-R and service water heating equipment1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/12/2026Maintenance information1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/12/2026HVAC-R and service water heating system controls1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/12/2026HVAC-R and service water piping design and insulation1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/12/2026HVAC-R and service water heating equipment1261 5 AVENUESIDERIS CARAMINTZOSenergy_progress
06/12/2026Tenant Protection Plan Compliance1261 5 AVENUESIDERIS CARAMINTZOSspecial
06/12/2026Heating Systems1261 5 AVENUESIDERIS CARAMINTZOSspecial
06/12/2026Fire-Resistant Penetrations and Joints1261 5 AVENUESIDERIS CARAMINTZOSspecial
06/08/2026Lighting in dwelling units147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
06/08/2026Air barrier - visual inspection147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
06/08/2026Fenestration areas147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
06/08/2026Preliminary147-34 3 AVENUESIDERIS CARAMINTZOSprogress
06/08/2026Insulation placement and R values147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
06/08/2026Fenestration air leakage147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
06/08/2026Fenestration and door U-factor and product ratings147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
06/08/2026Fire-Resistant Penetrations and Joints147-34 3 AVENUESIDERIS CARAMINTZOSspecial
06/08/2026Structural Stability – Alterations of existing buildings147-34 3 AVENUEMICHAEL KARANTINIDIS, P.E.special
06/08/2026Energy Code Compliance Inspections147-34 3 AVENUESIDERIS CARAMINTZOSprogress
06/08/2026Final147-34 3 AVENUESIDERIS CARAMINTZOSprogress
06/08/2026Fire-Resistance Rated Construction147-34 3 AVENUESIDERIS CARAMINTZOSprogress
04/28/2026Fenestration and door U-factor and product ratings147-34 3 AVENUESIDERIS CARAMINTZOSenergy_progress
Latest 50 of 150.
▾Documents — 537 on file (BIS + DOB NOW)
▸Plans & Drawings90
▸DOB NOWPlans/Sketch61
Showing 3 of 61 on file for this type
▸DOB NOWPlans/Sketch - Plumbing21
09/04/2026M00401610-I1 · 9 CHATHAM SQUARERequest digital key ↗
Showing 3 of 21 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler3
08/27/2026Q00407213-I1 · 32-10 30 AVENUERequest digital key ↗
08/26/2026Q00166015-I1 · 33-14 23 AVENUERequest digital key ↗
08/15/2026Q00166015-P1 · 33-14 23 AVENUERequest digital key ↗
▸DOB NOWPlans/Sketch - Plumbing Legalization3
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/28/2026Q00363184-I1 · 31-02 30 AVENUERequest digital key ↗
08/15/2026Q00253400-I1 · 21-51 31 STREETRequest digital key ↗
▸Applications & Permits17
▸DOB NOWLPC Approval/Permit16
09/03/2026M00320438-P1 · 321 WEST 90 STREETOpen ↗
09/03/2026M00320438-S1 · 321 WEST 90 STREETOpen ↗
08/13/2026Q00550720-I1 · 79-01 35 AVENUEOpen ↗
Showing 3 of 16 on file for this type
▸DOB NOWHPD Certification Letter or CPC Special Permit1
08/18/2026B01359565-S2 · 715 LORIMER STREETOpen ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWRestrictive Declaration/Easement 14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Seals & Professional Certifications310
▸DOB NOWProgress Inspector Seal & Signature153
09/26/2026B00271992-P3 · 1326 DEAN STREETOpen ↗
09/26/2026B00271992-P3 · 1326 DEAN STREETOpen ↗
09/23/2026M01448776-I1 · 1238 2 AVENUEOpen ↗
Showing 3 of 153 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature85
09/04/2026M00292744-P1 · 164 WEST 88 STREETOpen ↗
09/04/2026M00292744-I1 · 164 WEST 88 STREETOpen ↗
09/04/2026M00292744-S1 · 164 WEST 88 STREETOpen ↗
Showing 3 of 85 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature72
09/26/2026B00271992-P3 · 1326 DEAN STREETOpen ↗
09/23/2026M01448776-I1 · 1238 2 AVENUEOpen ↗
09/23/2026M01448776-I1 · 1238 2 AVENUEOpen ↗
Showing 3 of 72 on file for this type
▸Safety & Tenant Protection25
▸DOB NOWTenant Protection Plan19
09/03/2026M00320438-S1 · 321 WEST 90 STREETOpen ↗
09/03/2026M00320438-P1 · 321 WEST 90 STREETOpen ↗
08/13/2026X00273970-I1 · 1960 ANTHONY AVEOpen ↗
Showing 3 of 19 on file for this type
▸DOB NOWHPD-1: Anti-Harassment Area Checklist5
08/18/2026B01359565-S2 · 715 LORIMER STREETOpen ↗
Showing 1 of 5 on file for this type
▸DOB NOWCertificate of No Harassment1
08/18/2026B01359565-S2 · 715 LORIMER STREETOpen ↗
▸Environmental & Asbestos69
▸DOB NOWDEP ACP-5: Asbestos Assessment Report69
09/04/2026M00292744-S1 · 164 WEST 88 STREETOpen ↗
09/04/2026M00292744-P1 · 164 WEST 88 STREETOpen ↗
09/03/2026M00320438-P1 · 321 WEST 90 STREETOpen ↗
Showing 3 of 69 on file for this type
▸Energy Compliance6
▸DOB NOWEN2: As Built Energy Analysis.6
09/03/2026M00596476-I1 · 509 WEST 140 STREETOpen ↗
08/13/2026M00601401-I1 · 509 WEST 140 STREETOpen ↗
08/13/2026Q00623109-I1 · 35-40 82 STREETOpen ↗
Showing 3 of 6 on file for this type
▸Approvals, Objections & Sign-offs3
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Cost, Insurance & Ownership1
▸DOB NOWPW3: Cost Affidavit (Before Sign Off)1
08/13/2026Q00166015-I1 · 33-14 23 AVENUEOpen ↗
▸Other Documents9
▸DOB NOWSite Survey: Initial3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWPlot Diagram3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type