Elevator apt, miscellaneous
Taft (NYCHA)
1337 5 AVENUE · BIN 1080509
💬 Discuss this project
1959Year Built
19Stories
D9Building Class
R7-2Zoning
865,481 sfGross Floor Area
800Units
LL97 Covered2 Open Violations ▸FISP: UNSAFE
Elevator apt, miscellaneous · Owner of record: NYC HOUSING AUTHORITY · 298,710 sf lot · 2.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Permit Issued — active, not yet Signed-off
RoofUnder Construction8p · 1 filing · 4 docs
15 jobs · most recent 08/31/2026
General Wiring Lighting
FiledStatusContractorScope
08/31/2026Permit IssuedLIT MODE ELECL CONTG INC—
08/31/2026Permit IssuedLIT MODE ELECL CONTG INC—
07/06/2026Permit IssuedKRISCORP ELECL CONTNG INC1 meters, 1 new_meters
04/16/2026Permit IssuedJEMCO ELECT. CONTRS INCGeneral Wiring
03/24/2026Permit IssuedLIT MODE ELECL CONTG INC—
05/20/2025CompleteAPEX ELECTRIC CORPGeneral Wiring
09/05/2024Permit IssuedB.P. ELECTRIC CORP—
05/29/2024CompleteTRU-VAL ELECTRIC CORP.General Wiring
03/06/2024CancelledKRISCORP ELECL CONTNG INC1 meters, 1 new_meters
12/22/2023CompleteTRU-VAL ELECTRIC CORP.General Wiring, Lighting
07/11/2023CompleteTOUCHTEL TECHNOLOGY GROUPGeneral Wiring
05/24/2023CancelledEMENAR ELECL SVCS CONSTGeneral Wiring
04/14/2023CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
10/03/2019Permit IssuedAMIN ELECTRICAL CORP—
02/22/2019CompleteTRU-VAL ELECTRIC CORP.—
3 jobs · most recent 07/31/2026
Scaffold Fence Sidewalk Shed
FiledStatusContractorScope
07/31/2026Permit IssuedMNK ENTERPRISES LLCScaffold
06/17/2020Permit IssuedMNK ENTERPRISES LLCFence
06/17/2020Permit IssuedMNK ENTERPRISES LLCSidewalk Shed
1 job · most recent 04/04/2026
Suspended Scaffold
FiledStatusContractorScope
04/04/2026Permit IssuedZIRCON GROUP INCSuspended Scaffold
2 jobs · most recent 04/04/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
04/04/2026Permit IssuedZIRCON GROUP INCSuspended Scaffold (SC)
03/25/2026Permit IssuedP&K CONTRACTING INCSuspended Scaffold (SC)
Building Lifecycle
All (141)Filed (19)Permit Issued (30)Signed Off (5)Facade (FISP) (17)Violation (36)Objection (4)Special Inspection (30)
08/03/2026
Permit issued — Supported Scaffold
M01438222-I1-SF
07/31/2026
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 1740 MADISON AVENUE MANHATTAN NY 10029 AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01438222-I1
07/29/2026
Special inspection requirement — Post-installed Anchors
WALIUR RAHMAN
07/20/2026
Permit issued — Sidewalk Shed
M00333511-I1-SH
07/17/2026
Permit issued — Construction Fence
M00333516-I1-FN
07/09/2026
Permit issued — General Construction
M01319225-I1-GC
05/08/2026
Signed off — Alteration
Amendment for Suspended Scaffold out rigger installation for Facade inspections
M01344327-I1
05/05/2026
Cycle 10 facade report submitted
05/04/2026
Cycle 10 facade inspection completed
04/22/2026
Permit issued — General Construction
M00906638-I1-GC
04/09/2026
Special inspection requirement — Post-installed Anchors
Md Istiaque Hasan
04/09/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Md Istiaque Hasan
04/04/2026
Filed — Alteration
Amendment for Suspended Scaffold out rigger installation for Facade inspections
M01344327-P1
03/31/2026
Permit issued — Suspended Scaffold
M01376876-I1-SC
03/25/2026
Filed — Alteration
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM FOR EXTERIOR FACADE RESTORATION WORK AND FACADE INSPECTION AT 1734 MADISON AVENUE, MANHATTAN NY 10029
M01376876-I1
03/19/2026
Cycle 10 facade report signed — UNSAFE
02/05/2026
Permit issued — Suspended Scaffold
M01344327-I1-SC
01/22/2026
Objection resolved — Addressed
01/21/2026
Objection raised — Admin
01/14/2026
Filed — Alteration
Amendment for Suspended Scaffold out rigger installation for Facade inspections
M01344327-I1
12/04/2025
Filed — Alteration
FACADE RESTORATION AS PER INDICATED ON PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01319225-I1
12/04/2025
Special inspection requirement — Tenant Protection Plan Compliance
JACOB HAAS
12/04/2025
Special inspection requirement — Final
JACOB HAAS
12/04/2025
Special inspection requirement — Masonry
JACOB HAAS
12/04/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
JACOB HAAS
07/14/2025
Permit issued — Sidewalk Shed
M00333511-I1-SH
07/11/2025
Permit issued — Construction Fence
M00333516-I1-FN
07/03/2024
Permit issued — Sidewalk Shed
M00333511-I1-SH
07/01/2024
Permit issued — Construction Fence
M00333516-I1-FN
04/25/2024
Signed off — Alteration
Install new ventilation system for domestic water and replace duplex vacuum and condensate pump as shown on plans
M00265602-I1
04/24/2024
Signed off — Alteration
Installation of new concrete pad, hangers and supports in cellar boiler room in as shown on plans filed herewith.
M00265597-I1
02/05/2024
Permit issued — Sidewalk Shed
M00333511-I1-SH
01/31/2024
Permit issued — Construction Fence
M00333516-I1-FN
10/19/2023
Permit issued — Structural
M00265597-I1-ST
09/07/2023
Objection resolved — Addressed
08/10/2023
Objection raised — Other
07/28/2023
Filed — Alteration
M00906645-I1
07/28/2023
Filed — Alteration
INSTALLATION OF NEW 8FT HIGH ALUMINUM FENCE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY. Application to be reviewed with the Development HUB.
M00906638-I1
07/19/2023
Special inspection requirement — Final
CONNIE PISANI
07/19/2023
Special inspection requirement — Tenant Protection Plan Compliance
CONNIE PISANI
06/13/2023
Filed — Alteration
Install new ventilation system for domestic water and replace duplex vacuum and condensate pump as shown on plans
M00265602-P3
06/13/2023
Special inspection requirement — Chimneys and vents
GEORGE GHEBRYAL
06/13/2023
Special inspection requirement — Mechanical Systems
GEORGE GHEBRYAL
06/13/2023
Special inspection requirement — Final
GEORGE GHEBRYAL
06/13/2023
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
03/07/2023
Cycle 9 facade report submitted
03/06/2023
Permit issued — Construction Fence
M00333516-I1-FN
03/03/2023
Permit issued — Sidewalk Shed
M00333511-I1-SH
02/22/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/03/2023
Cycle 9 facade report signed — UNSAFE
01/10/2023
Cycle 9 facade inspection completed
01/05/2023
Permit issued — Mechanical Systems
M00265602-I1-MS
05/11/2022
Permit issued — Mechanical Systems
M00265602-I1-MS
04/11/2022
Permit issued — Sidewalk Shed
M00333511-I1-SH
04/07/2022
Permit issued — Construction Fence
M00333516-I1-FN
12/17/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/17/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/22/2021
Permit issued — Sidewalk Shed
M00333511-I1-SH
06/22/2021
Permit issued — Construction Fence
M00333516-I1-FN
06/11/2021
Special inspection requirement — Final
GEORGE GHEBRYAL
Latest 60 of 141 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA6108/04/2026
NYCHA 99503/22/2026
TECHNICO CONSTRUCTION SER103/22/2026
NYC HOUSING AUTHORITY1403/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S M EXPEDITING1203/21/2026
KINGSTON ENGINEERING203/21/2026
D&B ENGINEERS AND ARCHITECTS403/21/2026
MUNICIPAL BUILDING CONSULTANTS203/21/2026
AK CONSULTING SERVICES803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MNK ENTERPRISES LLCGeneral Contractor2108/04/2026
SKYWORX CONTRACTING INCGeneral Contractor1007/08/2026
FRAMAN MECHANICAL INCGeneral Contractor1007/08/2026
P & K CONTRACTING INCGeneral Contractor407/10/2026
JCC CONSTRUCTION CORPPlumbing203/22/2026
RODLAND, GLENNElectrical103/21/2026
SALADEEN ALCHAIBElectrical103/21/2026
TRU-VAL ELECTRIC CORP.Electrical103/22/2026
WHALEN, WILLIAMElectrical103/21/2026
JEMCO ELECTRICAL CONT INCGeneral Contractor107/08/2026
ANZELM KRYSAElectrical103/21/2026
SKYLINE P & H INCPlumbing103/22/2026
APEX ELECTRIC CORPElectrical103/22/2026
CPH PIPELINE OF N Y INCElectrical103/21/2026
JEFFREY, DARRINElectrical103/21/2026
MIRINO, MICHAELElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK CONSULTING SERVICES, I6198207/31/2026
RI CONSULTING SERVICES IN8904204/04/2026
20/20 INSPECTIONS INC1471112/04/2025
AMARACON TESTING & INSPEC5842207/28/2023
TECTONIC ENGINEERING CONS106906/13/2023
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedMNK ENTERPRISES LLC08/03/2026
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC07/20/2026
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC07/17/2026
DOB NOWGeneral ConstructionPermit IssuedP & K CONTRACTING INC07/09/2026
DOB NOWGeneral ConstructionPermit IssuedJEMCO ELECTRICAL CONT INC04/22/2026
DOB NOWSuspended ScaffoldPermit IssuedVENTURE NK CORP03/31/2026
DOB NOWSuspended ScaffoldPermit IssuedZIRCON GROUP INC02/05/2026
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC07/14/2025
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC07/11/2025
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC07/03/2024
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC07/01/2024
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC02/05/2024
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC01/31/2024
DOB NOWStructuralSigned-offFRAMAN MECHANICAL10/19/2023
DOB NOWConstruction FencePermit IssuedMNK ENTERPRISES LLC03/06/2023
DOB NOWSidewalk ShedPermit IssuedMNK ENTERPRISES LLC03/03/2023
DOB NOWMechanical SystemsSigned-offFRAMAN MECHANICAL01/05/2023
DOB NOWMechanical SystemsSigned-offFRAMAN MECHANICAL05/11/2022
DOB NOWSidewalk ShedPermit IssuedSKYWORX CONTRACTING INC04/11/2022
DOB NOWConstruction FencePermit IssuedSKYWORX CONTRACTING INC04/07/2022
DOB NOWSidewalk ShedPermit IssuedSKYWORX CONTRACTING INC06/22/2021
DOB NOWConstruction FencePermit IssuedSKYWORX CONTRACTING INC06/22/2021
DOB NOWMechanical SystemsSigned-offFRAMAN MECHANICAL05/05/2021
DOB NOWMechanical SystemsSigned-offFRAMAN MECHANICAL04/27/2021
DOB NOWMechanical SystemsSigned-offFRAMAN MECHANICAL12/22/2020
DOB NOWMechanical SystemsSigned-offFRAMAN MECHANICAL08/04/2020
DOB NOWSidewalk ShedPermit IssuedSKYWORX CONTRACTING INC06/18/2020
DOB NOWConstruction FencePermit IssuedSKYWORX CONTRACTING INC06/18/2020
DOB NOWConstruction FenceSigned-offP & K CONTRACTING INC10/24/2019
DOB NOWSidewalk ShedSigned-offP & K CONTRACTING INC10/18/2019
BISPLISSUEDVARSITY PLBG AND HTG INC02/06/2023
BISPLISSUEDVARSITY PLBG AND HTG INC02/02/2022
BISPLISSUEDVARSITY PLBG AND HTG INC02/08/2021
BISPLISSUEDVARSITY PLBG AND HTG INC07/29/2019
BISOTISSUEDTECHNICO CONSTRUCTION03/23/2015
BISEQISSUEDROMA SCAFFOLDING INC03/16/2015
BISEQISSUEDTECHNICO CONSTRUCTION02/23/2015
BISEQISSUEDROMA SCAFFOLDING INC12/04/2014
BISEQISSUEDMETRO. BRIDGE & SCAF. COR10/03/2014
BISEQISSUEDMETRO. BRIDGE & SCAF. COR09/23/2013
+ 11 more permits on file
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
07/29/2026Post-installed AnchorsWALIUR RAHMANspecial
04/09/2026Post-installed AnchorsMd Istiaque Hasanspecial
04/09/2026Alternative Materials - OTCR Buildings Bulletin NumberMd Istiaque Hasanspecial
12/04/2025Tenant Protection Plan ComplianceJACOB HAASspecial
12/04/2025FinalJACOB HAASprogress
12/04/2025MasonryJACOB HAASspecial
12/04/2025Structural Stability – Alterations of existing buildingsJACOB HAASspecial
07/19/2023FinalCONNIE PISANIprogress
07/19/2023Tenant Protection Plan ComplianceCONNIE PISANIspecial
06/13/2023Chimneys and ventsGEORGE GHEBRYALspecial
06/13/2023Mechanical SystemsGEORGE GHEBRYALspecial
06/13/2023FinalGEORGE GHEBRYALprogress
06/13/2023Maintenance informationGEORGE GHEBRYALenergy_progress
06/11/2021FinalGEORGE GHEBRYALprogress
06/11/2021Post-installed AnchorsGEORGE GHEBRYALspecial
06/11/2021Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
06/11/2021Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
06/11/2021MasonryGEORGE GHEBRYALspecial
05/16/2021Post-installed AnchorsGEORGE GHEBRYALspecial
05/16/2021Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
05/16/2021Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
05/16/2021MasonryGEORGE GHEBRYALspecial
05/16/2021FinalGEORGE GHEBRYALprogress
01/06/2021Post-installed AnchorsGEORGE GHEBRYALspecial
09/24/2020FinalGEORGE GHEBRYALprogress
Latest 25 of 36.
▾Documents — 269 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch6
08/29/2026M00906638-I1Request digital key ↗
08/29/2026M00906645-I1Request digital key ↗
08/20/2026M01319225-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Structural4
09/03/2026M00265597-I1Request digital key ↗
08/15/2026M00265597-P3Request digital key ↗
08/15/2026M00265597-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems4
09/05/2026M00265602-P2Request digital key ↗
09/05/2026M00265602-P1Request digital key ↗
09/05/2026M00265602-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence2
09/05/2026M00248334-I1Request digital key ↗
09/04/2026M00333516-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00246343-I1Request digital key ↗
09/04/2026M00333511-I1Request digital key ↗
▸Applications & Permits38
▸BISPLAN / WORK APPROVAL APPLICATION27
09/18/2023123475444Open ↗
09/14/2023123475444Open ↗
09/01/2023123475444Open ↗
Showing 3 of 27 on file for this type
▸BISWORK PERMIT APPLICATION10
07/29/2019123475444Open ↗
03/30/2015121967862Open ↗
02/22/2015140310330Open ↗
Showing 3 of 10 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
07/30/2020123475444Open ↗
▸Seals & Professional Certifications77
▸DOB NOWDPL-1: Design Professional Seal & Signature17
09/05/2026M00248334-I1Open ↗
09/05/2026M00265602-P1Open ↗
09/05/2026M00265602-P2Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature17
09/22/2026M00265597-I1Open ↗
09/01/2026M00265597-P2Open ↗
09/01/2026M00265597-P2Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION13
08/14/2019123475444Open ↗
07/12/2019123475444Open ↗
07/03/2019123475444Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/22/2026M00265597-I1Open ↗
09/01/2026M00265597-P2Open ↗
08/29/2026M00906638-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST7
09/14/2023123475444Open ↗
08/14/2019123475444Open ↗
08/12/2019123475444Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT7
09/27/2018123475444Open ↗
09/19/2018123475444Open ↗
09/19/2018123475444Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
02/22/2015140310330Open ↗
02/22/2015140310321Open ↗
—140285670Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
02/22/2015140310330Open ↗
02/22/2015140310321Open ↗
—140285670Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
03/15/2011120626661Open ↗
01/28/2010120253297Open ↗
▸Trade Schedules & Equipment11
▸BISSCHEDULE B - PLUMBING3
02/09/2023123475444Open ↗
04/08/2022123475444Open ↗
03/15/2011120626661Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
09/27/2018123475444Open ↗
09/19/2018123475444Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT2
01/23/2024123475444Open ↗
01/23/2024123475444Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS2
01/23/2024123475444Open ↗
01/23/2024123475444Open ↗
▸BISPLUMBING (PL) SIGNOFF1
01/23/2024123475444Open ↗
▸BISEQUIPMENT USE PERMITS1
09/21/2023123475444Open ↗
▸Safety & Tenant Protection13
▸DOB NOWTenant Protection Plan12
09/05/2026M00248334-I1Open ↗
09/05/2026M00265602-P2Open ↗
09/05/2026M00265602-P1Open ↗
Showing 3 of 12 on file for this type
▸BISTenant Protection Plan and Notes1
10/17/2018123475444Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
09/05/2026M00265602-I1Open ↗
09/05/2026M00265602-P1Open ↗
09/05/2026M00265602-P2Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
05/21/2020123475444Open ↗
07/29/2019123475444Open ↗
▸BISTHIS IS NOT AN ASBESTOS PROJECT2
07/08/2011120626661Open ↗
07/08/2011120626661Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
01/28/2010120253297Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
04/04/2016121967862Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
07/03/2019123475444Open ↗
09/27/2018123475444Open ↗
04/04/2016121967862Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/25/2023123475444Open ↗
07/18/2020123475444Open ↗
07/02/2020123475444Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
04/04/2016121967862Open ↗
04/04/2016121967862Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
01/23/2024123475444Open ↗
▸BISPROVIDE ORIGINAL TR8 WITH PROGRESSINSPECTION SEAL/SIGNATURE IN SEC.51
02/14/2024123475444Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
01/23/2024123475444Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
—140285670Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY7
09/25/2023123475444Open ↗
04/08/2022123475444Open ↗
07/18/2020123475444Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
08/14/2019123475444Open ↗
▸Approvals, Objections & Sign-offs51
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter18
09/05/2026M00248334-I1Open ↗
09/05/2026M00265602-P2Open ↗
09/05/2026M00265602-P1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)12
09/05/2026M00248334-I1Open ↗
09/05/2026M00265602-I1Open ↗
09/05/2026M00265602-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)6
09/05/2026M00248334-I1Open ↗
09/05/2026M00265602-I1Open ↗
08/13/2026M00265597-I1Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
02/14/2024123475444Open ↗
04/04/2016121967862Open ↗
12/03/2015140285670Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
10/13/2014120253297Open ↗
10/13/2014120253297Open ↗
10/13/2014120253297Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
03/15/2011120626661Open ↗
01/28/2010120253297Open ↗
▸BISFINAL1
01/23/2024123475444Open ↗
▸BISSHED LETTER1
09/30/2013120253297Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
11/16/2015121967862Open ↗
▸DOB NOWDEP Variance (V5) letter1
08/20/2026M01319225-I1Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT4
09/27/2018123475444Open ↗
04/04/2016121967862Open ↗
04/10/2014121967862Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
02/14/2024123475444Open ↗
▸Filing & Intake Forms13
▸BISADDITIONAL INFORMATION5
04/29/2022123475444Open ↗
04/13/2022123475444Open ↗
09/18/2020123475444Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
09/19/2018123475444Open ↗
04/10/2014121967862Open ↗
03/15/2011120626661Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
02/22/2015140310330Open ↗
02/22/2015140310321Open ↗
—140285670Open ↗
▸BISBOROUGH INTAKE FORM1
08/12/2019123475444Open ↗
▸Other Documents7
▸DOB NOWManufacturer's Specifications3
08/19/2026M01344327-P1Open ↗
08/13/2026M01376876-I1Open ↗
08/13/2026M01344327-I1Open ↗
▸DOB NOWCalculations3
08/19/2026M01344327-P1Open ↗
08/13/2026M01376876-I1Open ↗
08/13/2026M01344327-I1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
04/10/2014121967862Open ↗