15 BAY RIDGE AVENUE
BROOKLYN · Bay Ridge · BIN 3144947
💬 Discuss this project
1966Year Built
2Stories
O2Building Class
R5BZoning
15,893 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Office only, 2-6 stories · Owner of record: Bay Ridge Plaza · 15,917 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofBay Ridge Center40p · 7 filings · 20 docs
Floor 2Bay Ridge Center70p · 10 filings · 20 docs
Floor 1Bay Ridge Center63p · 12 filings · 20 docs
Site & exterior8-12 W. 14th Associates LLC2p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
8-12 W 14th Associates3407/08/2026
Philips International As Agent2107/08/2026
Bay Ridge Plaza703/21/2026
Metlife Facilities & Services403/21/2026
CFC Associates403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
G3 Architecture Interiors Planning310/27/2023
CFS Engineering410/17/2023
AR Consulting Engineer105/03/2023
HRM Engineering Services408/12/2022
Pba Engineering103/17/2021
Rosenbaum Design Group203/05/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rosenbaum Design Group703/21/2026
Metropolis Group1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Alante ConstructionGeneral Contractor2610/04/2026
Alante ConstructionScaffold307/08/2026
Hydrokinetic Plumbing & Heating IPlumbing307/08/2026
Anesis ServicesFire Protection207/08/2026
P&H Electric D/B/A Mage ElectricElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PSI Agency254610/17/2023
Macia Inspection & Testin402608/12/2022
Building Lifecycle
All (102)Filed (15)Permit Issued (22)Signed Off (11)Violation (7)Inspection (11)Objection (6)Special Inspection (30)
07/25/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/16/2024
Permit issued — General Construction
B00934117-I1-GC
08/22/2024
Violation issued (FDNY_ORDER, closed)
05/01/2024
Signed off — Alteration
FILING APPLICATION FOR REMOVAL AND INSTALLATION OF WALLS, DOORS, FLOOR FINISHES AND CEILINGS AS PER PLANS FILED. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00808023-I1
04/22/2024
Signed off — Alteration
NEW STEEL MEMBERS FOR SLAB OPENING AT 1ST FLOOR AND ROOF OPENING FOR NEW DUCTWORK. NEW STEEL DUNNAGE ON THE ROOF. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00854105-I1
04/17/2024
Signed off — Alteration
Installation of multiple split HVAC units for building shell. No change in use, square footage, zoning or egress under this Alteration Type 2 application.
B00434793-I1
04/08/2024
Permit issued — General Construction
B00808023-I1-GC
11/17/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/13/2023
Signed off — Alteration
FILING APPLICATION TO INSTALL NEW PLUMBING FIXTURES AS PER PLANS FILED. NO CHAGNE TO USE, EGRESS OR OCCUPANCY.
B00853948-I1
11/08/2023
Signed off — Alteration
FILING APPLICATION FOR INSTALLATION OF NEW MECHANICAL SYSTEMS AS PER PLANS FILED. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B00853542-I1
11/08/2023
Signed off — Alteration
B00854046-I1
10/27/2023
Filed — No Work
B00951677-I1
10/23/2023
Special inspection requirement — Public Assembly Emergency Lighting
MAURICIO ANDRADE
10/18/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAURICIO ANDRADE
10/18/2023
Special inspection requirement — Energy Code Compliance Inspections
MAURICIO ANDRADE
10/17/2023
Filed — Alteration
FILING APPLICATION TO INSTALL NEW PLUMBING FIXTURES AS PER PLANS FILED. NO CHAGNE TO USE, EGRESS OR OCCUPANCY.
B00853948-P1
10/16/2023
Permit issued — General Construction
B00934117-I1-GC
10/11/2023
Objection resolved — Addressed
10/11/2023
Objection resolved — Addressed
10/11/2023
Objection resolved — Addressed
10/11/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAURICIO ANDRADE
10/11/2023
Special inspection requirement — Energy Code Compliance Inspections
MAURICIO ANDRADE
10/10/2023
Objection raised — Zoning
10/10/2023
Objection raised — Zoning
10/10/2023
Objection raised — Scope
09/27/2023
Filed — Alteration CO
FILING TO CHANGE THE USE GROUP FROM OFFICES TO COMMUNITY FACILITY USE, AS WELL AS ANY MINOR WORK AS PER THE PLANS SUBMITTED.
B00934117-I1
09/18/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/08/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
09/04/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/10/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/21/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/05/2023
Permit issued — Mechanical Systems
B00853542-I1-MS
05/05/2023
Permit issued — Structural
B00854105-I1-ST
05/03/2023
Filed — Alteration
NEW STEEL MEMBERS FOR SLAB OPENING AT 1ST FLOOR AND ROOF OPENING FOR NEW DUCTWORK. NEW STEEL DUNNAGE ON THE ROOF. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00854105-I1
05/02/2023
Filed — Alteration
FILING APPLICATION FOR INSTALLATION OF NEW MECHANICAL SYSTEMS AS PER PLANS FILED. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B00853542-I1
04/26/2023
Signed off — Alteration
Installation of new plumbing fixtures for core bathrooms, elevator sump pit, janitors closets. Removal of gas service. No change in use, egress, occupancy, zoning computation and/or square footage under this ProCert, Alt. Type 2 application.
B00435909-I1
04/26/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/21/2023
Permit issued — Sprinklers
B00854046-I1-EW-SP
04/19/2023
Permit issued — Plumbing
B00853948-I1-PL
04/18/2023
Filed — Alteration
FILING APPLICATION TO INSTALL NEW PLUMBING FIXTURES AS PER PLANS FILED. NO CHAGNE TO USE, EGRESS OR OCCUPANCY.
B00853948-I1
04/18/2023
Filed — Alteration
B00854046-I1
04/14/2023
Signed off — Alteration
B00743211-I1
04/13/2023
Signed off — Alteration
INSTALLATION OF NEW NON-BEARING PARTITIONS, DOORS, CORE BATHROOMS WITH PLUMBING FIXTURES AND FINISHES. INSTALL A NEW ELEVATOR SHAFT AND NEW ROOF MOUNTED ROOFTOP MECHANICAL UNITS. NO CHANGE IN USE, EGRESS, OCCUPANCY, ZONING COMPUTATION.
B00448069-I1
04/06/2023
Permit issued — General Construction
B00808023-I1-GC
04/03/2023
Special inspection requirement — Structural Steel - High Strength Bolting
MAURICIO ANDRADE
04/03/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
MAURICIO ANDRADE
04/03/2023
Special inspection requirement — Final
MAURICIO ANDRADE
04/03/2023
Special inspection requirement — Structural Steel - Details
MAURICIO ANDRADE
04/03/2023
Special inspection requirement — Structural Steel - Welding
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — Final
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — Energy Code Compliance Inspections
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — Fire-Resistance Rated Construction
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — HVAC-R and service water heating equipment
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — HVAC-R and service water heating system controls
MAURICIO ANDRADE
03/31/2023
Special inspection requirement — Mechanical Systems
MAURICIO ANDRADE
Latest 60 of 102 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedAlante Construction09/16/2024
DOB NOWGeneral ConstructionSigned-offAlante Construction04/08/2024
DOB NOWGeneral ConstructionPermit IssuedAlante Construction10/16/2023
DOB NOWMechanical SystemsSigned-offAlante Construction05/05/2023
DOB NOWStructuralSigned-offAlante Construction05/05/2023
DOB NOWSprinklersSigned-offThomas Fay04/21/2023
DOB NOWPlumbingSigned-offHydrokinetic Plumbing & Heating I04/19/2023
DOB NOWGeneral ConstructionSigned-offAlante Construction04/06/2023
DOB NOWSprinklersSigned-offThomas Fay09/01/2022
DOB NOWMechanical SystemsSigned-offAlante Construction06/29/2022
DOB NOWGeneral ConstructionSigned-offAlante Construction06/29/2022
DOB NOWPlumbingSigned-offHydrokinetic Plumbing & Heating I05/18/2022
DOB NOWMechanical SystemsSigned-offAlante Construction04/25/2022
DOB NOWGeneral ConstructionSigned-offAlante Construction04/25/2022
DOB NOWMechanical SystemsSigned-offAlante Construction04/26/2021
DOB NOWStructuralSigned-offAlante Construction04/26/2021
DOB NOWConstruction FenceSigned-offAlante Construction04/23/2021
DOB NOWMechanical SystemsSigned-offAlante Construction03/24/2021
DOB NOWPlumbingSigned-offHydrokinetic Plumbing & Heating I03/24/2021
DOB NOWStructuralSigned-offAlante Construction03/18/2021
DOB NOWConstruction FenceSigned-offAlante Construction03/08/2021
DOB NOWGeneral ConstructionSigned-offAlante Construction03/08/2021
BISPLISSUEDB&B Mechanical Plumbing & Heating03/29/2019
BISOTISSUEDReliant Builders03/28/2019
BIS—ISSUEDNorth Shore Neon Sign Co04/26/2017
BIS—ISSUEDAmerican Sign & Electrical Con09/02/2016
BISPLISSUEDJpi Plumbing & Heating10/15/2014
BISBLISSUEDJpi Plumbing & Heating10/15/2014
BISMHISSUEDCampa Construction10/09/2014
BISOTISSUEDCampa Construction12/20/2012
BISOTISSUEDCampa Construction09/07/2012
BISPLISSUEDWexler PLG Heating02/02/2000
BISEQISSUEDAcc Construction01/31/2000
BISOTISSUEDAcc Construction01/31/2000
BISMHISSUEDAcc Construction01/31/2000
10 projects · most recent 10/16/2024
General Wiring
FiledStatusContractorScope
10/16/2024CompleteP&H Electric D/B/A Mage ElectricGeneral Wiring
10/10/2024CompleteP&H Electric D/B/A Mage ElectricGeneral Wiring
10/10/2024CompleteP&H Electric D/B/A Mage Electric—
10/10/2024CancelledP&H Electric D/B/A Mage Electric—
10/08/2024CompleteP&H Electric D/B/A Mage ElectricGeneral Wiring
10/08/2024CompleteP&H Electric D/B/A Mage Electric—
03/23/2023CompleteWest Shore ElectricGeneral Wiring
07/29/2021CompleteWest Shore ElectricGeneral Wiring
06/08/2021CompleteTuxedo Electrical Contracting—
04/10/2019CompleteS&R Electric & Contracting—
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
07/25/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/17/2023Pass-Final CND-Occupancy InspectionPassView ↗
09/18/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
09/08/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/04/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/10/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/01/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/26/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
03/03/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/01/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 54
DateRequirementInspectorRole
10/23/2023Public Assembly Emergency LightingMAURICIO ANDRADEprogress
10/18/2023Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
10/18/2023Energy Code Compliance InspectionsMAURICIO ANDRADEprogress
10/11/2023Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
10/11/2023Energy Code Compliance InspectionsMAURICIO ANDRADEprogress
04/03/2023Structural Steel - High Strength BoltingMAURICIO ANDRADEspecial
04/03/2023Structural Stability – Alterations of existing buildingsMAURICIO ANDRADEspecial
04/03/2023FinalMAURICIO ANDRADEprogress
04/03/2023Structural Steel - DetailsMAURICIO ANDRADEspecial
04/03/2023Structural Steel - WeldingMAURICIO ANDRADEspecial
03/31/2023Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
03/31/2023FinalMAURICIO ANDRADEprogress
03/31/2023Energy Code Compliance InspectionsMAURICIO ANDRADEprogress
03/31/2023Fire-Resistance Rated ConstructionMAURICIO ANDRADEprogress
03/31/2023HVAC-R and service water heating equipmentMAURICIO ANDRADEenergy_progress
03/31/2023HVAC-R and service water piping design and insulationMAURICIO ANDRADEenergy_progress
03/31/2023HVAC-R and service water heating system controlsMAURICIO ANDRADEenergy_progress
03/31/2023Mechanical SystemsMAURICIO ANDRADEspecial
03/31/2023Post-installed AnchorsMAURICIO ANDRADEspecial
01/05/2023FinalMAURICIO ANDRADEprogress
01/05/2023Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
01/05/2023Fire-Resistance Rated ConstructionMAURICIO ANDRADEprogress
01/05/2023Lighting controlsMAURICIO ANDRADEenergy_progress
01/05/2023Interior lighting powerMAURICIO ANDRADEenergy_progress
01/05/2023Post-installed AnchorsMAURICIO ANDRADEspecial
Latest 25 of 54.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Bay Ridge CenterCommunity FacilityFloors 1, 2
Project B00934117 Alteration CO · Permit Entire · 09/27/2023
Project B00808023 Alteration · LOC Issued · 03/30/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 201 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch9
09/01/2026B00478645-I1Request digital key ↗
08/28/2026B00743211-I1Request digital key ↗
08/27/2026B00808023-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
08/29/2026B00435909-I1Request digital key ↗
08/29/2026B00435909-P1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
09/01/2026B00448069-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/01/2026B00434793-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
08/26/2026B00951677-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/01/2026B00435914-I1Request digital key ↗
▸Applications & Permits22
▸BISPLAN / WORK APPROVAL APPLICATION14
06/26/2024321010507Open ↗
06/10/2024320518392Open ↗
05/16/2024320530724Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION8
04/01/2019321938560Open ↗
09/02/2016321438949Open ↗
10/16/2014321010507Open ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications81
▸DOB NOWProgress Inspector Seal & Signature29
09/12/2026B00435914-I1Open ↗
09/01/2026B00434793-I1Open ↗
09/01/2026B00434793-I1Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
09/01/2026B00478645-I1Open ↗
08/29/2026B00435909-I1Open ↗
08/29/2026B00435909-P1Open ↗
Showing 3 of 15 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION14
11/15/2019321938560Open ↗
04/01/2019321938560Open ↗
05/31/2018321438949Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/12/2026B00435914-I1Open ↗
09/12/2026B00435914-I1Open ↗
09/12/2026B00435914-I1Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
04/01/2019321938560Open ↗
05/02/2017321520083Open ↗
10/10/2014321010507Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
04/01/2019321938560Open ↗
04/01/2019321938560Open ↗
10/10/2014321010507Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
08/06/2012320530724Open ↗
07/26/2012320518392Open ↗
▸BISProfessional and Owner Certification (POC3)1
05/02/2017321520083Open ↗
▸Trade Schedules & Equipment11
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
04/01/2019321938560Open ↗
03/09/2015321010507Open ↗
10/10/2014321010507Open ↗
▸BISSELF-CERT PLUMBING NOTICE3
08/19/2015321010507Open ↗
05/21/2015321010507Open ↗
03/23/2015321010507Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
10/10/2014321010507Open ↗
08/06/2012320530724Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
04/10/2024321010507Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
04/10/2024321010507Open ↗
▸BISHEATING SYSTEMS1
04/09/2024321010507Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026B00934117-I1Open ↗
▸Environmental & Asbestos19
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
08/29/2026B00435909-I1Open ↗
08/29/2026B00435909-P1Open ↗
08/28/2026B00743211-I1Open ↗
Showing 3 of 13 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)6
04/01/2019321938560Open ↗
05/02/2017321520083Open ↗
09/02/2016321438949Open ↗
Showing 3 of 6 on file for this type
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
04/01/2019321938560Open ↗
10/10/2014321010507Open ↗
10/10/2014321010507Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.3
08/13/2026B00434793-I1Open ↗
08/13/2026B00448069-I1Open ↗
08/13/2026B00435909-I1Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
04/09/2024321010507Open ↗
▸BIS* HVAC INSULATION AND SEALING1
04/10/2024321010507Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
11/15/2019321938560Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/09/2024321010507Open ↗
▸Inspections & Test Reports1
▸BISMECHANICAL SYSTEMS1
04/09/2024321010507Open ↗
▸Approvals, Objections & Sign-offs9
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
11/15/2019321938560Open ↗
05/31/2018321438949Open ↗
02/27/2018321438949Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
10/10/2014321010507Open ↗
08/03/2012320530724Open ↗
▸BISFINAL1
04/09/2024321010507Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
04/12/2019321846767Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT9
11/15/2019321938560Open ↗
04/01/2019321938560Open ↗
02/05/2018321438949Open ↗
Showing 3 of 9 on file for this type
▸Filing & Intake Forms15
▸BISBOROUGH INTAKE FORM6
04/12/2019321846767Open ↗
05/31/2018321438949Open ↗
05/31/2018321438949Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET6
03/29/2019321938560Open ↗
05/02/2017321520083Open ↗
08/18/2016321438949Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION3
08/07/2015321010507Open ↗
06/17/2015321010507Open ↗
03/20/2015321010507Open ↗
▸Other Documents5
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
04/12/2019321846767Open ↗
▸BISINTERNAL (SECONDARY) BACKFLOW PREVENTION DEVICE TEST REPORT1
08/19/2015321010507Open ↗
▸BISSHUTOFF DAMPERS1
04/10/2024321010507Open ↗
▸BISLAA - Supporting Documentation1
02/05/2018321438949Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026B00934117-I1Open ↗