| Owner | Filings | Most Recent |
|---|---|---|
| JONATHAN ROSE COMPANIES | 17 | 09/13/2026 |
| 181 MONTAGUE | 13 | 07/08/2026 |
| MONTAGUE PIERREPONT OWNER LLC | 67 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/15/2015 | $5.8M | — | WARREN 325 LLC → MONTAGUE PIERREPONT APARTMENTS LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| LEON SKVIRSKY PE | 1 | 03/20/2026 |
| DAVID CHAGNON ARCHITECTURAL DESIGN | 5 | 01/19/2026 |
| NTA DESIGN GROUP, LLC | 1 | 10/05/2023 |
| NEW YORK ENGINEERS LLC | 1 | 01/11/2022 |
| PAPER PLANE ARCHITECTURE, PLLC | 1 | 11/02/2021 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 04/27/2021 |
| KEVIN GALLEN PE LLC | 6 | 01/13/2021 |
| MURDOCH ENGINEERING | 3 | 06/05/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| TSOLAKI'S EXPEDITING | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| WILLIAM VITTACO ASSOCIATES | 6 | 03/21/2026 |
| KAZAM CONSULTANTS | 6 | 03/21/2026 |
| EA DESIGN GROUP | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 5 | 07/08/2026 |
| TA & MT CONSTRUCTION INC | General Contractor | 4 | 04/09/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 3 | 07/08/2026 |
| SIGNA HVAC SYSTEMS INS | General Contractor | 3 | 03/21/2026 |
| BALATON CONSULTING LLC | Scaffold | 3 | 07/08/2026 |
| TEC PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| DONATO, INC | Plumbing | 1 | 07/08/2026 |
| JUST PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| WILLIAM F VENTURA P&H INC | Plumbing | 1 | 03/22/2026 |
| ELECTRIC ESSENTIALS CORP | Electrical | 1 | 03/22/2026 |
| PAUL SIGNS | Scaffold | 1 | 07/08/2026 |
| CURRENT FIRE PROTECTION INC | Fire Protection | 1 | 07/08/2026 |
| DEPENDABLE MECHANICAL COR | Fire Protection | 1 | 06/28/2026 |
| RIGHTWAY PLBG & HTG INC | Fire Protection | 1 | 07/08/2026 |
| INTERIOR BUILDING SERVICE | General Contractor | 1 | 07/08/2026 |
| RARE BREED RESTORATION IN | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MCDONOUGH ENGINEERING PRA | 9377 | 5 | 01/19/2026 |
| PAPER PLANE ARCHITECTURE, | 7155 | 3 | 01/11/2022 |
| DOMANI INSPECTION SERVICE | 843 | 7 | 01/13/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | STRUCTURAL PRESERVATION S | 07/09/2026 |
| DOB NOW | Sign | Permit Issued | PAUL SIGNS, INC | 03/27/2026 |
| DOB NOW | Sprinklers | Signed-off | DEPENDABLE MECHANICAL COR | 12/30/2025 |
| DOB NOW | Plumbing | Signed-off | A&H EXPRESS PLBG&HTG CORP | 12/08/2025 |
| DOB NOW | Mechanical Systems | Signed-off | TA & MT CONSTRUCTION INC | 11/25/2025 |
| DOB NOW | General Construction | Permit Issued | TA & MT CONSTRUCTION INC | 10/29/2025 |
| DOB NOW | General Construction | Permit Issued | RARE BREED RESTORATION IN | 12/14/2023 |
| DOB NOW | General Construction | Signed-off | INTERIOR BUILDING SERVICE | 10/20/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 09/09/2022 |
| DOB NOW | Plumbing | Signed-off | MOHAMED ABDELRAZEK | 02/23/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 04/28/2021 |
| DOB NOW | Mechanical Systems | Signed-off | SIGNA HVAC SYSTEMS INC | 03/07/2021 |
| DOB NOW | Sprinklers | Signed-off | RIGHTWAY PLBG & HTG INC | 01/27/2021 |
| DOB NOW | Plumbing | Signed-off | TEC PLUMBING CORP | 01/22/2021 |
| DOB NOW | Plumbing | Signed-off | TEC PLUMBING CORP | 12/21/2020 |
| DOB NOW | Sprinklers | Signed-off | CURRENT FIRE PROTECTION I | 06/03/2020 |
| DOB NOW | Plumbing | Signed-off | DONATO, INC | 02/04/2020 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 07/23/2019 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 07/18/2019 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 07/18/2019 |
| BIS | OT | ISSUED | DBD CONTRACTING LLC | 11/30/2020 |
| BIS | OT | ISSUED | LEEDING BUILDERS GROUP LL | 03/30/2020 |
| BIS | EQ | ISSUED | STRUCTURETECH NEW YORK IN | 01/22/2020 |
| BIS | OT | ISSUED | LEEDING BUILDERS GROUP LL | 01/03/2020 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 09/25/2019 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 09/25/2019 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 09/25/2019 |
| BIS | EQ | ISSUED | CONSIGLI & ASSOCIATES LLC | 07/15/2019 |
| BIS | PL | ISSUED | TRISTATE PLBG SVCS CORP | 05/30/2019 |
| BIS | SP | ISSUED | SIRINA FIRE PROT CORP | 04/15/2019 |
| BIS | OT | ISSUED | VERICON CONSTRUCTION CO | 04/04/2019 |
| BIS | MH | ISSUED | VERICON CONSTRUCTION CO | 04/04/2019 |
| BIS | OT | ISSUED | VERICON CONSTRUCTION CO | 04/04/2019 |
| BIS | PL | ISSUED | DEMAR PLUMBING CORP | 03/05/2019 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 02/14/2019 |
| BIS | — | ISSUED | CONSIGLI & ASSOCIATES LLC | 02/05/2019 |
| BIS | — | ISSUED | CONSIGLI & ASSOCIATES LLC | 12/29/2018 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 12/05/2018 |
| BIS | SD | ISSUED | DEMAR PLUMBING CORP | 11/05/2018 |
| BIS | EQ | ISSUED | STRUCTURETECH NEW YORK IN | 10/24/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/11/2022 | Signed-off | 2M MECHANICAL LLC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/18/2025 | Complete | E D ELECTRICAL INC | General Wiring |
| 08/07/2024 | Cancelled | ROMA ELECTRIC CORP | General Wiring |
| 12/13/2022 | Complete | CORP. ELEC'L TECHNOLOGIES | General Wiring |
| 03/03/2021 | Complete | ELECTRIC ESSENTIALS CORP | — |
| 02/04/2021 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 02/18/2020 | Cancelled | CITY ELEC'L SIGN ERECTORS | — |
| 04/02/2019 | Complete | CORP. ELEC'L TECHNOLOGIES | General Wiring, HVAC Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Permit Issued | STRUCTURAL PRESERVATION S | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/07/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/11/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/09/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/20/2026 | Fire-Resistant Penetrations and Joints | Brian McDonough | special |
| 01/20/2026 | Interior lighting power | Brian McDonough | energy_progress |
| 01/20/2026 | Lighting controls | Brian McDonough | energy_progress |
| 01/20/2026 | Final | DAVID CHAGNON | progress |
| 01/20/2026 | Energy Code Compliance Inspections | Brian McDonough | progress |
| 01/20/2026 | Tenant Protection Plan Compliance | Brian McDonough | special |
| 01/14/2026 | Tenant Protection Plan Compliance | — | special |
| 01/05/2026 | Final | DAVID CHAGNON | progress |
| 01/05/2026 | Energy Code Compliance Inspections | Brian McDonough | progress |
| 01/05/2026 | Fire-Resistant Penetrations and Joints | Brian McDonough | special |
| 01/05/2026 | Interior lighting power | Brian McDonough | energy_progress |
| 01/05/2026 | Lighting controls | Brian McDonough | energy_progress |
| 11/14/2025 | Duct leakage testing, insulation and design | Brian McDonough | energy_progress |
| 11/14/2025 | HVAC-R and service water heating equipment | Brian McDonough | energy_progress |
| 11/14/2025 | HVAC-R and service water heating system controls | Brian McDonough | energy_progress |
| 11/14/2025 | Maintenance information | Brian McDonough | energy_progress |
| 11/13/2025 | HVAC-R and service water heating system controls | Brian McDonough | energy_progress |
| 11/13/2025 | Fire-Resistant Penetrations and Joints | Brian McDonough | special |
| 11/13/2025 | Energy Code Compliance Inspections | Brian McDonough | progress |
| 11/13/2025 | HVAC-R and service water heating equipment | Brian McDonough | energy_progress |
| 11/13/2025 | Maintenance information | Brian McDonough | energy_progress |
| 11/06/2025 | Energy Code Compliance Inspections | Brian McDonough | progress |
| 11/04/2025 | Tenant Protection Plan Compliance | Brian McDonough | special |
| 11/04/2025 | Tenant Protection Plan Compliance | Brian McDonough | special |
| 11/04/2025 | Fire-Resistant Penetrations and Joints | Brian McDonough | special |