RoofUnder Construction15p · 14 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructuralSC
Issued Permit Scope
Antenna · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods
Modification to T-Mobile site - Replace 3 antennas on the roof. Install 3 RRU on the roof.
On file for this project
3 documents · 1 drawing sheet
PROPOSED FACADE REPAIRS AS PER PLANS SUBMITTED HEREWITH. THERE IS NO CHANGE IN USE, ERGREE OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
The scope of work for this project consist of extending dunnage to accommodate additional HVAC Equipment (filed under DOBNOW applications M01319621, M01319622,M01319603,M01319619). No change in use egress or occupancy.
On file for this project
11 documents · 2 drawing sheets
Latest 3 of 14 filings on this floor.
Floor 191p · 1 filing · 3 docs
Architecture
The scope of this application consists of the removal of the finishes in the bathrooms, the relocation of plumbing fixtures, and the installation of new finishes. No change of use, egress, or occupancy
On file for this project
3 documents · 1 drawing sheet
Floor 18Under Construction7p · 9 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe
Mechanical modifications at subject premises. No change of use egress or occupancy.
On file for this project
13 documents · 2 drawing sheets
The scope of this application consists of the removal of the finishes in the bathrooms, the relocation of plumbing fixtures, and the installation of new finishes. No change of use, egress, or occupancy
On file for this project
3 documents
Herewith filing Plumbing Work at 17th and 18th Floor in conjunction with Interior renovations.
On file for this project
11 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 176p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe
Herewith filing Plumbing Work at 17th and 18th Floor in conjunction with Interior renovations.
On file for this project
11 documents · 1 drawing sheet
Herewith Filing Modifications to Existing Sprinkler & Standpipe System. Work includes the rerouting of standpipe and sprinkler piping at the 17th & 18th Floors and installation of new sprinkler heads at the 18th Floor as per plans.
On file for this project
14 documents · 2 drawing sheets
Herewith Filing Interior Buildout at 17th and 18th Floors as per plans.
On file for this project
17 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 16Under Construction1 filing · 13 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications at subject premises. No change of use egress or occupancy.
On file for this project
13 documents
Floor 15Under Construction1 filing · 3 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
3 documents
Floor 14Under Construction2 filings · 15 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications (PHASE 4) -1 Hotel Central Park). No change of use egress or occupancy.
On file for this project
12 documents
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
3 documents
Floor 13Under Construction1 filing · 12 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications (PHASE 4) -1 Hotel Central Park). No change of use egress or occupancy.
On file for this project
12 documents
Floor 12Under Construction1p · 2 filings · 15 docs
DMFire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications (PHASE 4) -1 Hotel Central Park). No change of use egress or occupancy.
On file for this project
12 documents · 1 drawing sheet
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
3 documents
Floor 11Under Construction2 filings · 20 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications at subject premises. No change of use egress or occupancy.
On file for this project
13 documents
Mechanical modifications (PHASE 4) -1 Hotel Central Park). No change of use egress or occupancy.
On file for this project
12 documents
Floor 10Under Construction2 filings · 20 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications at subject premises. No change of use egress or occupancy.
On file for this project
13 documents
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
22 documents
Floor 9Under Construction2 filings · 20 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications at subject premises. No change of use egress or occupancy.
On file for this project
13 documents
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
22 documents
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4Under Construction1 filing · 20 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
22 documents
Floor 3Under Construction2p · 2 filings · 20 docs
Fire ProtectionMechanicalStructural
Issued Permit Scope
Mechanical Systems · Sprinklers · Structural
The scope of work for this project consist of extending dunnage to accommodate additional HVAC Equipment (filed under DOBNOW applications M01319621, M01319622,M01319603,M01319619). No change in use egress or occupancy.
On file for this project
11 documents
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
22 documents · 2 drawing sheets
Floor 2Under Construction2p · 1 filing · 3 docs
MechanicalStructural
Issued Permit Scope
Mechanical Systems
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
3 documents · 2 drawing sheets
Floor 1Under Construction6p · 6 filings · 20 docs
ArchitectureDMElectricalEquipmentGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Supported Scaffold
MODIFY EXISTING COMMERCIAL COOKING EQUIPMENTS AND PIPING AT 001, AS PER PLANS, NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
3 documents · 2 drawing sheets
Mechanical modifications at subject location. No change in use egress or occupancy,
On file for this project
22 documents · 1 drawing sheet
INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2014 CHAPTER 33 . NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 6 filings on this floor.
CellarUnder Construction4p · 3 filings · 18 docs
MechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing
MODIFY EXISTING COMMERCIAL COOKING EQUIPMENTS AND PIPING AT 001, AS PER PLANS, NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
3 documents · 2 drawing sheets
Mechanical modifications (PHASE 4) -1 Hotel Central Park). No change of use egress or occupancy.
On file for this project
12 documents · 2 drawing sheets
Filing Plumbing in relation to bar renovation and new barista station as shown on drawings as submitted herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Site & exteriorUnder Construction5 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Sidewalk Shed · Supported Scaffold
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS AND MATERIAL STORAGE. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 11 drawing sheets
PROPOSED FACADE REPAIRS AS PER PLANS SUBMITTED HEREWITH. THERE IS NO CHANGE IN USE, ERGREE OR OCCUPANCY.
On file for this project
3 documents · 6 drawing sheets
INSTALLATION OF 300 PSF SIDEWALK SHED AND OVERHEAD PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 3 drawing sheets
Latest 3 of 5 filings on this floor.
Filed — no permit issued4 filings · 20 docs
ArchitectureGeneralPlumbingStructuralSC
No filed description on record for this project.
On file for this project
2 documents · 4 drawing sheets
No filed description on record for this project.
On file for this project
7 documents · 2 drawing sheets
No filed description on record for this project.
On file for this project
3 documents · 6 drawing sheets
Latest 3 of 4 filings on this floor.