| Owner | Filings | Most Recent |
|---|---|---|
| MACYS | 62 | 09/07/2026 |
| METROPOLITAN CONSTRUCTION SYSTEMS I | 8 | 07/08/2026 |
| MACY'S INC. | 44 | 03/22/2026 |
| CROWN RETAIL SERVICES | 13 | 03/22/2026 |
| TRI BOROUGH SCAFFOLDING | 6 | 03/22/2026 |
| CROWN ACQUISITIONS | 3 | 03/22/2026 |
| 136-32 ROOSEVELT LLC | 3 | 03/22/2026 |
| BENIDER COMPANY | 12 | 03/22/2026 |
| BENIDA COMPANY, LLC | 1 | 03/22/2026 |
| BENEDEZ COMPANY LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KZ ENGINEERING, P.C | 7 | 06/30/2026 |
| MATTHEW DAVID HICKEY ARCHITECT PLLC | 1 | 04/14/2026 |
| FISKAA ENGINEERING | 5 | 12/03/2025 |
| CALLISONRTKL ARCHITECTS, P.C. | 1 | 11/21/2025 |
| NELSON ARCHITECTURE &INTERIORS, INC | 9 | 04/07/2025 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 1 | 03/25/2024 |
| CAESAR BUSTAMANTE, AIA | 1 | 09/23/2022 |
| O'NEIL LANGAN ARCHITECTS, P.C. | 1 | 09/20/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 4 | 03/21/2026 |
| DOMINION EXPEDITING | 9 | 03/21/2026 |
| Integrated Companies | 5 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 2 | 03/21/2026 |
| INTEGRATED C O MILROSE CONSULTANTS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRI BOROUGH SCAFFOLDING | General Contractor | 9 | 03/21/2026 |
| BUCH CONSTRUCTION, INC | General Contractor | 5 | 07/08/2026 |
| BRELLA SERVICES LLC | General Contractor | 4 | 07/03/2026 |
| PAR PLUMBING CO., INC | Plumbing | 4 | 07/08/2026 |
| J. PHELAN CONSTRUCTION CO | General Contractor | 4 | 03/21/2026 |
| CREATIVE INSTALLATIONS IN | General Contractor | 4 | 07/08/2026 |
| ACM CONSULTING CORP | General Contractor | 3 | 03/21/2026 |
| STARR INDUSTRIES LLC | General Contractor | 3 | 07/08/2026 |
| METROPOLITAN CONSTRUCTION | General Contractor | 2 | 09/07/2026 |
| ACM ELECTRIC CORPORATION | Electrical | 2 | 03/22/2026 |
| S & P CONSTRUCTION MGMT.I | Electrical | 1 | 03/21/2026 |
| SHORR, GLENN | Electrical | 1 | 03/21/2026 |
| RICOTTA, THOMAS | Electrical | 1 | 03/21/2026 |
| MARCIAL, MARIO | Electrical | 1 | 03/21/2026 |
| RATHDURAGE, DAMITH | Electrical | 1 | 03/21/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 1 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 1 | 07/08/2026 |
| V. VASS ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONCRETE SOLUTIONS LAB CO | 5344 | 4 | 12/03/2025 |
| SHAHRISH SHUVO ENGINEERIN | 8524 | 6 | 04/07/2025 |
| MILROSE CONSULTANTS LLC | 2003 | 3 | 03/25/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | METROPOLITAN CONSTRUCTION | 07/10/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | BRELLA SERVICES LLC | 07/01/2026 |
| DOB NOW | General Construction | Permit Issued | METROPOLITAN CONSTRUCTION | 05/29/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | BRELLA SERVICES LLC | 04/27/2026 |
| DOB NOW | Construction Fence | Permit Issued | BRELLA SERVICES LLC | 04/27/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | BRELLA SERVICES LLC | 04/27/2026 |
| DOB NOW | Sprinklers | Permit Issued | LAWRENCE J. LEVINE | 12/19/2025 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 12/19/2025 |
| DOB NOW | General Construction | Signed-off | BUCH CONSTRUCTION, INC | 12/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BUCH CONSTRUCTION, INC | 12/09/2025 |
| DOB NOW | Sprinklers | Signed-off | PAR PLUMBING CO., INC | 02/20/2025 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 01/30/2025 |
| DOB NOW | General Construction | Signed-off | J PHELAN CONSTRUCTION | 01/09/2025 |
| DOB NOW | Mechanical Systems | Signed-off | J PHELAN CONSTRUCTION | 01/09/2025 |
| DOB NOW | Structural | Signed-off | BUCH CONSTRUCTION, INC | 03/29/2024 |
| DOB NOW | Sprinklers | Signed-off | PAR PLUMBING CO., INC | 10/07/2021 |
| DOB NOW | Mechanical Systems | Signed-off | CREATIVE INSTALLATIONS IN | 10/06/2021 |
| DOB NOW | General Construction | Permit Issued | CREATIVE INSTALLATIONS IN | 10/06/2021 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 10/01/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | STARR INDUSTRIES LLC | 06/24/2019 |
| DOB NOW | Supported Scaffold | Signed-off | STARR INDUSTRIES LLC | 06/21/2019 |
| DOB NOW | Construction Fence | Signed-off | STARR INDUSTRIES LLC | 06/21/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | TRI BOROUGH SCAFFOLDING | 03/29/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | TRI BOROUGH SCAFFOLDING | 11/28/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | TRI BOROUGH SCAFFOLDING | 09/17/2018 |
| BIS | OT | ISSUED | JOHN O'HARA CO., INC | 03/19/2020 |
| BIS | OT | ISSUED | JOHN O'HARA CO., INC | 03/19/2020 |
| BIS | OT | ISSUED | METROPOLITAN CONSTRUCTION | 07/23/2019 |
| BIS | OT | ISSUED | METROPOLITAN CONSTRUCTION | 06/21/2019 |
| BIS | EQ | ISSUED | STARR INDUSTRIES LLC | 06/21/2019 |
| BIS | OT | ISSUED | JVS RESTORATION INC | 06/04/2019 |
| BIS | OT | ISSUED | JVS RESTORATION INC | 04/25/2019 |
| BIS | OT | ISSUED | JVS RESTORATION INC | 04/18/2019 |
| BIS | OT | ISSUED | JVS RESTORATION INC | 09/26/2018 |
| BIS | OT | ISSUED | JVS RESTORATION INC | 09/14/2018 |
| BIS | SP | ISSUED | AGGRESSIVE FIRE PROT LLC | 12/13/2017 |
| BIS | PL | ISSUED | NEW YORK PLBG-HTG-COOLING | 11/01/2017 |
| BIS | OT | ISSUED | E. C. PROVINI CO., INC | 10/24/2017 |
| BIS | PL | ISSUED | MJH ENERGY CONSULTING INC | 09/20/2016 |
| BIS | MH | ISSUED | DECA DEVELOPMENT II INC | 09/07/2016 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Permit Issued | PAR FIRE PROTECTION LLC | 9 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | Permit Issued | SOLAS ELECTRICAL CORP | — |
| 12/01/2025 | Complete | ACM ELECTRIC CORPORATION | General Wiring |
| 01/21/2025 | Permit Issued | ACM ELECTRIC CORPORATION | General Wiring |
| 11/03/2024 | Complete | SRM ELECTRICAL SVC INC | — |
| 05/08/2024 | Complete | BIGMAN BROS., INC. | General Wiring |
| 05/31/2023 | Complete | ACM ELECTRIC CORPORATION | General Wiring |
| 01/17/2023 | Complete | SRM ELECTRICAL SVC INC | — |
| 06/15/2022 | Permit Issued | SRM ELECTRICAL SVC INC | General Wiring |
| 10/07/2021 | Complete | ACM ELECTRIC CORPORATION | General Wiring |
| 11/23/2020 | Complete | ATLAS-ACON ELEC. SERVICE | — |
| 11/11/2020 | Complete | ACM ELECTRIC CORPORATION | — |
| 05/14/2020 | Complete | SRM ELECTRICAL SVCS INC | General Wiring |
| 03/02/2020 | Complete | H. & L. ELECTRIC INC | General Wiring |
| 06/21/2019 | Complete | STANCO SYSTEM ELEC'L CONT | — |
| 05/19/2019 | Complete | CORP. ELEC'L TECHNOLOGIES | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | Permit Issued | BRELLA SERVICES LLC | Fence, Scaffold, Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/08/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/02/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/27/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/23/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/08/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/09/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/27/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/16/2021 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/01/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/30/2026 | Insulation placement and R values | CONNIE PISANI | energy_progress |
| 01/30/2026 | Air barrier - visual inspection | CONNIE PISANI | energy_progress |
| 01/29/2026 | Final | CONNIE PISANI | progress |
| 11/24/2025 | Post-installed Anchors | MINA HANNA | special |
| 11/24/2025 | HVAC-R and service water heating equipment | MINA HANNA | energy_progress |
| 11/24/2025 | HVAC-R and service water heating system controls | MINA HANNA | energy_progress |
| 11/24/2025 | HVAC-R and service water piping design and insulation | MINA HANNA | energy_progress |
| 11/24/2025 | Post-installed Anchors | MINA HANNA | special |
| 11/03/2025 | Final | MINA HANNA | progress |
| 11/03/2025 | Sprinkler Systems | MINA HANNA | special |
| 11/03/2025 | Mechanical Systems | MINA HANNA | special |
| 03/14/2025 | Mechanical Systems | Shahrish Shuvo | special |
| 03/14/2025 | Interior lighting power | Shahrish Shuvo | energy_progress |
| 03/14/2025 | Final | Shahrish Shuvo | progress |
| 03/14/2025 | Lighting controls | Shahrish Shuvo | energy_progress |
| 01/23/2024 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 01/23/2024 | Post-installed Anchors | Christopher Drutjons | special |
| 01/23/2024 | Final | Christopher Drutjons | progress |
| 09/01/2021 | Fire-Resistance Rated Construction | CAESAR BUSTAMANTE | progress |
| 09/01/2021 | Final | Steven O'Neil | progress |
| 08/27/2021 | Sprinkler Systems | CAESAR BUSTAMANTE | special |
| 05/29/2019 | Final | Karol Zdancewicz | progress |
| 05/29/2019 | Final | Karol Zdancewicz | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Shiseido | Retail | Floor 1 | Project Q01311871 |
| Lancome L'Oreal USA | Retail | Floor 1 | Project Q00994542 |
| Estée Lauder Companies | Retail | Floor 1 | Project Q00584438 |
| Macy's Herald Square | Retail | Floor 1 | Project Q00584551 |
| Renutriv + Spa | Other | Floor 1 | Project Q00584547 |