Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
EXTEND BOILER/HOT WATER HEATER FLUE AWAY FROM ADJACENT BUILDING. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS FILING.
On file for this project
5 documents
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 8 filings on this floor.
Bulkhead4p · 1 filing · 20 docs
ArchitectureStructural
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 16TH FLOOR (17TH FLOOR MARKETING) AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
40 documents · 4 drawing sheets
Floor 178p · 7 filings · 20 docs
Fire ProtectionMechanicalPlumbing
MECHANICAL MODIFICATIONS TAKING PLACE ON THE 16TH FLOOR (17TH FLOOR MARKETING) AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 16TH FLOOR (17TH FLOOR MARKETING) AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
PLUMBING MODIFICATIONS TAKING PLACE ON THE 16TH FLOOR (17TH FLOOR MARKETING) AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 16Under Construction23p · 7 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Sprinklers
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
SUBSEQUENT APPLICATION FILED FOR SPRINKLER MODIFICATIONS/ADDITIONS ON THE 16TH FLOOR AS PER PLANS FILED HERE WITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
9 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 15Under Construction3p · 2 filings · 7 docs
Mechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
Floor 14Under Construction7p · 3 filings · 10 docs
ArchitectureGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
FILED HEREWITH FOR INTERIOR REMOVAL OF NON-LOAD BEARING WALLS ON THE 14TH FLOOR TO CREATE WHITE BOX AS PER PLAN, NO CHANGE TO USE EGRESS OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
Floor 13Under Construction3p · 2 filings · 7 docs
Mechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
Floor 12Under Construction3p · 2 filings · 7 docs
Mechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
Floor 11Under Construction6p · 3 filings · 10 docs
ArchitectureDMMechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
INTERIOR RENOVATION AT 11TH FLOOR OFFICE SPACE AS PER PLANS FILED HEREWITH
On file for this project
3 documents · 3 drawing sheets
Floor 10Under Construction8p · 3 filings · 11 docs
ArchitectureDMGeneralMechanicalOther
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 10TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 5 drawing sheets
Floor 9Under Construction3p · 2 filings · 7 docs
Mechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
Floor 8Under Construction3p · 2 filings · 7 docs
Mechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
Floor 7Under Construction6p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 7TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 6Under Construction6p · 3 filings · 10 docs
ArchitectureGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
FILED HEREWITH FOR INTERIOR REMOVAL OF NON-LOAD BEARING WALLS ON THE 6TH FLOOR TO CREATE WHITE BOX AS PER PLAN, NO CHANGE TO USE EGRESS OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
Floor 5Under Construction13p · 7 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 5TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 4Under Construction18p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
STRUCTURAL WORK FILED IN CONJUNCTION WITH APPLICATION # M01260479-I1
On file for this project
40 documents · 9 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 3Under Construction11p · 3 filings · 20 docs
ArchitectureDMMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
STRUCTURAL WORK FILED IN CONJUNCTION WITH APPLICATION # M01260479-I1
On file for this project
40 documents · 7 drawing sheets
Floor 2Under Construction13p · 4 filings · 20 docs
ArchitectureDMMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY BETAMAX MATERIAL HOIST PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
On file for this project
3 documents
STRUCTURAL WORK FILED IN CONJUNCTION WITH APPLICATION # M01260479-I1
On file for this project
40 documents · 9 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 1Under Construction21p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods
FILING FOR THREE NEW COMMERCIAL DUCTWORKS IN THE BUILDING, THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents · 1 drawing sheet
PROPOSED MODIFICATION OF EXISTING SPRINKLER SYSTEM TO INCLUDE RELOCATION, ADDITION AND REMOVAL OF SPRINKLER HEADS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
9 documents · 6 drawing sheets
FILED HEREWITH TO REMOVE PLUMBING FIXTURES AS PER PLANS.
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
MezzanineUnder Construction5p · 2 filings · 16 docs
ArchitectureFire Protection
Issued Permit Scope
General Construction
PROPOSED MODIFICATION OF EXISTING SPRINKLER SYSTEM TO INCLUDE RELOCATION, ADDITION AND REMOVAL OF SPRINKLER HEADS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
9 documents · 2 drawing sheets
FILED HEREWITH TO REMOVE PLUMBING FIXTURES AS PER PLANS.
On file for this project
7 documents
CellarUnder Construction11p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems
EXTEND BOILER/HOT WATER HEATER FLUE AWAY FROM ADJACENT BUILDING. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS FILING.
On file for this project
5 documents · 1 drawing sheet
PROPOSED MODIFICATION OF EXISTING SPRINKLER SYSTEM TO INCLUDE RELOCATION, ADDITION AND REMOVAL OF SPRINKLER HEADS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
9 documents · 5 drawing sheets
FILED HEREWITH TO REMOVE PLUMBING FIXTURES AS PER PLANS.
On file for this project