Limited service hotel, often national chain
144-02 135TH AVENUE
QUEENS · Baisley Park · BIN 4624981
💬 Discuss this project
1987Year Built
12Stories
H3Building Class
C4-2Zoning
197,532 sfGross Floor Area
1Units
LL97 CoveredRent Stabilized10 Open Violations 9 unresolved · 1 paperwork only ▸FISP: SAFEFDNY Report ↗
Limited service hotel, often national chain · Owner of record: RB 135TH AVENUE HOUSING DEVELOPMENT FUND CORP · 61,615 sf lot · 3.21 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction7p · 7 filings · 20 docs
Floor 14Under Construction1 filing · 5 docs
Floor 13Under Construction1 filing · 5 docs
Floor 12Under Construction2p · 2 filings · 13 docs
Floor 11Under Construction1 filing · 5 docs
Floor 10Under Construction2p · 2 filings · 13 docs
Floor 9Under Construction1 filing · 5 docs
Floor 8Under Construction1 filing · 5 docs
Floor 7Under Construction1 filing · 5 docs
Floor 6Under Construction1 filing · 5 docs
Floor 5Under Construction1 filing · 5 docs
Floor 4Under Construction1 filing · 5 docs
Floor 3Under Construction1p · 2 filings · 13 docs
Floor 2Under Construction23p · 3 filings · 20 docs
Floor 1Under Construction20p · 4 filings · 20 docs
CellarUnder Construction28p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RISEBORO COMMUNITY PARTNERSHIP7309/12/2026
JFK HOTEL PARTNERS2807/08/2026
UNIVERSAL SYSTEMS807/08/2026
ALBA SERVICES INC503/22/2026
T-MOBILE303/22/2026
RB 135TH AVENUE HOUSING DEVELOPM103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/14/2023$64.0M—JFK HOTEL PARTNERS LLC → RB 135TH AVENUE OWNER LLC$324/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.4203/21/2026
ECC603/21/2026
GENE KAUFMAN ARCHITECT903/21/2026
A1 EXPEDITING SERVICE CORP.203/21/2026
CCM CONSULTING GROUP, INC.103/21/2026
EUROCELT EXPEDITING, INC403/21/2026
CONSTRUCTION PERMIT SERVICES203/21/2026
KD DESIGNS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SD BUILDERS AND CONSTRUCTGeneral Contractor1304/09/2026
ZAPAS CONSTRUCTION CORPPlumbing607/08/2026
E.M.P. FIRE SPRINKLER LLCFire Protection607/08/2026
SPARTAN DEMOLITION CO LLCGeneral Contractor507/08/2026
UNIVERSAL SYSTEMS INCGeneral Contractor407/08/2026
WATCH HILL WIRELESS SOLUGeneral Contractor303/21/2026
NORTHEAST PLBG & HTG CORPPlumbing207/08/2026
STREAM PLUMBING INCPlumbing207/08/2026
VOLK INDUSTRIAL SERVICESGeneral Contractor104/09/2026
A & M WARSHAW PLBG & HTGPlumbing107/08/2026
G.P. MECHANICAL CORPPlumbing107/08/2026
RAMAPO COMMUNICATION CORPGeneral Contractor104/09/2026
A&M WARSHAW SERVICES LLCFire Protection107/08/2026
STONEHILL CONSTR SERV INCGeneral Contractor104/09/2026
AMERICAN STANDARD PLUMBING &Fire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GEODESIGN, INC., P.C.627311/10/2025
MACIA INSPECTION & TESTIN402511/10/2025
CROSSCHECK INSPECTION SER5442508/04/2025
SOUTH BAY ENGINEERING PLL6682203/15/2024
GRANT ENGINEERING CONSULT3512110/06/2022
Building Lifecycle
All (283)Filed (51)Permit Issued (40)Signed Off (19)Facade (FISP) (6)Violation (60)Inspection (51)Objection (26)Special Inspection (30)
05/26/2026
Signed off — Alteration
Renovation of community facility on the 1st floor. no change in use, egress, or occupancy.
Q01179140-S3
05/05/2026
Violation issued (ECB, open)
Construction
05/05/2026
Violation issued (ECB, open)
Construction
05/05/2026
Violation issued (ECB, open)
Unknown
03/16/2026
Filed — Alteration
Renovation of community facility on the 1st floor. no change in use, egress, or occupancy.
Q01179140-P2
02/26/2026
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S5
02/11/2026
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S8
02/11/2026
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S9
02/11/2026
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S4
02/09/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/13/2026
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
01/07/2026
Filed — Alteration
Renovation of community facility on the 1st floor. no change in use, egress, or occupancy.
Q01179140-P1
12/22/2025
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
12/12/2025
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S7
12/12/2025
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S6
12/12/2025
Signed off — Alteration
Renovation of community facility on the 1st floor. no change in use, egress, or occupancy.
Q01179140-I1
12/12/2025
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S3
12/12/2025
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S2
12/03/2025
Signed off — Alteration
PARTIAL DEMOLITION OF 1 STORY CONCRETE & STEEL FRAME BUILDING.
Q00858276-I1
12/03/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/02/2025
Signed off — Alteration
Q00858293-I1
12/01/2025
Permit issued — Mechanical Systems
Q01179140-S2-MS
11/24/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/19/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/19/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/14/2025
Permit issued — Plumbing
Q00494984-I1-PL
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/10/2025
Filed — Alteration
HEREBY FILING FOR UNDERGROUND EXTERIOR PLUMBING WORK, DENTENTION /RETENTION FACILITIES.
Q01063038-P2
11/07/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/05/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Jeffrey Stones
11/05/2025
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
THOMAS THOMANN
10/22/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/06/2025
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-I1
09/22/2025
Signed off — Alteration
Proposed interior demolition of existing non-structural interior partitions of existing hotel building as per plan. No change of use, egress and occupancy. Proposed plans provided on Alt CO #421134276.
Q00965620-I1
09/15/2025
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
09/03/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/18/2025
Signed off — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-S1
08/14/2025
Special inspection requirement — Subgrade Inspections
EUGENE BIFULCO
08/14/2025
Special inspection requirement — Final
EUGENE BIFULCO
08/14/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
EUGENE BIFULCO
08/14/2025
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
EUGENE BIFULCO
08/14/2025
Special inspection requirement — Concrete - Cast-In-Place
EUGENE BIFULCO
08/14/2025
Special inspection requirement — Post-installed Anchors
EUGENE BIFULCO
08/14/2025
Special inspection requirement — Footing and Foundation
EUGENE BIFULCO
08/12/2025
Special inspection requirement — Shutoff dampers
EUGENE BIFULCO
08/12/2025
Special inspection requirement — Mechanical Systems
EUGENE BIFULCO
08/12/2025
Special inspection requirement — Heating Systems
EUGENE BIFULCO
08/12/2025
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
08/12/2025
Special inspection requirement — HVAC-R and service water heating equipment
EUGENE BIFULCO
08/12/2025
Special inspection requirement — Maintenance information
EUGENE BIFULCO
08/12/2025
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
08/12/2025
Special inspection requirement — Final
EUGENE BIFULCO
08/12/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
EUGENE BIFULCO
08/04/2025
Filed — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-A5
08/01/2025
Permit issued — Sprinklers
Q01179140-S3-EW-SP
08/01/2025
Permit issued — Plumbing
Q01179140-S1-PL
07/30/2025
Filed — Alteration
SP/SD work for floors 9-12 as per plans filed.
Q00914318-A4
07/30/2025
Special inspection requirement — Sprinkler Systems
EUGENE BIFULCO
07/30/2025
Special inspection requirement — Standpipe Systems
EUGENE BIFULCO
Latest 60 of 283 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offSD BUILDERS AND CONSTRUCT12/01/2025
DOB NOWPlumbingPermit IssuedSTREAM PLUMBING INC11/14/2025
DOB NOWSprinklersSigned-offZAPAS CONSTRUCTION CORP08/01/2025
DOB NOWPlumbingPermit IssuedZAPAS CONSTRUCTION CORP08/01/2025
DOB NOWGeneral ConstructionSigned-offSD BUILDERS AND CONSTRUCT05/29/2025
DOB NOWStandpipeSigned-offE.M.P. FIRE SPRINKLER LLC04/02/2025
DOB NOWSprinklersSigned-offE.M.P. FIRE SPRINKLER LLC04/02/2025
DOB NOWFoundationPermit IssuedSD BUILDERS AND CONSTRUCT03/05/2025
DOB NOWConstruction FenceSigned-offSD BUILDERS AND CONSTRUCT01/23/2025
DOB NOWSupport of ExcavationSigned-offSD BUILDERS AND CONSTRUCT01/21/2025
DOB NOWMechanical SystemsSigned-offSD BUILDERS AND CONSTRUCT01/16/2025
DOB NOWStandpipeSigned-offZAPAS CONSTRUCTION CORP12/20/2024
DOB NOWPlumbingSigned-offNORTHEAST PLBG & HTG CORP12/16/2024
DOB NOWPlumbingPermit IssuedSTREAM PLUMBING INC11/27/2024
DOB NOWStandpipeSigned-offE.M.P. FIRE SPRINKLER LLC10/11/2024
DOB NOWSprinklersSigned-offE.M.P. FIRE SPRINKLER LLC10/11/2024
DOB NOWCurb CutPermit IssuedSTONEHILL CONSTR SERV INC09/23/2024
DOB NOWPlumbingSigned-offNORTHEAST PLBG & HTG CORP08/07/2024
DOB NOWSprinklersSigned-offA&M WARSHAW SERVICES LLC06/21/2024
DOB NOWSprinklersSigned-offAMERICAN STANDARD PLUMBIN05/17/2024
DOB NOWPlumbingSigned-offZAPAS CONSTRUCTION CORP05/09/2024
DOB NOWPlumbingSigned-offG.P. MECHANICAL CORP04/18/2024
DOB NOWPlumbingSigned-offA & M WARSHAW PLBG & HTG04/16/2024
DOB NOWGeneral ConstructionSigned-offVOLK INDUSTRIAL SERVICES03/14/2024
DOB NOWStandpipeSigned-offE.M.P. FIRE SPRINKLER LLC03/07/2024
DOB NOWSprinklersSigned-offE.M.P. FIRE SPRINKLER LLC03/07/2024
DOB NOWFoundationPermit IssuedSD BUILDERS AND CONSTRUCT03/04/2024
DOB NOWStructuralSigned-offSD BUILDERS AND CONSTRUCT03/04/2024
DOB NOWPlumbingSigned-offZAPAS CONSTRUCTION CORP01/19/2024
DOB NOWStandpipeSigned-offZAPAS CONSTRUCTION CORP01/19/2024
DOB NOWConstruction FenceSigned-offSD BUILDERS AND CONSTRUCT01/12/2024
DOB NOWMechanical SystemsSigned-offSD BUILDERS AND CONSTRUCT01/11/2024
DOB NOWGeneral ConstructionSigned-offSD BUILDERS AND CONSTRUCT11/30/2023
DOB NOWProtection and Mechanical MethodsPermit IssuedUNIVERSAL SYSTEMS INC08/22/2023
DOB NOWSidewalk ShedPermit IssuedUNIVERSAL SYSTEMS INC08/21/2023
DOB NOWGeneral ConstructionSigned-offSPARTAN DEMOLITION CO LLC06/27/2023
DOB NOWProtection and Mechanical MethodsSigned-offSPARTAN DEMOLITION CO LLC06/23/2023
DOB NOWConstruction FencePermit IssuedSPARTAN DEMOLITION CO LLC06/15/2023
DOB NOWAntennaPermit IssuedWATCH HILL WIRELESS SOLU10/28/2022
DOB NOWAntennaSigned-offRAMAPO COMMUNICATION CORP06/23/2022
+ 12 more permits on file
1 project · most recent 03/16/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
03/16/2026Signed-offSD BUILDERS AND CONSTRUCTHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Carrier 48FCEM12A3A5A0A0A0 127,900 BTU · Rooftop Unit ×2
Ventilation
Greenheck CUBE-240HP-30 5,130 CFM · Exhaust Fan ×1
CUBE-300HP-50 5,900 CFM · Exhaust Fan ×1
CUE-160XP-VG 800 CFM · Exhaust Fan ×1
Aaon RNA-011-B-A-8 4,720 BTU · Rooftop Unit ×2
1 project · most recent 03/16/2026
Sprinkler System
FiledStatusContractorScope
03/16/2026——Sprinkler System
3 projects · most recent 03/16/2026
Water/Sanitary Gas Storm
FiledStatusContractorScope
03/16/2026Permit IssuedZAPAS CONSTRUCTION CORPGas, Water/Sanitary
11/10/2025Signed-offNORTHEAST WATER&SEWER CORStorm, Water/Sanitary
12/12/2024Signed-offNORTHEAST WATER&SEWER CORWater/Sanitary
5 projects · most recent 08/08/2025
General Wiring
FiledStatusContractorScope
08/08/2025Permit IssuedEQUAL ELECTRICAL CONT INCGeneral Wiring
03/10/2025Permit IssuedEQUAL ELECTRICAL CONT INCGeneral Wiring
03/10/2025CompleteEQUAL ELECTRICAL CONT INCGeneral Wiring
03/10/2025Permit IssuedEQUAL ELECTRICAL CONT INCGeneral Wiring
03/25/2024CompleteAPPROVED ELECTRIC CORP.General Wiring
2 projects · most recent 08/18/2023
Sidewalk Shed Fence
FiledStatusContractorScope
08/18/2023Permit IssuedUNIVERSAL SYSTEMS INCSidewalk Shed
05/04/2023Permit IssuedSPARTAN DEMOLITION CO LLCFence
▾Field Inspections (DOB CAP) — 51
DateTypeResultReport
02/09/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/13/2026Pass-Final SP - Up to 9 Requested FloorsPassView ↗
12/22/2025Pass-Final PL - More than 10 Requested FloorsPassView ↗
12/03/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/24/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/19/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/19/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/07/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/22/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/15/2025Pass-Final SP - Up to 3 Requested FloorsPassView ↗
09/03/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
05/02/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/01/2025Pass-Final PL - UndergroundPassView ↗
04/18/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
04/15/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/15/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
04/09/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/09/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
04/04/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
04/03/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/03/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/27/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
03/27/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
03/25/2025Certified StandPipe-Fire Pump (SD)-Fire Pump TestCertifiedView ↗
03/20/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
Latest 25 of 51.
▾Special Inspection Requirements (DOB NOW) — 84
DateRequirementInspectorRole
11/05/2025Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesTHOMAS THOMANNspecial
11/05/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJeffrey Stonesspecial
08/14/2025Subsurface Conditions – Fill Placement & In-Place DensityEUGENE BIFULCOspecial
08/14/2025FinalEUGENE BIFULCOprogress
08/14/2025Footing and FoundationEUGENE BIFULCOprogress
08/14/2025Post-installed AnchorsEUGENE BIFULCOspecial
08/14/2025Concrete - Cast-In-PlaceEUGENE BIFULCOspecial
08/14/2025Subgrade InspectionsEUGENE BIFULCOspecial
08/14/2025Structural Stability – Alterations of existing buildingsEUGENE BIFULCOspecial
08/12/2025Energy Code Compliance InspectionsEUGENE BIFULCOprogress
08/12/2025Mechanical SystemsEUGENE BIFULCOspecial
08/12/2025Heating SystemsEUGENE BIFULCOspecial
08/12/2025HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
08/12/2025Maintenance informationEUGENE BIFULCOenergy_progress
08/12/2025Shutoff dampersEUGENE BIFULCOenergy_progress
08/12/2025HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
08/12/2025HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
08/12/2025FinalEUGENE BIFULCOprogress
07/30/2025Sprinkler SystemsEUGENE BIFULCOspecial
07/30/2025Standpipe SystemsEUGENE BIFULCOspecial
07/28/2025FinalEUGENE BIFULCOprogress
07/28/2025Footing and FoundationEUGENE BIFULCOprogress
07/28/2025Concrete - Cast-In-PlaceEUGENE BIFULCOspecial
07/28/2025Post-installed AnchorsEUGENE BIFULCOspecial
07/28/2025Subgrade InspectionsEUGENE BIFULCOspecial
Latest 25 of 84.
▾Documents — 388 on file (BIS + DOB NOW)
▸Plans & Drawings51
▸DOB NOWPlans/Sketch51
08/26/2026Q00583910-I1Request digital key ↗
08/24/2026Q00858293-I1Request digital key ↗
08/24/2026Q00860078-I1Request digital key ↗
Showing 3 of 51 on file for this type
▸Applications & Permits56
▸BISPLAN / WORK APPROVAL APPLICATION43
09/02/2025421134276Open ↗
08/28/2025421134276Open ↗
08/20/2025421839434Open ↗
Showing 3 of 43 on file for this type
▸BISWORK PERMIT APPLICATION11
06/27/2025421134276Open ↗
06/24/2015420910152Open ↗
08/07/2012420331974Open ↗
Showing 3 of 11 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
09/25/2024421134276Open ↗
12/13/2014420910152Open ↗
▸Zoning, Tax Lot & Property Records11
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED3
01/05/2024421839434Open ↗
10/06/2023421134276Open ↗
07/17/2023421790119Open ↗
▸BISZONING DIAGRAM3
11/03/2023421134276Open ↗
11/02/2023421134276Open ↗
01/11/2022421788694Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
03/25/2025421134276Open ↗
▸BISZONING EXHIBIT I- CERTIFICATION1
06/27/2014420910152Open ↗
▸BISZONING EXHIBIT III- DESC & OWNERSHIP STMNT1
06/27/2014420910152Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
06/09/2021421788685Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
12/02/2015420910152Open ↗
▸Seals & Professional Certifications120
▸DOB NOWDPL-1: Design Professional Seal & Signature49
08/26/2026Q00583910-I1Open ↗
08/25/2026Q08010957-I1Open ↗
08/24/2026Q00858293-I1Open ↗
Showing 3 of 49 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature29
09/23/2026Q00914318-S5Open ↗
09/23/2026Q00914318-A5Open ↗
09/02/2026Q00914318-P6Open ↗
Showing 3 of 29 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION19
07/17/2025421134276Open ↗
07/22/2016420910152Open ↗
11/28/2015420910152Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/05/2026Q00965620-P1Open ↗
09/02/2026Q00495187-I1Open ↗
09/01/2026Q00914318-I1Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
01/11/2022421788694Open ↗
06/05/2014420910152Open ↗
10/26/2013420910152Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
04/15/2021440670034Open ↗
10/25/2013420910152Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/05/2014420910152Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
04/15/2021440670034Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/15/2021440670034Open ↗
▸Trade Schedules & Equipment18
▸BISSELF-CERT PLUMBING NOTICE14
12/12/2012420331974Open ↗
11/17/2012420331974Open ↗
10/04/2012420331974Open ↗
Showing 3 of 14 on file for this type
▸BISSCHEDULE B - PLUMBING2
06/21/2011420370164Open ↗
Showing 1 of 2 on file for this type
▸BISSEWER CONNECTION: DEP SD1 & SD21
10/06/2014420910152Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
10/22/2024421134276Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST3
10/25/2023421134276Open ↗
06/08/2021421788694Open ↗
10/26/2013420910152Open ↗
▸BISSTREET TREES SITE PLAN2
09/19/2025421134276Open ↗
12/04/2024421134276Open ↗
▸BISST-1 Street Tree Checklist1
06/05/2014420910152Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
12/18/2024421134276Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/26/2026Q00583910-I1Open ↗
08/23/2026Q00965620-I1Open ↗
08/20/2026Q01179140-S3Open ↗
Showing 3 of 10 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
06/21/2011420370164Open ↗
Showing 1 of 2 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
11/02/2023421134276Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026Q00858276-I1Open ↗
▸Energy Compliance24
▸DOB NOWPreliminary Commissioning Report Certification4
08/13/2026Q00914318-S7Open ↗
08/13/2026Q00914318-S6Open ↗
08/13/2026Q00914318-S3Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
07/17/2025421134276Open ↗
10/03/2014420910152Open ↗
10/26/2013420910152Open ↗
▸BISTECHNICAL REPORT: ENERGY3
06/21/2011420370164Open ↗
04/05/2011420331974Open ↗
03/16/2011420331974Open ↗
▸BISTR8: Energy Code Progress Inspections2
06/05/2014420910152Open ↗
07/22/2011420370164Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
03/25/2025421134276Open ↗
▸BISLIGHTING IN DWELLING UNITS1
03/25/2025421134276Open ↗
▸BISELECTRIC MOTORS1
03/25/2025421134276Open ↗
▸BISLIGHTING CONTROLS1
03/25/2025421134276Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
03/25/2025421134276Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/10/2025421134276Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
03/25/2025421134276Open ↗
▸BISEXTERIOR LIGHTING POWER1
03/25/2025421134276Open ↗
▸BISINTERIOR LIGHTING POWER1
03/25/2025421134276Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
08/06/2015420910152Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
03/25/2025421134276Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
10/23/2023421134276Open ↗
▸Inspections & Test Reports4
▸BISSPRAYED FIRE-RESISTANT MATERIALS1
03/25/2025421134276Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
10/23/2023421134276Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
10/09/2014420910152Open ↗
▸BISTECHNICAL REPORT: CONCRETE-TEST CYLINDER1
10/09/2014420910152Open ↗
▸Approvals, Objections & Sign-offs34
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter21
08/20/2026Q01179140-P2Open ↗
08/20/2026Q01179140-S3Open ↗
08/20/2026Q01179140-P1Open ↗
Showing 3 of 21 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE7
06/04/2025421134276Open ↗
11/14/2024421134276Open ↗
11/13/2024421134276Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
01/03/2024421839434Open ↗
04/15/2021440670034Open ↗
08/20/2015420910152Open ↗
▸BISADMINISTRATIVE OBJECTIONS3
10/25/2013420910152Open ↗
06/21/2011420370164Open ↗
Showing 2 of 3 on file for this type
▸Cost, Insurance & Ownership14
▸BISCOST AFFIDAVIT11
06/09/2021421788694Open ↗
04/15/2021440670034Open ↗
11/28/2015420910152Open ↗
Showing 3 of 11 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)3
01/05/2024421839434Open ↗
10/25/2023421134276Open ↗
01/11/2022421788694Open ↗
▸Filing & Intake Forms29
▸BISEFILING COVER SHEET12
01/03/2024421839434Open ↗
07/07/2021421790119Open ↗
06/09/2021421788694Open ↗
Showing 3 of 12 on file for this type
▸BISADDITIONAL INFORMATION9
12/18/2024421134276Open ↗
06/30/2023440670034Open ↗
01/11/2022421788694Open ↗
Showing 3 of 9 on file for this type
▸BISBOROUGH INTAKE FORM7
07/03/2025421134276Open ↗
07/07/2021421790119Open ↗
06/09/2021421788694Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
04/15/2021440670034Open ↗
▸Other Documents5
▸BISPLOT DIAGRAM2
12/02/2015420910152Open ↗
10/26/2013420910152Open ↗
▸BISVESTIBULES1
03/25/2025421134276Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
07/27/2023421790119Open ↗
▸BISPERMANENT CERTIFICATE1
03/25/2025421134276Open ↗