← Back
Miscellaneous educational facility
133 WEST 21 STREET
MANHATTAN · Chelsea-Hudson Yards · BIN 1014771
💬 Discuss this project
1911Year Built
12Stories
W9Building Class
C6-3AZoning
115,895 sfGross Floor Area
5Units
LL97 Covered3 Open Violations 2 unresolved · 1 paperwork only ▸FISP: No Report Filed
Miscellaneous educational facility · Owner of record: SS 133 W 21,LLC · 9,924 sf lot · 11.68 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof23p · 8 filings · 20 docs
Floor 121p · 1 filing · 5 docs
Floor 11
Floor 10
Floor 9
Floor 8
Floor 77p · 1 filing · 20 docs
Floor 623p · 3 filings · 20 docs
Floor 5
Floor 4
Floor 3
Floor 21p · 1 filing · 15 docs
Floor 1
Basement1p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SCHOOL OF VISUAL ARTS10507/08/2026
SS 133 W 21,LLC1403/22/2026
SS 133 WEST 21603/22/2026
SS 133 WEST 21ST6303/22/2026
55 133 W 21, LLC203/22/2026
CONSIGLI ASSOCIATES203/22/2026
133 WEST 21303/22/2026
133 WEST 21 ST LLC103/22/2026
MURRAY HILL PROPERTIES403/22/2026
HELMLEY SPEAR INC.1003/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
THORNTON TOMASETTI312/19/2025
WELLWORTH CONSULTING LLC212/19/2025
LAURENCE G. JONES ARCHITECTS, PLLC511/06/2024
EP ENGINEERING LLC1809/19/2024
PAUL PERDEK, PROF. ENG. PLLC206/06/2024
NARINDER CHHABRA306/09/2022
ASHRAF CORP310/31/2020
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CREATIVE TEAM INTERIORS IGeneral Contractor603/21/2026
INTERSYSTEM INSTALLATIONGeneral Contractor607/08/2026
TAURINO MANAGEMENT, INCGeneral Contractor507/08/2026
SPRING SCAFFOLDING LLCGeneral Contractor507/08/2026
SPK/LEWIS CONSTRUCTION LLGeneral Contractor307/08/2026
GENERAL PLUMBING CORPPlumbing207/08/2026
GENERAL PLUMBING CORPFire Protection207/08/2026
NICHOLSON & GALLOWAY, INC.General Contractor203/21/2026
STRUCTURAL PRESERV SYSTEMGeneral Contractor203/21/2026
DPH PLUMBING & HTG CORPPlumbing107/08/2026
SATO CONSTRUCTION CO.INCGeneral Contractor107/08/2026
DEMAR PLUMBING CORPFire Protection107/08/2026
PROSPECT ELECT. SERV INCElectrical103/22/2026
HIG ELECTRIC ASSC NYC INCElectrical103/22/2026
JOSEPH SORTINOElectrical103/21/2026
THE GRENADIER CORPORATIONGeneral Contractor104/09/2026
ACCESS PLUMBING CORPPlumbing107/08/2026
AINSWORTH INCGeneral Contractor107/08/2026
FIREQUEST CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
EP INSPECTIONS AND COMMIS70792012/19/2025
CROSSCHECK INSPECTION SER544106/25/2025
LAURENCE G. JONES ARCHITE55601111/06/2024
SPECIAL TESTING & CONSULT1688204/22/2020
Building Lifecycle
All (216)Filed (39)Permit Issued (30)Signed Off (26)Facade (FISP) (13)Violation (60)Inspection (18)Special Inspection (30)
05/11/2026
Cycle 10 facade report submitted
05/05/2026
Cycle 10 facade inspection completed
04/17/2026
Signed off — Alteration
Proposed to repair the facade and proposed inspection of the steel welding by a third party as per the plan. No change to Use, egress, or occupancy.
M01330311-I1
04/07/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SIDEWALK SHED AT WEST 21ST STREET ELEVATION.
M01315820-I1
04/02/2026
Signed off — Alteration
INITIAL CD5 FISP. INSPECTION, REPAIRS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ADDING NEW DROPS WITH NEW TIE BACK LOCATIONS OPTION.
M01330601-I1
02/10/2026
Signed off — Alteration
Proposed to repair existing terra cotta on facade, all as per plan. No change of the use or occupancy or egress.
M01237160-I1
01/29/2026
Permit issued — Structural
M01237160-I1-ST
01/19/2026
Filed — Alteration
INITIAL CD5 FISP. INSPECTION, REPAIRS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ADDING NEW DROPS WITH NEW TIE BACK LOCATIONS OPTION.
M01330601-P1
01/14/2026
Permit issued — General Construction
M01330311-I1-GC
01/07/2026
Signed off — Alteration
M01289980-I1
01/05/2026
Permit issued — Suspended Scaffold
M01330601-I1-SC
12/19/2025
Filed — Alteration
Proposed to repair the facade and proposed inspection of the steel welding by a third party as per the plan. No change to Use, egress, or occupancy.
M01330311-I1
12/19/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SIDEWALK SHED AT WEST 21ST STREET ELEVATION.
M01315820-P1
12/09/2025
Special inspection requirement — Masonry
MOLLY GLENN
12/09/2025
Special inspection requirement — Tenant Protection Plan Compliance
MOLLY GLENN
12/09/2025
Special inspection requirement — Final
Robert Kornfeld
12/09/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
MOLLY GLENN
12/08/2025
Filed — Alteration
INITIAL CD5 FISP. INSPECTION, REPAIRS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ADDING NEW DROPS WITH NEW TIE BACK LOCATIONS OPTION.
M01330601-I1
11/10/2025
Permit issued — Sidewalk Shed
M01315820-I1-SH
11/07/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SIDEWALK SHED AT WEST 21ST STREET ELEVATION.
M01315820-I1
09/29/2025
Permit issued — Suspended Scaffold
M01289980-I1-SC
09/26/2025
Signed off — Alteration
Proposed to repair the ceiling on the 12th floor, all as per plan. No change of use, occupancy or egress.
M01238921-I1
09/19/2025
Filed — Alteration
M01289980-I1
07/23/2025
Permit issued — General Construction
M01238921-I1-GC
06/25/2025
Filed — Alteration
Proposed to repair existing terra cotta on facade, all as per plan. No change of the use or occupancy or egress.
M01237160-I1
06/23/2025
Permit issued — General Construction
M01238921-I1-GC
06/13/2025
Filed — Alteration
Proposed to repair the ceiling on the 12th floor, all as per plan. No change of use, occupancy or egress.
M01238921-I1
02/12/2025
Signed off — Alteration
M01036085-I1
01/07/2025
Signed off — Alteration
RE-FILING OF ALT. 2 SPRINKLER APPLICATION #104782754 FOR MODIFICATION TO EXISTING SPRINKLER SYSTEM.
M00816007-I1
12/20/2024
Signed off — Alteration
RE-FILING OF PLUMBING WORK UNDER ALT. 2 #102085994 AS PER PLANS FILED HEREWITH.
M00816156-I1
12/20/2024
Signed off — Alteration
REFILING OF PLUMBING WORK UNDER ALT. 2 #104464027 AS PER PLANS FILED HEREWITH.
M00816144-I1
12/20/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/21/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/20/2024
Signed off — Alteration
SPRINKLER MODIFICATIONS AND INSTALLATION OF TEMPORARY LOOP SYSTEM AND PERMANENT SPRINKLER LAYOUT FOR 7TH FLOOR COMMERCIAL SPACE AS PER PLANS FILED HEREWITH.
M01041244-I1
11/18/2024
Signed off — Alteration
SPRINKLER MODIFICATIONS AND INSTALLATION OF TEMPORARY LOOP SYSTEM AND PERMANENT SPRINKLER LAYOUT FOR 7TH FLOOR COMMERCIAL SPACE AS PER PLANS FILED HEREWITH.
M01041244-S2
11/15/2024
Signed off — Alteration
SPRINKLER MODIFICATIONS AND INSTALLATION OF TEMPORARY LOOP SYSTEM AND PERMANENT SPRINKLER LAYOUT FOR 7TH FLOOR COMMERCIAL SPACE AS PER PLANS FILED HEREWITH.
M01041244-S1
11/15/2024
Signed off — Alteration
SPRINKLER MODIFICATIONS AND INSTALLATION OF TEMPORARY LOOP SYSTEM AND PERMANENT SPRINKLER LAYOUT FOR 7TH FLOOR COMMERCIAL SPACE AS PER PLANS FILED HEREWITH.
M01041244-S3
11/06/2024
Filed — Alteration
SPRINKLER MODIFICATIONS AND INSTALLATION OF TEMPORARY LOOP SYSTEM AND PERMANENT SPRINKLER LAYOUT FOR 7TH FLOOR COMMERCIAL SPACE AS PER PLANS FILED HEREWITH.
M01041244-P2
11/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Laurence Jones
11/06/2024
Special inspection requirement — Final
Laurence Jones
11/06/2024
Special inspection requirement — Lighting controls
MOLLY GLENN
11/06/2024
Special inspection requirement — Interior lighting power
MOLLY GLENN
11/06/2024
Special inspection requirement — Tenant Protection Plan Compliance
MOLLY GLENN
11/05/2024
Special inspection requirement — Interior lighting power
MOLLY GLENN
11/05/2024
Special inspection requirement — Tenant Protection Plan Compliance
11/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Laurence Jones
11/05/2024
Special inspection requirement — Final
Laurence Jones
11/05/2024
Special inspection requirement — Lighting controls
MOLLY GLENN
10/25/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01059283-I1
10/25/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01059275-I1
10/02/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/26/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/23/2024
Special inspection requirement — Tenant Protection Plan Compliance
MOLLY GLENN
09/20/2024
Permit issued — Plumbing
M00816144-I1-PL
09/20/2024
Special inspection requirement — Tenant Protection Plan Compliance
MOLLY GLENN
09/20/2024
Special inspection requirement — Sprinkler Systems
MOLLY GLENN
09/20/2024
Special inspection requirement — Tenant Protection Plan Compliance
MOLLY GLENN
09/19/2024
Filed — Alteration
RE-FILING OF ALT. 2 SPRINKLER APPLICATION #104782754 FOR MODIFICATION TO EXISTING SPRINKLER SYSTEM.
M00816007-P1
09/19/2024
Filed — Alteration
REFILING OF PLUMBING WORK UNDER ALT. 2 #104464027 AS PER PLANS FILED HEREWITH.
M00816144-P1
09/19/2024
Filed — Alteration
RE-FILING OF PLUMBING WORK UNDER ALT. 2 #102085994 AS PER PLANS FILED HEREWITH.
M00816156-P1
Latest 60 of 216 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offTHE GRENADIER CORPORATION01/29/2026
DOB NOWGeneral ConstructionSigned-offSATO CONSTRUCTION CO.INC01/14/2026
DOB NOWSuspended ScaffoldSigned-offSATO CONSTRUCTION CO. INC01/05/2026
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC11/10/2025
DOB NOWSuspended ScaffoldSigned-offSTRUCTUAL PRESV SYSTEM09/29/2025
DOB NOWGeneral ConstructionSigned-offCREATIVE TEAM INTERIORS I07/23/2025
DOB NOWGeneral ConstructionSigned-offCREATIVE TEAM INTERIORS I06/23/2025
DOB NOWPlumbingSigned-offGENERAL PLUMBING CORP09/20/2024
DOB NOWSprinklersSigned-offGENERAL PLUMBING CORP09/06/2024
DOB NOWPlumbingSigned-offGENERAL PLUMBING CORP09/05/2024
DOB NOWMechanical SystemsSigned-offAINSWORTH INC09/04/2024
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP06/14/2024
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC06/06/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/06/2024
DOB NOWMechanical SystemsSigned-offSPK/LEWIS CONSTRUCTION LL05/29/2024
DOB NOWSprinklersSigned-offDEMAR PLUMBING CORP05/29/2024
DOB NOWGeneral ConstructionSigned-offSPK/LEWIS CONSTRUCTION LL05/21/2024
DOB NOWGeneral ConstructionSigned-offCREATIVE TEAM INTERIORS I03/07/2023
DOB NOWGeneral ConstructionSigned-offTAURINO MANAGEMENT, INC12/30/2022
DOB NOWStructuralSigned-offNICHOLSON & GALLOWAY, INC.07/27/2022
DOB NOWSprinklersSigned-offFIREQUEST CORP05/09/2022
DOB NOWMechanical SystemsPermit IssuedTAURINO MANAGEMENT, INC04/27/2022
DOB NOWGeneral ConstructionSigned-offTAURINO MANAGEMENT, INC04/27/2022
DOB NOWPlumbingSigned-offACCESS PLUMBING CORP04/26/2022
DOB NOWSidewalk ShedSigned-offINTERSYSTEM INSTALLATION08/05/2021
DOB NOWSupported ScaffoldSigned-offINTERSYSTEM INSTALLATION08/01/2021
DOB NOWSidewalk ShedSigned-offINTERSYSTEM INSTALLATION10/19/2020
DOB NOWSupported ScaffoldSigned-offINTERSYSTEM INSTALLATION10/19/2020
DOB NOWSprinklersSigned-offGENERAL PLUMBING CORP01/16/2020
DOB NOWStructuralSigned-offSTRUCTURAL PRESERV SYSTEM11/25/2019
BISSPISSUEDGENERAL PLUMBING CORP05/01/2025
BISPLISSUEDGENERAL PLUMBING CORP08/01/2024
BISSPISSUEDGENERAL PLUMBING CORP08/01/2024
BISSPISSUEDPEAK FIRE PROTECTION LLC10/12/2022
BISPLISSUEDPEAK PLUMBING SOLUTIONS LLC10/12/2022
BISOTISSUEDPRAT ENTERPRISES CORP09/07/2021
BISEQISSUEDPRAT ENTERPRISES CORP08/18/2021
BISPLISSUEDPEAK PLUMBING SOLUTIONS LLC01/19/2021
BISSPISSUEDPEAK FIRE PROTECTION LLC01/19/2021
BISOTISSUEDPRATT CONSTRUCTION & REST12/01/2020
+ 40 more permits on file
17 projects · most recent 01/21/2026
General Wiring Boiler Controls HVAC Wiring
FiledStatusContractorScope
01/21/2026Permit IssuedTOP SHELF ELECTRIC CORP—
07/02/2024CompleteJUMPER ELECTRIC CORPGeneral Wiring
06/07/2024CompleteTOP SHELF ELECTRIC CORP—
12/09/2022CompletePROSPECT ELECT. SERV INCGeneral Wiring
12/09/2022CompletePROSPECT ELECT. SERV INCGeneral Wiring
05/17/2022CompleteHIG ELECTRIC ASSC NYC INCGeneral Wiring
05/06/2022CompleteHIG ELECTRIC ASSC NYC INC—
03/29/2021CompleteVALMAR ELECTRIC CORP.General Wiring
03/04/2021CompletePROSPECT ELECT. SERV INCGeneral Wiring
02/23/2021CompleteSTEVEN FARKAS—
10/15/2020CompleteSTEVEN FARKAS—
09/02/2020CompleteROMCON ELECTRIC, INCBoiler Controls
07/29/2020CompletePROSPECT ELECT. SERV INCGeneral Wiring
08/13/2019CompleteJOROB CONTR'G & ELEC'L COGeneral Wiring
06/17/2019CompleteCHT ELECTRIC CORP.General Wiring
▾Field Inspections (DOB CAP) — 18
DateTypeResultReport
12/20/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/21/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/02/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/26/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/10/2024Pass-Final SP - Up to 9 Requested FloorsPassView ↗
09/06/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/22/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/07/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/11/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/08/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/25/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/19/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/02/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/06/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/21/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/24/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/16/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/03/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 131
DateRequirementInspectorRole
12/09/2025Structural Stability – Alterations of existing buildingsMOLLY GLENNspecial
12/09/2025MasonryMOLLY GLENNspecial
12/09/2025FinalRobert Kornfeldprogress
12/09/2025Tenant Protection Plan ComplianceMOLLY GLENNspecial
11/06/2024Fire-Resistant Penetrations and JointsLaurence Jonesspecial
11/06/2024Lighting controlsMOLLY GLENNenergy_progress
11/06/2024Interior lighting powerMOLLY GLENNenergy_progress
11/06/2024Tenant Protection Plan ComplianceMOLLY GLENNspecial
11/06/2024FinalLaurence Jonesprogress
11/05/2024Fire-Resistant Penetrations and JointsLaurence Jonesspecial
11/05/2024FinalLaurence Jonesprogress
11/05/2024Interior lighting powerMOLLY GLENNenergy_progress
11/05/2024Lighting controlsMOLLY GLENNenergy_progress
11/05/2024Tenant Protection Plan Compliance—special
09/23/2024Tenant Protection Plan ComplianceMOLLY GLENNspecial
09/20/2024Sprinkler SystemsMOLLY GLENNspecial
09/20/2024Tenant Protection Plan ComplianceMOLLY GLENNspecial
09/20/2024Tenant Protection Plan ComplianceMOLLY GLENNspecial
09/18/2024Sprinkler SystemsMOLLY GLENNspecial
09/18/2024Tenant Protection Plan Compliance—special
09/12/2024Fire-Resistant Penetrations and JointsLaurence Jonesspecial
09/12/2024Mechanical SystemsMOLLY GLENNspecial
09/12/2024HVAC-R and service water heating equipmentMOLLY GLENNenergy_progress
09/12/2024Duct leakage testing, insulation and designMOLLY GLENNenergy_progress
09/12/2024Maintenance informationMOLLY GLENNenergy_progress
Latest 25 of 131.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Schoolof Visual ArtsEducationGround
Project M00816144 Alteration · LOC Issued · 09/06/2023
SVA | NYC | NYO | Animation DeptEducationFloor 6
Project M00708277 Alteration · LOC Issued · 04/13/2022
Project M00708288 Alteration · LOC Issued · 04/13/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 1,355 on file (BIS + DOB NOW)
▸Plans & Drawings38
▸DOB NOWPlans/Sketch31
09/02/2026M00708288-I1Request digital key ↗
09/02/2026M00708277-P1Request digital key ↗
09/02/2026M00708277-I1Request digital key ↗
Showing 3 of 31 on file for this type
▸DOB NOWPlans/Sketch - Structural2
09/05/2026M00216173-I1Request digital key ↗
08/15/2026M00216173-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/05/2026M00290012-I1Request digital key ↗
08/15/2026M00290012-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/04/2026M00414154-I1Request digital key ↗
08/15/2026M00414154-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00414132-I1Request digital key ↗
▸Applications & Permits250
▸BISPLAN / WORK APPROVAL APPLICATION157
04/24/2025123117698Open ↗
03/26/2025123117714Open ↗
03/24/2025123117714Open ↗
Showing 3 of 157 on file for this type
▸BISWORK PERMIT APPLICATION90
05/02/2025123117714Open ↗
08/01/2024123346753Open ↗
08/01/2024120856476Open ↗
Showing 3 of 90 on file for this type
▸BISSIDEWALK SHED APPLICATION & PERMIT1
12/01/2020123854043Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
12/01/2020123854043Open ↗
▸BISSCAFFOLD APPLICATION & PERMIT1
12/01/2020123854043Open ↗
▸Seals & Professional Certifications315
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION115
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 115 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature46
09/01/2026M00290012-P1Open ↗
09/01/2026M00290012-P1Open ↗
09/01/2026M00290012-P1Open ↗
Showing 3 of 46 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST40
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 40 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature35
09/05/2026M00216173-I1Open ↗
09/05/2026M00290012-P1Open ↗
09/05/2026M00290012-I1Open ↗
Showing 3 of 35 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT30
11/09/2020140975835Open ↗
Showing 1 of 30 on file for this type
▸DOB NOWProgress Inspector Seal & Signature27
09/05/2026M00414154-I1Open ↗
09/01/2026M00216173-P1Open ↗
09/01/2026M00705591-I1Open ↗
Showing 3 of 27 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
11/09/2020140975835Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
11/09/2020140975835Open ↗
Showing 1 of 2 on file for this type
▸Trade Schedules & Equipment116
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISEQUIPMENT USE PERMITS21
04/10/2025123117698Open ↗
05/24/2023121150468Open ↗
05/11/2023120384413Open ↗
Showing 3 of 21 on file for this type
▸BISSELF-CERT PLUMBING NOTICE18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISSCHEDULE B - PLUMBING17
03/24/2025123117714Open ↗
05/10/2023123117714Open ↗
Showing 2 of 17 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA10
04/06/2023123349527Open ↗
10/26/2020123423615Open ↗
Showing 2 of 10 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT3
04/10/2025123117698Open ↗
05/24/2023121150468Open ↗
05/11/2023120856485Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS2
04/10/2025123117698Open ↗
05/24/2023121150468Open ↗
▸BISSPRINKLER SYSTEMS2
11/21/2024120856476Open ↗
09/25/2024123117714Open ↗
▸BISSPRINKLER INSP REPORT : FP-852
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection23
▸BISTenant Protection Plan and Notes17
11/09/2020140975835Open ↗
Showing 1 of 17 on file for this type
▸DOB NOWTenant Protection Plan5
09/05/2026M00290012-I1Open ↗
09/04/2026M00414132-I1Open ↗
08/13/2026M00414154-P1Open ↗
Showing 3 of 5 on file for this type
▸BISST-1 Street Tree Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos77
▸BISASBESTOS: CERTIFICATION (DEP ACP5)31
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 31 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'24
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 24 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report22
09/05/2026M00216173-I1Open ↗
09/05/2026M00290012-P1Open ↗
09/05/2026M00290012-I1Open ↗
Showing 3 of 22 on file for this type
▸Energy Compliance71
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS14
02/22/2021123853142Open ↗
07/10/2020123744341Open ↗
06/02/2020123587047Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY9
05/11/2022122861705Open ↗
04/26/2022122861705Open ↗
04/25/2022122861705Open ↗
Showing 3 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)7
05/14/2025123346753Open ↗
04/10/2025123117698Open ↗
05/24/2023121150468Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: ENERGY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISINTERIOR LIGHTING POWER2
05/24/2023121150468Open ↗
04/26/2022122861705Open ↗
▸BIS* HVAC INSULATION AND SEALING2
04/10/2025123117698Open ↗
05/24/2023121150468Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026M00705591-I1Open ↗
08/13/2026M00708277-I1Open ↗
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports32
▸BISTECHNICAL REPORT: RESPONSIBILITY19
10/24/2022120856467Open ↗
08/12/2022123854043Open ↗
04/21/2022122861705Open ↗
Showing 3 of 19 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)5
05/14/2025123346753Open ↗
04/10/2025123117698Open ↗
09/25/2024123117714Open ↗
Showing 3 of 5 on file for this type
▸BISMECHANICAL SYSTEMS4
04/10/2025123117698Open ↗
05/24/2023121150468Open ↗
05/11/2023120384413Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs105
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST49
01/29/2026123117714Open ↗
05/14/2025123346753Open ↗
04/25/2025123117698Open ↗
Showing 3 of 49 on file for this type
▸BISADMINISTRATIVE OBJECTIONS21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISSUPERSEDING LETTER11
05/02/2025123117714Open ↗
08/01/2024120856476Open ↗
08/01/2024123346753Open ↗
Showing 3 of 11 on file for this type
▸BISFINAL7
05/14/2025123346753Open ↗
04/10/2025123117698Open ↗
09/25/2024123117714Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE4
01/22/2025123363779Open ↗
11/04/2021123363779Open ↗
09/28/2021123363779Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/20/2026M01315820-I1Open ↗
08/20/2026M01315820-P1Open ↗
▸Cost, Insurance & Ownership126
▸BISCOST AFFIDAVIT111
04/26/2022122861705Open ↗
04/26/2022122861705Open ↗
04/25/2022122861705Open ↗
Showing 3 of 111 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW313
01/29/2026123117714Open ↗
05/14/2025123346753Open ↗
04/10/2025123117698Open ↗
Showing 3 of 13 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE2
09/08/2021123854043Open ↗
12/01/2020123854043Open ↗
▸Filing & Intake Forms146
▸BISEFILING COVER SHEET57
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 57 on file for this type
▸BISADDITIONAL INFORMATION47
03/26/2025123117714Open ↗
01/23/2025123363779Open ↗
08/13/2024120856485Open ↗
Showing 3 of 47 on file for this type
▸BISBOROUGH INTAKE FORM39
05/02/2025123117714Open ↗
08/01/2024120856476Open ↗
08/01/2024123346753Open ↗
Showing 3 of 39 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
11/09/2020140975835Open ↗
Showing 1 of 3 on file for this type
▸Other Documents36
▸BISLOFT BOARD CERTIFICATE20
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 20 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸DOB NOWManufacturer's Specifications2
08/19/2026M01330601-P1Open ↗
08/13/2026M01330601-I1Open ↗
▸DOB NOWCalculations2
08/19/2026M01330601-P1Open ↗
08/13/2026M01330601-I1Open ↗
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWIRA Certification1
08/13/2026M01289980-I1Open ↗
▸DOB NOWLoft Board Certificate1
09/05/2026M00290012-I1Open ↗