| B01027309 ↗ | 225 AVENUE T BROOKLYN | Alteration | Permit Issued | 04/04/2024 | 09/29/2026 | Design LAWLESS & MANGIONE Filer BG & ASSOCIATES | FILING FOR FACADE REPAIRS, BALCONY REPAIRS, BRICK REPLACEMENT, POINTING, SILL REPLACEMENT, SHELF ANGLE REPLACEMENT, INTERIOR REPAIRS/UPGRADE… |
| M01144742 ↗ | 180 RIVERSIDE BOULEVARD MANHATTAN | Alteration | Permit Issued | 05/28/2025 | 09/29/2026 | Owner EQUITY RESIDENTIAL | Facade repairs as per plans; no change to use, egress, or occupancy. |
| X01342944 ↗ | 815 HUTCHINSON RVR PKWY BRONX | Alteration | Permit Issued | 02/26/2026 | 09/28/2026 | Parking lot expansion joint replacement at upper level as shown on plot plan. | |
| B01054736 ↗ | 671 LINCOLN AVENUE BROOKLYN | Alteration | Permit Issued | 08/07/2024 | 09/25/2026 | Design IMEG Consulting Corp. Owner LP PRESERVATION LLC Filer JM ZONING, LLC. | STRUCTURAL WORK FILED IN CONJUNCTION WITH GC APPLICATION: REHABILITATION OF THE EXISTING GARAGES (GARAGES 1, 2 & 3) AND PLAZA STRUCTURE. NO … |
| M01150543 ↗ | 1524 3 AVENUE MANHATTAN | Alteration | Permit Issued | 12/19/2024 | 09/22/2026 | Design SIMPSON GUMPERTZ & HEGER Filer RITE ONE EXPEDITING | CONCRETE REPAIR OF BALCONY CURBS AND SLABS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| M01228894 ↗ | 2391 2 AVENUE MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 09/22/2026 | Application filed for window replacements at all floors 6-35, as per drawings filed herewith. |
| Name | Projects together | Most recent |
|---|---|---|
| SOCOTEC, INC. | 19 | 07/16/2026 |
| THORNTON TOMASETTI | 16 | 08/19/2026 |
| RAND ENGINEERING & ARCHITECTURE | 15 | 08/28/2026 |
| SIMPSON GUMPERTZ & HEGER | 11 | 08/05/2026 |
| CANY ARCHITECTURE & ENGINEERING DPC | 10 | 06/23/2026 |
| DESIMONE CONSULTING ENGINEERS | 10 | 10/10/2025 |
| LAWLESS & MANGIONE | 10 | 03/04/2026 |
| TERJESEN ASSOCIATES ARCHITECTS PC | 10 | 08/17/2026 |
| HOWARD L ZIMMERMAN ARCH & ENG DPC | 9 | 02/03/2025 |
| O&S ASSOCIATES | 9 | 11/18/2025 |
| OFFICE OF JAMES RUDERMAN | 9 | 07/01/2026 |
| WJE ENGINEERS & ARCHITECTS, P.C. | 9 | 08/11/2026 |
| EDG | 8 | 01/14/2026 |
| NY RESTORATION TECHNOLOGY CORP | 8 | 06/23/2026 |
| DIBARI ENGINEERING, P.C. | 5 | 08/17/2026 |
| MERRITT ENGINEERING CONSULTANTS, DPC | 5 | 03/18/2024 |
| AG ENGINEERING PLLC | 4 | 03/18/2024 |
| KMA DESIGNS LLC | 4 | 07/16/2026 |
| NYC FACADE ARCHITECTURE, PLLC | 4 | 03/23/2026 |
| TARIQ M. BASHIR | 4 | 09/25/2024 |
| BERTOLINI ARCHITECTURAL WORKS | 3 | 11/15/2024 |
| EOC-NY | 3 | 05/01/2025 |
| GILSANZ MURRAY STEFICEK LLP | 3 | 08/18/2025 |
| IMEG Consulting Corp. | 3 | 08/19/2026 |
| RAS PE CONSULTING ENGINEERS | 3 | 02/10/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| KINGS GROUP NY CORP | 8 | 07/16/2026 |
| SLSCO,LTD | 3 | 07/24/2024 |
| CENTRAL CONSTRUCTION MANA | 2 | 03/10/2023 |
| SKYLINE RESTORATION INC | 2 | 07/18/2025 |
| ALLIED MD CONSTRUCTION LL | 1 | 07/30/2025 |
| BEDROCK PLBG. & HTG., INC | 1 | 09/19/2023 |
| CARDONE CONCRETE INC | 1 | 06/12/2025 |
| COLGATE RESTORATION CORP | 1 | 02/28/2025 |
| FERRAN CONTRACTING CORP | 1 | 06/16/2025 |
| FIFTH AVENUE BUILDERS LLC | 1 | 08/19/2026 |
| LATTY'S GEN PLBG CONT COR | 1 | 09/19/2023 |
| NEPTUNE MECHANICAL INC | 1 | 08/19/2026 |
| RALLY RESTORATION CORP | 1 | 02/06/2024 |
| SKYLINE BUILDERS GROUP LL | 1 | 05/24/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| KINGS GROUP NY CORP | 8 | 07/16/2026 |
| SL GREEN REALTY CORP | 8 | 01/15/2026 |
| AKAM ASSOCIATES, INC. | 7 | 07/16/2026 |
| BOULEVARD GARDENS OWNERS CORP. | 6 | 03/18/2024 |
| BPP PARKER TOWER PROPERTY OWNER | 6 | 03/16/2023 |
| EQUITY RESIDENTIAL | 6 | 05/28/2025 |
| L+M FUND MANAGEMENT LLC | 6 | 05/14/2026 |
| STELLAR MANAGEMENT | 5 | 03/23/2026 |
| BSC HOUSING COMPANY, INC | 3 | 08/05/2026 |
| DIVCO WEST REAL ESTATE SERVICES | 3 | 08/11/2026 |
| DOUGLAS ELLIMAN PROPERTY MANAGEMENT | 3 | 07/01/2025 |
| FirstService Residential | 3 | 07/29/2025 |
| Montefiore Medical Center | 3 | 07/22/2025 |
| NEW WATER STREET CORP | 3 | 07/01/2026 |
| VORNADO REALTY TRUST | 3 | 01/14/2026 |
| ALBERT EINSTEN COLLEGE OF MEDICINE | 2 | 07/29/2024 |
| C&C APARTMENT MANAGEMENT LLC | 2 | 08/07/2024 |
| GARTHCHESTER REALTY | 2 | 04/27/2026 |
| LP PRESERVATION LLC | 2 | 08/19/2026 |
| METRO MANAGEMENT DEVELOPMENT INC. | 2 | 03/04/2026 |
| PELICAN MANAGEMENT INC. | 2 | 06/12/2025 |
| PRESTIGE MANAGEMENT INC. | 2 | 05/22/2025 |
| SCHOOL OF VISUAL ARTS | 2 | 04/22/2024 |
| TAINO TOWERS | 2 | 06/02/2025 |
| THE LOVETT GROUP | 2 | 03/16/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| RIZZO GROUP | 14 | 08/11/2026 |
| SOMMA DESIGN & CONSULTING | 9 | 08/17/2026 |
| CONVERSANO ASSOCIATES, INC. | 8 | 07/16/2026 |
| JAM CONSULTANTS, INC. | 8 | 07/22/2026 |
| JULIAN A. GOMEZ | 8 | 08/28/2026 |
| HLZAE | 6 | 05/07/2024 |
| LMS-ACE SERVICES | 6 | 01/14/2026 |
| PROFESSIONAL DESIGN CONSULTANTS, LL | 5 | 02/09/2024 |
| ARSENAL BUILDING CONSULTANTS LLC | 4 | 03/18/2024 |
| BG & ASSOCIATES | 4 | 03/04/2026 |
| BURNHAM NATIONWIDE INC | 4 | 05/07/2026 |
| KMA DESIGNS LLC | 4 | 07/16/2026 |
| MERRITT ENGINEERING CONSULTANT, DPC | 4 | 03/18/2024 |
| MUNICIPAL BUILDING CONSULTANTS | 4 | 07/15/2025 |
| CAESAR BUSTAMANTE, AIA | 3 | 02/03/2025 |
| GREEN LIGHT EXPEDITING LLC | 3 | 06/23/2026 |
| MK ARCHITECTURE PC | 3 | 01/29/2025 |
| O&S ASSOCIATES | 3 | 11/18/2025 |
| WILLIAM VITACCO ASSOCIATES | 3 | 03/12/2026 |
| A1 EXPEDITING SERVICE CORP. | 2 | 06/26/2025 |
| BERTOLINI ARCHITECTURAL WORKS, DPC | 2 | 11/15/2024 |
| CONSTRUCTION PERMIT SERVICES | 2 | 07/18/2025 |
| EMPIRE CITY CONSULTANTS, INC. | 2 | 05/27/2025 |
| GARO GUMUSYAN | 2 | 06/03/2024 |
| GILLMAN CONSULTING INC | 2 | 10/05/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01027309 ↗ | 225 AVENUE T BROOKLYN | Alteration | Permit Issued | 04/04/2024 | 09/29/2026 | Design LAWLESS & MANGIONE Filer BG & ASSOCIATES | FILING FOR FACADE REPAIRS, BALCONY REPAIRS, BRICK REPLACEMENT, POINTING, SILL REPLACEMENT, SHELF ANGLE REPLACEMENT, INTERIOR REPAIRS/UPGRADE… |
| M01144742 ↗ | 180 RIVERSIDE BOULEVARD MANHATTAN | Alteration | Permit Issued | 05/28/2025 | 09/29/2026 | Owner EQUITY RESIDENTIAL | Facade repairs as per plans; no change to use, egress, or occupancy. |
| X01342944 ↗ | 815 HUTCHINSON RVR PKWY BRONX | Alteration | Permit Issued | 02/26/2026 | 09/28/2026 | Parking lot expansion joint replacement at upper level as shown on plot plan. | |
| B01054736 ↗ | 671 LINCOLN AVENUE BROOKLYN | Alteration | Permit Issued | 08/07/2024 | 09/25/2026 | Design IMEG Consulting Corp. Owner LP PRESERVATION LLC Filer JM ZONING, LLC. | STRUCTURAL WORK FILED IN CONJUNCTION WITH GC APPLICATION: REHABILITATION OF THE EXISTING GARAGES (GARAGES 1, 2 & 3) AND PLAZA STRUCTURE. NO … |
| M01150543 ↗ | 1524 3 AVENUE MANHATTAN | Alteration | Permit Issued | 12/19/2024 | 09/22/2026 | Design SIMPSON GUMPERTZ & HEGER Filer RITE ONE EXPEDITING | CONCRETE REPAIR OF BALCONY CURBS AND SLABS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| M01228894 ↗ | 2391 2 AVENUE MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 09/22/2026 | Application filed for window replacements at all floors 6-35, as per drawings filed herewith. | |
| M00913946 ↗ | 211 EAST 122 STREET MANHATTAN | Alteration | Permit Issued | 07/15/2024 | 09/21/2026 | Application filed for interior apartment renovations; lobby renovation; roof repairs; ramp repairs, as per drawings filed herewith. | |
| M00915361 ↗ | 2243 3 AVENUE MANHATTAN | Alteration | Permit Issued | 07/15/2024 | 09/21/2026 | Application filed for interior apartment renovations; lobby renovation; roof repairs; as per drawings filed herewith. | |
| M00915364 ↗ | 2391 2 AVENUE MANHATTAN | Alteration | Permit Issued | 07/15/2024 | 09/21/2026 | Application filed for interior apartment renovations; lobby renovation; roof repairs; ramp repairs, as per drawings filed herewith. | |
| M00915366 ↗ | 2383 2 AVENUE MANHATTAN | Alteration | Permit Issued | 07/15/2024 | 09/21/2026 | Application filed for interior apartment renovations; lobby renovation; roof repairs; ramp repairs, as per drawings filed herewith. | |
| M01078741 ↗ | 211 EAST 122 STREET MANHATTAN | Alteration | Permit Issued | 07/24/2024 | 09/21/2026 | Design DIBARI ENGINEERING, P.C. | Replacement of residential Ductwork, exhaust fans, equipment, Lobby, as per drawings filed herewith. |
| M01078750 ↗ | 2243 3 AVENUE MANHATTAN | Alteration | Permit Issued | 07/24/2024 | 09/21/2026 | Design DIBARI ENGINEERING, P.C. | Replacement of residential Ductwork, exhaust fans, equipment, Lobby, as per drawings filed herewith. |
| M01078759 ↗ | 2391 2 AVENUE MANHATTAN | Alteration | Permit Issued | 07/24/2024 | 09/21/2026 | Design DIBARI ENGINEERING, P.C. | Replacement of residential Ductwork, exhaust fans, equipment, Lobby, as per drawings filed herewith. |
| M01078763 ↗ | 2383 2 AVENUE MANHATTAN | Alteration | Permit Issued | 07/24/2024 | 09/21/2026 | Design DIBARI ENGINEERING, P.C. | Replacement of residential Ductwork, exhaust fans, equipment, Lobby, as per drawings filed herewith. |
| M01228870 ↗ | 211 EAST 122 STREET MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 09/21/2026 | Application filed for GC/ST for emergency generator installation in open space, as per drawings filed herewith. | |
| M01228887 ↗ | 2243 3 AVENUE MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 09/21/2026 | Application filed for window replacements at all floors 6-35, as per drawings filed herewith. | |
| M01228903 ↗ | 2383 2 AVENUE MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 09/21/2026 | Application filed for window replacements at all floors 6-35, as per drawings filed herewith. | |
| M01230199 ↗ | 2391 2 AVENUE MANHATTAN | Alteration | Permit Issued | 05/29/2025 | 09/21/2026 | Owner TAINO TOWERS Filer JAM CONSULTANTS, INC. | Structural modifications related to cellar renovation for exercise room. No change to use, occupancy or egress. |
| M01309203 ↗ | 919 3 AVENUE MANHATTAN | Alteration | Permit Issued | 12/03/2025 | 09/11/2026 | Design THORNTON TOMASETTI Owner SL GREEN REALTY CORP Filer RIZZO GROUP | Structural modifications for LL26 Cycle 1A REM repairs as per plans. No change in use, egress or occupancy. |
| B01046510 ↗ | 475 CARLTON AVENUE BROOKLYN | Alteration | Permit Issued | 06/10/2024 | 08/31/2026 | Design LAWLESS & MANGIONE | Filing for facade repairs as per plans filed herewith. No change in use, occupancy or egress. |
| M00954052 ↗ | 711 3 AVENUE MANHATTAN | Alteration | Signed-off | 11/08/2023 | 08/19/2026 | Design SOCOTEC, INC. Owner SL GREEN REALTY CORP | Garage repairs. No change in egress, use or occupancy. |
| M01334070 ↗ | 885 THIRD AVE MANHATTAN | Alteration | Permit Issued | 01/15/2026 | 08/19/2026 | Owner SL GREEN REALTY CORP Filer RIZZO GROUP | GENERAL CONSTRUCTION & STRUCTURAL MODIFICATIONS TAKING PLACE ON FACADE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY |
| M01432367 ↗ | 540 MADISON AVENUE MANHATTAN | Alteration | Permit Issued | 08/11/2026 | 08/19/2026 | Design THORNTON TOMASETTI Filer RIZZO GROUP | Structural modifications taking place on Roof as per plans filed herewith. No change in use, egress or occupancy. |
| M01432372 ↗ | 540 MADISON AVENUE MANHATTAN | Alteration | Permit Issued | 08/11/2026 | 08/19/2026 | Design THORNTON TOMASETTI Filer RIZZO GROUP | Structural modifications taking place on Roof (davit base pedestals) as per plans filed herewith. No change in use, egress or occupancy. |
| M01437902 ↗ | 540 MADISON AVENUE MANHATTAN | Alteration | Permit Issued | 08/11/2026 | 08/19/2026 | Filer RIZZO GROUP | Structural modifications taking place on 38th and 39th floors as per plans filed herewith. No change in use, egress or occupancy. |
| M01345424 ↗ | 2411 FREDRICK DOUGLASS BL MANHATTAN | Alteration | Permit Issued | 03/06/2026 | 08/12/2026 | Design SOCOTEC, INC. Owner L+M FUND MANAGEMENT LLC | installation of heavy duty sidewalk shed. no change in use, occupancy or egress. all work to comply with chapter 33 of nycbc |
| M01345436 ↗ | 2411 FREDRICK DOUGLASS BL MANHATTAN | Alteration | Permit Issued | 03/06/2026 | 08/12/2026 | Design KMA DESIGNS LLC Owner KINGS GROUP NY CORP Filer KMA DESIGNS LLC | INSTALLATION OF HEAVY DUTY SIDEWALK SHED. NO CHANGE IN USE, OCCUPANCY OR EGRESS. ALL WORK TO COMPLY WITH CHAPTER 33 OF NYCBC |
| M01129230 ↗ | 100 CHERRY STREET MANHATTAN | Alteration | Permit Issued | 10/31/2024 | 08/06/2026 | Design SULLIVAN ENGINEERING Owner L+M FUND MANAGEMENT LLC | Main roof & 12th floor Terraces roof restorations work including remove existing and install new roof system & railings. All work as per pl… |
| B01366762 ↗ | 211 MCGUINNESS BOULEVARD BROOKLYN | Alteration | Permit Issued | 03/23/2026 | 08/05/2026 | Owner STELLAR MANAGEMENT | HEREBY FILING FACADES REPAIRS AS PER PLANS FILED HEREWITH. |
| M00487299 ↗ | 711 3 AVENUE MANHATTAN | Alteration | Permit Issued | 05/20/2021 | 08/05/2026 | Owner SL GREEN REALTY CORP. | FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE,EGRESS OR OCCUPANCY. |
| B01226866 ↗ | 636 BROOKLYN AVENUE BROOKLYN | Alteration | Permit Issued | 05/22/2025 | 07/29/2026 | Design O&S ASSOCIATES Owner PRESTIGE MANAGEMENT INC. Filer O&S ASSOCIATES | Filing for repairs to facades at this existing building. No change to use, occupancy or egress. |
| M01360773 ↗ | 280 RECTOR PLACE MANHATTAN | Alteration | Permit Issued | 05/04/2026 | 07/21/2026 | Design KMA DESIGNS LLC Owner KINGS GROUP NY CORP Filer KMA DESIGNS LLC | installation of heavy duty sidewalk shed. no change in use, occupancy or egress. all work to comply with chapter 33 of nycbc |
| M01348117 ↗ | 524 EAST 72 STREET MANHATTAN | Alteration | Permit Issued | 02/25/2026 | 07/10/2026 | Design ONSE Owner HSS Properties Corp Filer MUNICIPAL EXPEDITING INC | Garage repair including replacement of deteriorated sealant, vertica, overhead, topside, and full depth concrete repairs, and traffic coatin… |
| Q00851338 ↗ | 36-17 PARSONS BOULEVARD QUEENS | Alteration | Signed-off | 09/01/2023 | 07/10/2026 | SIDEWALK AND TOPPING SLAB REPLACEMENT, COURTYARD ROOF REPLACEMENT, DRAIN REPLACEMENT, COUNTER-FLASHING REPLACEMENT AND MISC. REPAIRS AS PER … | |
| B01065150 ↗ | 475 CARLTON AVENUE BROOKLYN | Alteration | Permit Issued | 09/18/2024 | 07/09/2026 | Design LAWLESS & MANGIONE | Filing for plaza and garage repairs as per plans filed herewith. No change in use occupancy or egress. |
| M01228881 ↗ | 211 EAST 122 STREET MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 07/06/2026 | Application filed for window replacements at all floors 6-35, as per drawings filed herewith. | |
| M01279561 ↗ | PIER 40 MANHATTAN | Alteration | Permit Issued | 10/09/2025 | 07/06/2026 | Owner HUDSON RIVER PARK TRUST | Concrete, masonry and steel repair on levels 1 and 2 of Pier 40. |
| M01420359 ↗ | 43 WATER STREET MANHATTAN | Alteration | Permit Issued | 07/01/2026 | 07/06/2026 | Design OFFICE OF JAMES RUDERMAN Owner NEW WATER STREET CORP Filer Integrated Companies | Structural work including concrete repair. |
| X01009729 ↗ | 1925 EASTCHESTER ROAD BRONX | Alteration | Permit Issued | 02/26/2024 | 07/02/2026 | Design EDG Filer LMS-ACE SERVICES | INSTALLATION OF TEMPORARY EMERGENCY NETTING AS PER PLANS FILEDHEREWITH. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B01215283 ↗ | 224 JAVA STREET BROOKLYN | Alteration | Permit Issued | 05/07/2025 | 07/01/2026 | Design JarmelKizel Architects | PROPOSED WORK FOR THE REPLACEMENT OF THE EXISTING FACADE FINISHES,INCLUDING THE EIFS ON 002 FLOOR, COPINGMATERIAL, METAL PANEL AND WINDOW RE… |
| M01065682 ↗ | 750 COLUMBUS AVENUE MANHATTAN | Alteration | Permit Issued | 08/30/2024 | 07/01/2026 | Owner EQUITY RESIDENTIAL | Facade repairs as per plans; no change to egress, use, or occupancy. |
| M01111725 ↗ | 1399 PARK AVENUE MANHATTAN | Alteration | Permit Issued | 10/04/2024 | 07/01/2026 | Design GACE DPC | Miscellaneous Facade Restoration as per plans. No change in use, egress or occupancy. |
| M01188910 ↗ | 1185 AVENUE OF THE AMER MANHATTAN | Alteration | Permit Issued | 04/02/2025 | 07/01/2026 | Owner SL GREEN REALTY CORP Filer RIZZO GROUP | Facade repairs as per plans. No change to use, egress or occupancy. |
| M01254631 ↗ | 5 WEST 65 STREET MANHATTAN | Alteration | Permit Issued | 07/23/2025 | 07/01/2026 | Herewith filing demolition and replacement of Sub-Cellar concrete slab as per plans. No Change in Use, Egress, or Occupancy is proposed unde… | |
| M01401276 ↗ | 767 3 AVENUE MANHATTAN | Alteration | Permit Issued | 05/14/2026 | 07/01/2026 | Design GACE DPC Owner 767 GC LLC Filer DVA Advisors | Slab reinforcement for new mechanical openings |
| X01031372 ↗ | 1925 EASTCHESTER ROAD BRONX | Alteration | Permit Issued | 09/20/2024 | 07/01/2026 | Design EDG | PROPOSED GARAGE REPAIRS AS PER PLANS FILEDHEREWITH. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01196616 ↗ | 817 BROADWAY MANHATTAN | Alteration | Signed-off | 07/07/2025 | 06/25/2026 | Design LOCI ARCHITECTURE PLLC | EXTERIOR WALL REPAIRS INCLUDING BRICK REPLACEMENT AND REPOINTING,AND TERRA COTTA AND LIMESTONE REPAIRS IN RESPONSE TO SUMMONS#35689466M. SID… |
| B01041323 ↗ | 180 MONTAGUE STREET BROOKLYN | Alteration | Permit Issued | 11/21/2024 | 06/23/2026 | Owner KINGS GROUP NY CORP Filer KMA DESIGNS LLC | INSTALLATION OF ROOF OVERHEAD PROTECTION. NO CHANGE IN USE, OCCUPANCY OR EGRESS. ALL WORK TO COMPLY WITH CHAPTER 33 OF NYCBC |
| M01366821 ↗ | 177 EAST 75 STREET MANHATTAN | Alteration | Permit Issued | 03/23/2026 | 06/22/2026 | Design THORNTON TOMASETTI Owner Joshua Baily Shipping Co Filer RIZZO GROUP | Structural modifications taking place on garage ramp from 1st to cellar level for repairs. No change in use, egress or occupancy. |
| M00948722 ↗ | 515 EAST 79 STREET MANHATTAN | Alteration | Permit Issued | 11/17/2023 | 05/27/2026 | Filer BG & ASSOCIATES | PLAZA RENOVATIONS AND GARAGE REPAIRS. NO CHANGE IN USE, EGRESS OR OCUPANCY. |
| S01372803 ↗ | 2636 HYLAN BLVD STATEN ISLAND | Alteration | Permit Issued | 03/18/2026 | 05/07/2026 | Design SOCOTEC, INC. Owner KIMCO REALTY | PARKING GARAGE REPAIRS AS INDICATED ON DRAWINGS. THERE IS NO CHANGE TO USE, EGRESS, OR OCCUPANCY |
| M01312170 ↗ | 2411 FREDRICK DOUGLASS BL MANHATTAN | Alteration | Permit Issued | 01/16/2026 | 05/01/2026 | Design WRG ENGINEERING, P.C. Owner L+M FUND MANAGEMENT LLC Filer WRG ENGINEERING, P.C. | Structural concrete repairs at an existing garage on the ground floor & terrace on top. No changes to use, egress, or certificate of occupan… |
| S01152337 ↗ | 561 RICHMOND TERRACE STATEN ISLAND | Alteration | Permit Issued | 02/03/2025 | 04/29/2026 | Owner REGAL ESTATES LLC Filer CAESAR BUSTAMANTE, AIA | Partial Demolition and repair of chimney. |
| M01129239 ↗ | 100 CHERRY STREET MANHATTAN | Alteration | Permit Issued | 10/19/2024 | 04/27/2026 | Design SULLIVAN ENGINEERING Owner L+M FUND MANAGEMENT LLC | Main roof & 12th floor Terraces roof restoration work including remove existing and install new roof system & railing. All work as per plan… |
| M01095659 ↗ | 450 WEST 17 STREET MANHATTAN | Alteration | Permit Issued | 03/06/2025 | 04/15/2026 | Design SPAR UNLIMITED LLC | Removal of the existing window assembly, partial closure of the opening to include installation of new interior and exterior wall, and insta… |
| Q01197863 ↗ | 48-18 NORTHERN BOULEVARD QUEENS | Alteration | Permit Issued | 03/27/2025 | 04/14/2026 | Design THORNTON TOMASETTI Filer JAM CONSULTANTS, INC. | STRUCTURAL WORK REINFORCEMENT/TYPICAL REPAIR AT EXISTINGROOF LEVEL. IMPROVEMENTS/MINOR MODIFICATIONS TO ROOFSLAB, DECK, BEAMS, COLUMNS AND C… |
| M01267352 ↗ | 209 SULLIVAN STREET MANHATTAN | Alteration | Permit Issued | 08/21/2025 | 03/27/2026 | Design SILMAN Owner THE LOVETT GROUP | Structural modifications including reinforcement of concrete girders. No changes in use, egress of occupancy. |
| M01359354 ↗ | 209 SULLIVAN STREET MANHATTAN | Alteration | Permit Issued | 03/16/2026 | 03/20/2026 | Owner THE LOVETT GROUP Filer BURNHAM NATIONWIDE INC | Filing herewith general construction to include waterproofing and structural modifications as per plans. |
| Q01058951 ↗ | 20-55 SEAGIRT BOULEVARD QUEENS | Alteration | Signed-off | 05/31/2024 | 03/19/2026 | Design RAS PE CONSULTING ENGINEERS | Structural repairs of existing parking garage. Repairs include beams, girders, columns and floor slab. |
| M01040700 ↗ | 41 WEST 86 STREET MANHATTAN | Alteration | Permit Issued | 08/30/2024 | 03/12/2026 | Owner EQUITY RESIDENTIAL | Facade repairs as per plans; no change to use, egress, or occupancy. |
| B01100280 ↗ | 1426 FREEPORT LOOP BROOKLYN | Alteration | Signed-off | 08/30/2024 | 03/04/2026 | Design SIMPSON GUMPERTZ & HEGER Owner BSC HOUSING COMPANY, INC Filer METROPOLIS GROUP INC | HEREWITH FILING LOCALIZED CONCRETE REPAIR OF SLABS, COLUMNS AND WALLS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATIO… |
| M01112618 ↗ | 199 WATER STREET MANHATTAN | Alteration | Permit Issued | 10/15/2024 | 02/26/2026 | Design GILSANZ MURRAY STEFICEK LLP Owner RESNICK SEAPORT, LLC Filer JAM CONSULTANTS, INC. | Garage repair to include surface preparation and patching of existing concrete slabs |
| X00910254 ↗ | 2500 JOHNSON AVENUE BRONX | Alteration | Permit Issued | 08/14/2024 | 02/26/2026 | 9th Cycle FISP repairs. No change to use, occupancy or egress. | |
| B01347414 ↗ | 177 VANDALIA AVENUE BROOKLYN | Alteration | Signed-off | 02/05/2026 | 02/17/2026 | Design SIMPSON GUMPERTZ & HEGER | HEREWITH FILING STRUCTURAL REPAIRS TO ADDRESS VIOLATIONS 122625C25-03338 AND 39171671K PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDE… |
| X01177978 ↗ | 613 EAST 233 STREET BRONX | Alteration | Permit Issued | 02/07/2025 | 02/06/2026 | Design EDG Filer LMS-ACE SERVICES | TEMPORARY SHORING AND NETTING INSTALLATION AS PER PLANS SUBMITTED HEREWITH. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B00757417 ↗ | 41 EASTERN PARKWAY BROOKLYN | Alteration | Permit Issued | 08/19/2022 | 02/03/2026 | 8th Cycle Facade Repair and Roofing Replacement Program. No change in use, egress or occupancy. | |
| M00792996 ↗ | 420 LEXINGTON AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2022 | 01/27/2026 | Owner SL GREEN REALTY CORP | FACADE REPAIRS CONSISTING OF THE FOLLOWING MINOR STEEL REPAIRS, CAST IRON REPAIRS AND REPLACEMENT, CONCRETE REPAIRS AND REPLACEMENT, BRICKMA… |
| M01163583 ↗ | 711 3 AVENUE MANHATTAN | Alteration | Permit Issued | 01/15/2025 | 01/27/2026 | Owner SL GREEN REALTY CORP | SHORING AND NETTING TO BE INSTALLED AS PER DRAWINGS FOR LOCAL LAW 11 REPAIRS |
| M01217537 ↗ | 2081 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 05/01/2025 | 01/22/2026 | Design EOC-NY Owner Monadnock Development | PROPOSED FACADE RESTORATION AS PER PLANS NO CHANGE TO USE EGRESS OR OCCUPANCY. |
| M00792999 ↗ | 420 LEXINGTON AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2022 | 01/13/2026 | CON-ED ENCLOSURE REPAIRS CONSISTING OF THE FOLLOWING: CONCRETE REPAIRS, STEEL REINFORCEMENT AND PAINTING, ROOF REPLACEMENT, LADDER REPLACEME… | |
| M00936083 ↗ | 310 GREENWICH STREET MANHATTAN | Alteration | Permit Issued | 12/10/2023 | 01/12/2026 | Design TARIQ M. BASHIR | Garage Repairs as per plans |
| M00936087 ↗ | 310 GREENWICH STREET MANHATTAN | Alteration | Permit Issued | 10/26/2023 | 01/12/2026 | Design TARIQ M. BASHIR | MISC CONCRETE REPAIRS IN GARAGE AS PER PLANS |
| Q01299358 ↗ | 165-15 ARCHER AVENUE QUEENS | Alteration | Signed-off | 10/24/2025 | 01/09/2026 | Design PVE ENGINEERING | PROPOSED PARKING GARAGE CONCRETE AND REMEDIAL STRUCTURAL REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B00790059 ↗ | 652 KENT AVENUE BROOKLYN | Alteration | Permit Issued | 08/10/2022 | 12/19/2025 | Design THORNTON TOMASETTI | Remedial Facade work to include but not limited to localized facade concrete panel repairs. No change in use, egress or occupancy under this… |
| B00910856 ↗ | 652 KENT AVENUE BROOKLYN | Alteration | Permit Issued | 08/17/2023 | 12/19/2025 | Design SOCOTEC, INC. Owner BOSTON PROPERTIES | TEMPORARY INSTALLATION OF SUSPENDED SCAFFOLD USING DAVIT SYSTEM. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M00865353 ↗ | 105 MADISON AVENUE MANHATTAN | Alteration | Permit Issued | 05/10/2023 | 12/19/2025 | Design O&S ASSOCIATES Owner A&R Filer MK ARCHITECTURE PC | Exterior Wall Repairs. No change to use, occupancy or egress. |
| M01083159 ↗ | 304 PARK AVENUE SOUTH MANHATTAN | Alteration | Permit Issued | 07/26/2024 | 12/19/2025 | Owner SL GREEN REALTY CORP Filer RIZZO GROUP | Roof replacement (Roof A) as per plans. No change to use, egress or occupancy. |
| B01046566 ↗ | 475 CARLTON AVENUE BROOKLYN | Alteration | Permit Issued | 06/10/2024 | 12/15/2025 | Design LAWLESS & MANGIONE | Filing for facade repairs as per plans filed herewith. No change in use, occupancy or egress. |
| B01206776 ↗ | 186 VANDALIA AVENUE BROOKLYN | Alteration | Permit Issued | 05/13/2025 | 12/11/2025 | Design SIMPSON GUMPERTZ & HEGER Owner BSC HOUSING COMPANY, INC Filer METROPOLIS GROUP INC | HEREWITH FILING LOCALIZED CONCRETE REPAIR OF SLABS, COLUMNS AND WALLS FOR GARAGE B PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER TH… |
| M01123362 ↗ | 100 CHERRY STREET MANHATTAN | Alteration | Permit Issued | 10/21/2024 | 12/11/2025 | Design RIMKUS NEW YORK PLLC Owner L+M FUND MANAGEMENT LLC Filer RIMKUS NEW YORK PLLC | Exterior facade and waterproofing repairs including lintel replacements and partial parapet rebuild as per plans submitted. No change in us… |
| B00718907 ↗ | 41 EASTERN PARKWAY BROOKLYN | Alteration | Permit Issued | 08/19/2022 | 12/10/2025 | Structural work to be performed at Penthouse Roof & Water Tank to facilitate 8th Cycle Facade Repair & Roofing Replacement Program. No chang… | |
| M01123365 ↗ | 100 CHERRY STREET MANHATTAN | Alteration | Permit Issued | 10/22/2024 | 12/10/2025 | Design SULLIVAN ENGINEERING | Exterior facade repairs including brick replacements and repointing as necessary. All work as per plans submitted herewith. No change in u… |
| B01046542 ↗ | 475 CARLTON AVENUE BROOKLYN | Alteration | Permit Issued | 06/06/2024 | 12/05/2025 | Design LAWLESS & MANGIONE Owner PRESTIGE MANAGEMENT INC. Filer BG & ASSOCIATES | Filing for facade repairs as per plans filed herewith. No change in use, occupancy or egress. |
| X01303155 ↗ | EAST 13 STREET BRONX | Alteration | Permit Issued | 11/18/2025 | 12/03/2025 | Design O&S ASSOCIATES Owner METRO MANAGEMENT Filer O&S ASSOCIATES | Herewith filing for repairs to this existing 2-family building. No Change to use, occupancy or egress. |
| M01291381 ↗ | 68 EAST 11 STREET MANHATTAN | Alteration | Permit Issued | 10/16/2025 | 11/26/2025 | Owner Avis Budget Group Filer JULIAN A. GOMEZ | Parking Structure Repair Program. No change In Use, Egress or Occupancy. |
| M01252309 ↗ | 31 WEST 15 STREET MANHATTAN | Alteration | Permit Issued | 07/29/2025 | 11/06/2025 | Design SIMPSON GUMPERTZ & HEGER Owner FirstService Residential | REPAIR AND REPLACEMENT OF JOINT SEALANTS AND GRANITE PANELS. |
| M01090549 ↗ | 100 11 AVENUE MANHATTAN | Alteration | Signed-off | 08/08/2024 | 10/31/2025 | — | PROPOSED REPAIR TO EX. FAC+ ROF TO INCLUDE, BUT NOT LIMITED TO, REPAIR OR ALUMINUM FRAMED WINDOWS, CRACKS IN MORTAR JOINTS + BRICKS. CHIMNEY… |
| B01027289 ↗ | 225 AVENUE T BROOKLYN | Alteration | Permit Issued | 04/04/2024 | 10/27/2025 | Design LAWLESS & MANGIONE Filer BG & ASSOCIATES | FILING FOR FACADE REPAIRS, BALCONY REPAIRS, BRICK REPLACEMENT, POINTING, SILL REPLACEMENT, SHELF ANGLE REPLACEMENT, INTERIOR REPAIRS/UPGRADE… |
| M01265276 ↗ | 181 EAST 65 STREET MANHATTAN | Alteration | Signed-off | 08/04/2025 | 09/25/2025 | Filer PEROTTO CONSULTING MGT | #8973 - Minor structural modifications to interior column. No change in egress, use, or occupancy. |
| M01285806 ↗ | 315 EAST 102 STREET MANHATTAN | Alteration | Permit Issued | 09/12/2025 | 09/25/2025 | Design IMEG Consulting Corp. Owner Phipps Houses Filer JM ZONING, LLC. | Concrete repairs at cellar level, no change to use egress or occupancy. |
| M01247707 ↗ | 888 7 AVENUE MANHATTAN | Alteration | Permit Issued | 08/18/2025 | 09/24/2025 | Design GILSANZ MURRAY STEFICEK LLP | Structural work on sub-cellar 2, sub-cellar 1 and cellar levels (LL126 Parking Garage Repairs) as indicated on drawings. |
| M00951064 ↗ | 340 EAST 24 STREET MANHATTAN | Alteration | Signed-off | 04/12/2024 | 09/22/2025 | Owner CBRE | 9th Cycle Facade Inspection and Safety Repair Program. No changes to use, egress, or occupancy. |
| M01200469 ↗ | 1239 MADISON AVENUE MANHATTAN | Alteration | Signed-off | 04/24/2025 | 09/10/2025 | Design SOCOTEC, INC. | Garage repairs. No change in egress, use or occupancy. |
| B01057503 ↗ | 311 MARCUS GARVEY BLVD BROOKLYN | Alteration | Permit Issued | 06/18/2024 | 09/05/2025 | Design O&S ASSOCIATES | Filing for repairs to existing garage and roof over garage. No change to occupancy, egress or use. |
| B00914196 ↗ | 350 JAY STREET BROOKLYN | Alteration | Signed-off | 08/10/2023 | 08/26/2025 | Design OFFICE OF JAMES RUDERMAN Owner MUSS DEVELOPMENT LLC | New replacement slab with temp shorting |
| M01049057 ↗ | 345 SOUTH END AVENUE MANHATTAN | Alteration | Signed-off | 07/26/2024 | 08/12/2025 | Design O&S ASSOCIATES Filer MK ARCHITECTURE PC | Waterproofing and slab repairs at exterior plaza. no change to use, occupancy or egress. |
| M01249738 ↗ | 515 AUDUBON AVENUE MANHATTAN | Alteration | Permit Issued | 07/15/2025 | 08/11/2025 | Design WALKER CONSULTANTS | PARKING GARAGE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| M00986283 ↗ | 515 EAST 79 STREET MANHATTAN | Alteration | Permit Issued | 02/13/2024 | 08/05/2025 | Filer BG & ASSOCIATES | FILING FOR LANDSCAPING WORK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCPANCY. |
| 322017722BIS | 79 CLARK STREET BROOKLYN | — | ISSUED | 08/05/2021 | 08/04/2025 | — | OT |
| Q01047187 ↗ | 4-74 48 AVENUE QUEENS | Alteration | Permit Issued | 05/09/2024 | 07/28/2025 | Owner AKAM ASSOCIATES, INC. | Exterior restoration to include brick replacement, concrete repairs and patching as per plans filed herewith. No change to use, egress or o… |