← Back
Hospital, sanitarium, mental institution
NYU Langone Hospital
5501 1 AVENUE · BIN 3014856
💬 Discuss this project
1931Year Built
5Stories
I1Building Class
R6Zoning
460,000 sfGross Floor Area
1Units
LL97 Covered1 Open Violation ▸FDNY Report ↗
Hospital, sanitarium, mental institution · 140,000 sf lot · 3.29 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Permit Issued — active, not yet Signed-off
Roof173p · 30 filings · 20 docs
PenthouseUnder Construction23p · 4 filings · 20 docs
Floor 8Under Construction1 filing · 4 docs
Floor 7Under Construction1 filing · 4 docs
Floor 6Under Construction13p · 10 filings · 20 docs
Floor 5Under Construction111p · 14 filings · 20 docs
Floor 413p · 25 filings · 20 docs
Floor 3219p · 32 filings · 20 docs
Floor 2Under Construction174p · 14 filings · 20 docs
Floor 1231p · 26 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SKYLINE SCAFFOLDING GROUP3609/23/2026
NYULH16507/08/2026
NYU LANGONE HEALTH703/22/2026
LENDLEASE US CONSTRUCTION103/22/2026
EMPIRE GENERAL CONTRACTIN203/21/2026
LUTHERINE MEDICAL HOSPITAL103/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
OUTSOURCE CONSULTANTS, INC.30303/21/2026
EUROCELT EXPEDITING, INC1403/21/2026
A1 EXPEDITING SERVICE3003/21/2026
AE DESIGN SOLUTION2803/21/2026
Rigid Structural Design, LLC1903/21/2026
DIRECT ACCESS EXPEDITING, INC.203/21/2026
WILLIAM VITACCO ASSOCIATES1903/21/2026
CONSTRUCTION PERMIT SERVICES103/21/2026
RPO203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EMPIRE GENERAL CONTRACTINGeneral Contractor4809/13/2026
B.R. FRIES & ASSOCIATES LLCGeneral Contractor4207/08/2026
SKYLINE SCAFFOLDING GROUPGeneral Contractor3609/18/2026
SKANSKA USA BUILDING, INCGeneral Contractor2408/05/2026
POWERS BRIDGING & SCAFFOLDINGGeneral Contractor2207/08/2026
SAFWAY ATLANTIC, LLCGeneral Contractor2109/18/2026
L.F. DRISCOLL COMPANY LLCGeneral Contractor1907/08/2026
UNIVERSAL BUILD SUPP LLCGeneral Contractor1507/08/2026
ALLIANCE PLUMBING CORPPlumbing1209/18/2026
NELSON AIR DEVICE CORPGeneral Contractor1207/08/2026
CARDOZA PLUMBING CORPPlumbing1107/08/2026
LENDLEASE(US)CONSTRUCTIONGeneral Contractor1007/08/2026
ASHLAR MECHANICAL CORPFire Protection907/08/2026
NYC FIRE SPRINKLER CORPFire Protection909/13/2026
EXPERT MAINTENANCE CORPGeneral Contractor704/09/2026
GLASS ARMOR OF NEW YORK IGeneral Contractor707/08/2026
KING HOIST & SCAFFOLDINGGeneral Contractor707/08/2026
PAUL M MAINTENANCE INCGeneral Contractor607/08/2026
BENJAMIN CONSTRUCTION CORGeneral Contractor507/08/2026
SIRINA FIRE PROT CORPFire Protection507/08/2026
AMERICON CONSTRUCTION INC.General Contractor404/09/2026
J T & T AIR CONDITIONINGGeneral Contractor407/08/2026
SCOTT BIGMANElectrical403/21/2026
BIGMAN BROS., INC.Electrical403/22/2026
HOLT CONSTRUCTION CORPGeneral Contractor307/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALAN MARGOLIN & ASSOC42315208/18/2026
SONI ENGINEERING CONSULTI9819111/12/2025
G. BLINN CONSULTING, LLC2894206/18/2025
ATLANTIC ENGINEERINGLABOR13811407/06/2023
ATLAS ATC ENGINEERING INC8011205/12/2021
JOEL PHAGOO ,PE, PLLC2416103/06/2020
Building Lifecycle
All (300)Filed (71)Permit Issued (80)Signed Off (10)Violation (3)Inspection (30)Objection (76)Special Inspection (30)
09/17/2026
Permit issued — Protection and Mechanical Methods
B01143252-I1-PMM
09/17/2026
Permit issued — Supported Scaffold
B01450400-I1-SF
09/17/2026
Permit issued — Supported Scaffold
B01239220-I1-SF
09/17/2026
Permit issued — Protection and Mechanical Methods
B01239231-I1-PMM
09/17/2026
Permit issued — Protection and Mechanical Methods
B01453633-I1-PMM
09/17/2026
Permit issued — Construction Fence
B01142993-I1-FN
09/17/2026
Permit issued — Plumbing
B01408513-S2-PL
09/17/2026
Permit issued — Supported Scaffold
B01144126-I1-SF
09/17/2026
Permit issued — Protection and Mechanical Methods
B01143263-I1-PMM
09/16/2026
Filed — Alteration
Installation of a temporary overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application
B01453633-I1
09/15/2026
Permit issued — Suspended Scaffold
B01316258-I1-SC
09/11/2026
Permit issued — Mechanical Systems
B01408513-S1-MS
09/11/2026
Permit issued — Sprinklers
B01408513-S3-EW-SP
09/09/2026
Permit issued — General Construction
B01408513-I1-GC
09/08/2026
Permit issued — Sprinklers
B01152884-S2-EW-SP
08/31/2026
Permit issued — Plumbing
B01107884-S2-PL
08/28/2026
Permit issued — Boiler Equipment
B01107884-I1-BE
08/27/2026
Permit issued — Mechanical Systems
B01107884-S3-MS
08/26/2026
Permit issued — Mechanical Systems
B01107884-S1-MS
08/25/2026
Objection resolved — Resolved
08/24/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/18/2026
Filed — Alteration
NYU - 150 55TH STREET - Mechanical work on first floor Associated with the installation of (2) New 49.5 HP, Dual fuel boilers. Boiler work and plumbing work filed under separate applications. No change in egress, occupancy or use.
B01107884-S3
08/18/2026
Permit issued — Sprinklers
B01358261-S3-EW-SP
08/18/2026
Permit issued — Mechanical Systems
B01358261-S1-MS
08/14/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/14/2026
Objection resolved — Resolved
08/04/2026
Permit issued — Mechanical Systems
B01270357-S1-MS
07/31/2026
Permit issued — Plumbing
B01270357-S2-PL
07/31/2026
Permit issued — Sprinklers
B01270357-S3-EW-SP
07/30/2026
Permit issued — Structural
B01270357-S4-ST
07/29/2026
Permit issued — General Construction
B01270357-I1-GC
07/28/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
07/24/2026
Permit issued — Plumbing
B01358261-S2-PL
07/23/2026
Objection raised — Other
07/23/2026
Objection raised — Other
07/22/2026
Permit issued — General Construction
B01358261-I1-GC
07/21/2026
Filed — Alteration
NYU - 150 55TH STREET - Mechanical work on first floor Associated with the installation of (2) New 49.5 HP, Dual fuel boilers. Boiler work and plumbing work filed under separate applications. No change in egress, occupancy or use.
B01107884-S2
07/16/2026
Filed — Alteration
NYU - 150 55TH STREET - Mechanical work on first floor Associated with the installation of (2) New 49.5 HP, Dual fuel boilers. Boiler work and plumbing work filed under separate applications. No change in egress, occupancy or use.
B01107884-S1
07/14/2026
Filed — Alteration
NYU - 150 55TH STREET - Mechanical work on first floor Associated with the installation of (2) New 49.5 HP, Dual fuel boilers. Boiler work and plumbing work filed under separate applications. No change in egress, occupancy or use.
B01107884-I1
07/13/2026
Permit issued — Sidewalk Shed
B01009288-I1-SH
07/10/2026
Special inspection requirement — Chimneys and vents
Young Suh
07/10/2026
Special inspection requirement — Post-installed Anchors
Young Suh
07/10/2026
Special inspection requirement — High-Pressure Steam Piping (Welding)
Young Suh
07/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
07/07/2026
Filed — Alteration
NYULH BROOKLYN - MRI EXPANSION P1 - MECHANICAL MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01408513-S1
07/02/2026
Objection resolved — Resolved
07/02/2026
Objection resolved — Resolved
07/02/2026
Objection resolved — Resolved
07/02/2026
Objection resolved — Resolved
07/02/2026
Objection resolved — Addressed
07/02/2026
Objection resolved — Addressed
07/02/2026
Objection resolved — Addressed
07/02/2026
Objection resolved — Addressed
06/29/2026
Filed — Alteration
NYULH BROOKLYN - MRI EXPANSION P1 - MECHANICAL MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01408513-S3
06/29/2026
Filed — Alteration
NYULH BROOKLYN - MRI EXPANSION P1 - MECHANICAL MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01408513-S2
06/29/2026
Objection resolved — Resolved
06/29/2026
Objection resolved — Resolved
06/28/2026
Filed — Alteration
NYULH BROOKLYN - MRI EXPANSION P1 - MECHANICAL MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01408513-I1
06/23/2026
Special inspection requirement — Lighting controls
Young Suh
06/23/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedALLIANCE PLUMBING CORP09/17/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedSAFWAY ATLANTIC, LLC09/17/2026
DOB NOWSupported ScaffoldPermit IssuedSAFWAY ATLANTIC, LLC09/17/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedSAFWAY ATLANTIC, LLC09/17/2026
DOB NOWSupported ScaffoldPermit IssuedSKYLINE SCAFFOLDING GROUP09/17/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedSAFWAY ATLANTIC, LLC09/17/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedSKYLINE SCAFFOLDING GROUP09/17/2026
DOB NOWConstruction FencePermit IssuedSAFWAY ATLANTIC, LLC09/17/2026
DOB NOWSupported ScaffoldPermit IssuedSAFWAY ATLANTIC, LLC09/17/2026
DOB NOWSuspended ScaffoldPermit IssuedBENJAMIN CONSTRUCTN CORP09/15/2026
DOB NOWSprinklersPermit IssuedNYC FIRE SPRINKLER CORP09/11/2026
DOB NOWMechanical SystemsPermit IssuedEMPIRE GENERAL CONTRACTIN09/11/2026
DOB NOWGeneral ConstructionPermit IssuedEMPIRE GENERAL CONTRACTIN09/09/2026
DOB NOWSprinklersPermit IssuedPAR FIRE PROTECTION LLC09/08/2026
DOB NOWPlumbingPermit IssuedFRESH MEADOW MECH PLBG LL08/31/2026
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP08/28/2026
DOB NOWMechanical SystemsPermit IssuedFRESH MEADOW MECHANICAL C08/27/2026
DOB NOWMechanical SystemsPermit IssuedFRESH MEADOW MECHANICAL C08/26/2026
DOB NOWSprinklersPermit IssuedARCHER CONSULTANTS GROUP08/18/2026
DOB NOWMechanical SystemsPermit IssuedRACANELLI CONSTRUCTION CO08/18/2026
DOB NOWMechanical SystemsPermit IssuedSKANSKA USA BUILDING, INC08/04/2026
DOB NOWPlumbingPermit IssuedPAR PLUMBING CO., INC07/31/2026
DOB NOWSprinklersPermit IssuedPAR FIRE PROTECTION LLC07/31/2026
DOB NOWStructuralPermit IssuedSKANSKA USA BUILDING, INC07/30/2026
DOB NOWGeneral ConstructionPermit IssuedSKANSKA USA BUILDING, INC07/29/2026
DOB NOWPlumbingPermit IssuedPAR PLUMBING CO., INC07/24/2026
DOB NOWGeneral ConstructionPermit IssuedRACANELLI CONSTRUCTION CO07/22/2026
DOB NOWSidewalk ShedPermit IssuedSKYLINE SCAFFOLDING GROUP07/13/2026
DOB NOWSprinklersPermit IssuedARCHER CONSULTANTS GROUP06/22/2026
DOB NOWPlumbingPermit IssuedCAPITAL CONTR P&H CORP06/10/2026
DOB NOWPlumbingPermit IssuedCAPITAL CONTR P&H CORP06/09/2026
DOB NOWSprinklersPermit IssuedSIRINA FIRE PROT CORP05/19/2026
DOB NOWStandpipePermit IssuedSIRINA FIRE PROT CORP05/18/2026
DOB NOWConstruction FencePermit IssuedSKYLINE SCAFFOLDING GROUP05/15/2026
DOB NOWSupported ScaffoldPermit IssuedTOPLINE NYC CONTRACTING05/15/2026
DOB NOWSidewalk ShedPermit IssuedSKYLINE SCAFFOLDING GROUP04/28/2026
DOB NOWGeneral ConstructionPermit IssuedSKANSKA USA BUILDING, INC04/28/2026
DOB NOWGeneral ConstructionPermit IssuedSKANSKA USA BUILDING, INC04/27/2026
DOB NOWConstruction FencePermit IssuedSKYLINE SCAFFOLDING GROUP04/24/2026
DOB NOWSupported ScaffoldPermit IssuedSKYLINE SCAFFOLDING GROUP04/24/2026
+ 60 more permits on file
9 projects · most recent 08/18/2026
Ventilation Systems Air Conditioning Systems Heating Systems Generators
FiledStatusContractorScopeMake / Model / Capacity
08/18/2026Permit IssuedFRESH MEADOW MECHANICAL CVentilation Systems
Ventilation
Acrovent DDR 1,500 CFM · Exhaust Fan ×1
07/07/2026Permit IssuedEMPIRE GENERAL CONTRACTINHeating Systems
Heating
Precision Coils HW58S01Q10-24x56-RH 3,100 CFM ×1
05/20/2026Permit IssuedRACANELLI CONSTRUCTION COAir Conditioning Systems, Ventilation Systems
Cooling
Climatemaster SR-024 24,000 BTU · Wshp ×1
Ventilation
— DDM-16 2,700 CFM · Ductwork ×2
04/21/2026Permit IssuedAMERICON CONSTRUCTION INCAir Conditioning Systems, Ventilation Systems
Cooling
Ventilation
Twin City Fan TL-400R 275 CFM · Exhaust Fan ×3
03/29/2026——Ventilation Systems
Ventilation
Twin City Fan BAV-122 1,300 CFM ×2
10/29/2025Permit IssuedSKANSKA USA BUILDING, INCAir Conditioning Systems, Generators
Cooling
Daikin FXAQ18PVJU 13,375 BTU · Vrf Indoor ×2
RXTQ36TAVJ9A 36,174 BTU · Vrf Outdoor ×1
Generators
Caterpillar 3516C 2,000 kW · Generator ×3
07/08/2025Permit IssuedSKANSKA USA BUILDING, INCAir Conditioning Systems
Cooling
Liebert PW017UC 60,500 BTU · Crac Unit ×14
PW017US 60,500 BTU · Crac Unit ×2
05/19/2025Permit IssuedCENTRAL CONSULTING & CONTVentilation Systems
Ventilation
Twin City Fan BCV-122 1,300 CFM · Exhaust Fan ×1
04/13/2022Permit IssuedB.R. FRIES & ASSOCIATES LHeating Systems—
14 projects · most recent 07/07/2026
Sprinkler System
FiledStatusContractorScope
07/07/2026Permit IssuedNYC FIRE SPRINKLER CORP—
05/20/2026Permit IssuedARCHER CONSULTANTS GROUP—
04/23/2026Permit IssuedA & F FIRE PROTECTION CO72 heads
03/29/2026——Sprinkler System
03/27/2026——87 heads
03/06/2026——4 heads
01/05/2026Permit IssuedPAR FIRE PROTECTION LLC236 heads
12/19/2025Permit IssuedPREFERRED SPKLR AND MECHSprinkler System
11/21/2025Permit IssuedARCHER CONSULTANTS GROUP52 heads
11/12/2025Permit IssuedPAR FIRE PROTECTION LLCSprinkler System
10/29/2025Permit IssuedSIRINA FIRE PROT CORP—
04/19/2022Permit IssuedASHLAR MECHANICAL CORP36 heads
07/16/2021Permit IssuedNYC FIRE SPRINKLER CORP—
12/21/2020Signed-offSIRINA FIRE PROT CORP4 heads
17 projects · most recent 08/18/2026
Water/Sanitary Gas Medical Gas Storm
FiledStatusContractorScope
08/18/2026Permit IssuedFRESH MEADOW MECH PLBG LLGas, Water/Sanitary
07/07/2026Permit IssuedCARDOZA PLUMBING CORPWater/Sanitary
05/20/2026Permit IssuedPAR PLUMBING CO., INCWater/Sanitary
04/23/2026———
04/21/2026Permit IssuedCAPITAL CONTR P&H CORPWater/Sanitary
03/29/2026——Medical Gas, Water/Sanitary
03/27/2026——Gas, Water/Sanitary
03/27/2026——Water/Sanitary
03/06/2026——Water/Sanitary
02/17/2026Permit IssuedCAPITAL CONTR P&H CORPWater/Sanitary
01/05/2026Permit IssuedPAR PLUMBING CO., INCMedical Gas, Water/Sanitary
12/19/2025Permit IssuedALLIANCE PLUMBING CORPWater/Sanitary
11/21/2025———
11/12/2025Permit IssuedCARDOZA PLUMBING CORPWater/Sanitary
10/29/2025Permit IssuedJ.M. BOTTO INCStorm
25 projects · most recent 08/26/2026
General Wiring
FiledStatusContractorScope
08/26/2026Permit IssuedHUGH O'KANE ELEC. CO. INCGeneral Wiring
07/17/2026Permit IssuedALLAN BRITEWAY ELECTRICALGeneral Wiring
06/19/2026Permit IssuedTOP SHELF ELECTRIC CORP—
01/13/2026Permit IssuedBIGMAN BROS., INC.General Wiring
10/10/2025Permit IssuedBIGMAN BROS., INC.General Wiring
09/10/2025Permit IssuedHUGH O'KANE ELEC. CO. INCGeneral Wiring
09/02/2025Permit IssuedFOREST ELECTRIC CORP.General Wiring
09/02/2025Permit IssuedFOREST ELECTRIC CORP.General Wiring
09/02/2025CompleteFOREST ELECTRIC CORP.General Wiring
07/29/2025Permit IssuedFOREST ELECTRIC CORP.General Wiring
04/22/2025Permit IssuedE-J ELEC. INSTALLATION COGeneral Wiring
03/12/2025CompleteRIGID ELECTRIC, INC.General Wiring
02/11/2025Permit IssuedE-J ELEC. INSTALLATION CO—
01/06/2025Permit IssuedBIGMAN BROS., INC.General Wiring
12/02/2024Permit IssuedCORPORATE ELEC. GROUP INC—
4 projects · most recent 03/29/2026
Steel Concrete
FiledStatusContractorScope
03/29/2026——Steel
11/12/2025Permit IssuedPAR FIRE PROTECTION LLCSteel, Concrete
10/29/2025Permit IssuedSIRINA FIRE PROT CORPSteel, Concrete
02/07/2025Permit IssuedSKANSKA USA BUILDING, INCSteel, Concrete
6 projects · most recent 06/12/2026
Scaffold Fence Sidewalk Shed
FiledStatusContractorScope
06/12/2026Permit IssuedSKYLINE SCAFFOLDING GROUPScaffold
01/23/2026Permit IssuedSKYLINE SCAFFOLDING GROUPSidewalk Shed
06/18/2025Permit IssuedSAFWAY ATLANTIC, LLCScaffold
12/18/2024Permit IssuedSAFWAY ATLANTIC, LLCScaffold
12/18/2024Permit IssuedSAFWAY ATLANTIC, LLCFence
03/23/2021Permit IssuedLENDLEASE(US)CONSTRUCTIONFence
2 projects · most recent 11/12/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
11/12/2025Permit IssuedBENJAMIN CONSTRUCTN CORPSuspended Scaffold (SC)
12/14/2023Permit IssuedC&C DALEY'S CONST.CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 125
DateTypeResultReport
08/24/2026Fail-Final General Construction Non-Directive 14FailView ↗
08/14/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/28/2026Fail-Final General Construction Non-Directive 14FailView ↗
05/01/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/29/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/23/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/19/2025Fail-Final Boiler Equipment InspectionFailView ↗
09/23/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/17/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/02/2025Pass-Final CND-Occupancy InspectionPassView ↗
08/18/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/23/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/18/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/25/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/24/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/19/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/27/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/23/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/19/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/02/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/24/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/24/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/17/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/11/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
Latest 25 of 125.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
07/10/2026Post-installed AnchorsYoung Suhspecial
07/10/2026Chimneys and ventsYoung Suhspecial
07/10/2026High-Pressure Steam Piping (Welding)Young Suhspecial
07/10/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
06/23/2026HVAC-R and service water heating equipmentYoung Suhenergy_progress
06/23/2026Energy Code Compliance InspectionsYoung Suhprogress
06/23/2026Duct leakage testing, insulation and designYoung Suhenergy_progress
06/23/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
06/23/2026Interior lighting powerYoung Suhenergy_progress
06/23/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
06/23/2026Heating SystemsYoung Suhspecial
06/23/2026HVAC-R and service water heating system controlsYoung Suhenergy_progress
06/23/2026Maintenance informationYoung Suhenergy_progress
06/23/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
06/23/2026Lighting controlsYoung Suhenergy_progress
06/23/2026Post-installed AnchorsYoung Suhspecial
06/23/2026HVAC-R and service water piping design and insulationYoung Suhenergy_progress
06/23/2026Post-installed AnchorsYoung Suhspecial
06/09/2026Sprinkler SystemsYoung Suhspecial
06/09/2026Post-installed AnchorsYoung Suhspecial
06/09/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
06/04/2026Electrical motors and elevatorsYoung Suhenergy_progress
06/04/2026Duct leakage testing, insulation and designYoung Suhenergy_progress
06/04/2026HVAC-R and service water heating system controlsYoung Suhenergy_progress
06/04/2026HVAC-R and service water heating system controlsYoung Suhenergy_progress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Nyu Langone BrooklynMedical / HealthcareFloor 2
Project B00709485 Alteration · Permit Entire · 04/19/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 3,801 on file (BIS + DOB NOW)
▸Plans & Drawings271
▸DOB NOWPlans/Sketch223
09/23/2026B01453633-I1Request digital key ↗
09/03/2026B00036272-I1Request digital key ↗
09/02/2026B00081213-I1Request digital key ↗
Showing 3 of 223 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems11
09/02/2026B00204053-I1Request digital key ↗
09/01/2026B00427084-P1Request digital key ↗
09/01/2026B00427084-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Plumbing8
09/01/2026B00464915-I1Request digital key ↗
09/01/2026B00441266-I1Request digital key ↗
09/01/2026B00466896-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler8
09/02/2026B00427433-I1Request digital key ↗
09/01/2026B00442845-I1Request digital key ↗
09/01/2026B00466905-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - General Construction7
09/01/2026B00454452-I1Request digital key ↗
09/01/2026B00471191-I1Request digital key ↗
09/01/2026B00464751-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed7
09/02/2026B00327753-I1Request digital key ↗
09/02/2026B00345783-I1Request digital key ↗
Showing 2 of 7 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold4
09/02/2026B00327731-I1Request digital key ↗
09/02/2026B00387472-I1Request digital key ↗
09/02/2026B00387472-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Structural2
09/01/2026B00466884-I1Request digital key ↗
Showing 1 of 2 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Applications & Permits548
▸BISPLAN / WORK APPROVAL APPLICATION264
02/03/2026340794723Open ↗
08/13/2025321472143Open ↗
07/22/2025321472143Open ↗
Showing 3 of 264 on file for this type
▸BISWORK PERMIT APPLICATION234
12/07/2023321496671Open ↗
04/11/2022321469683Open ↗
06/09/2021340797472Open ↗
Showing 3 of 234 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION40
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 40 on file for this type
▸BISPLACE OF ASSEMBLY10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWRestrictive Declaration/Easement 12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Seals & Professional Certifications1,083
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION359
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 359 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature267
09/18/2026B01453633-I1Open ↗
09/03/2026B00036272-I1Open ↗
09/02/2026B00081213-I1Open ↗
Showing 3 of 267 on file for this type
▸DOB NOWProgress Inspector Seal & Signature158
09/28/2026B08037835-I1Open ↗
09/28/2026B08037835-I1Open ↗
09/23/2026B00894997-I1Open ↗
Showing 3 of 158 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature133
09/28/2026B08037835-I1Open ↗
09/23/2026B00894997-I1Open ↗
09/23/2026B01245380-S1Open ↗
Showing 3 of 133 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST64
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 64 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT50
12/16/2020340794830Open ↗
Showing 1 of 50 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM26
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 26 on file for this type
▸BISProfessional and Owner Certification (POC3)7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY7
01/28/2021340797472Open ↗
12/16/2020340794830Open ↗
12/14/2020340794723Open ↗
Showing 3 of 7 on file for this type
▸BISPC FULL REPORT6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
12/16/2020340794830Open ↗
Showing 1 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
01/28/2021340797472Open ↗
12/14/2020340794723Open ↗
▸Trade Schedules & Equipment225
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE54
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 54 on file for this type
▸BISSCHEDULE B - PLUMBING42
02/15/2022321496671Open ↗
05/18/2021321496671Open ↗
04/30/2021321496671Open ↗
Showing 3 of 42 on file for this type
▸BISEQUIPMENT USE PERMITS35
05/01/2023321469683Open ↗
05/01/2023321469683Open ↗
05/01/2023321469683Open ↗
Showing 3 of 35 on file for this type
▸BISSELF-CERT PLUMBING NOTICE35
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 35 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA28
12/03/2024321472143Open ↗
02/06/2024321725068Open ↗
09/15/2021321753125Open ↗
Showing 3 of 28 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT20
05/01/2023321469683Open ↗
05/01/2023321469683Open ↗
05/01/2023321469683Open ↗
Showing 3 of 20 on file for this type
▸BISSPRINKLER INSP REPORT : FP-855
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSTANDPIPE INSP REPORT : FP-842
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸Environmental & Asbestos244
▸DOB NOWDEP ACP-5: Asbestos Assessment Report81
09/03/2026B00036272-I1Open ↗
09/01/2026B00464915-I1Open ↗
09/01/2026B00441266-I1Open ↗
Showing 3 of 81 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form55
09/01/2026B00427084-I1Open ↗
09/01/2026B00442815-I1Open ↗
09/01/2026B00442845-I1Open ↗
Showing 3 of 55 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)47
12/14/2020340794723Open ↗
Showing 1 of 47 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)18
06/02/2021340797472Open ↗
12/18/2020340794830Open ↗
Showing 2 of 18 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM10
12/02/2020321695803Open ↗
Showing 1 of 10 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISDEP ASBESTOS PROJECT CONDITIONAL COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWACP5/20/21 or V51
09/01/2026B00479803-I1Open ↗
▸Energy Compliance221
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS107
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 107 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS40
02/15/2023321469683Open ↗
02/10/2023321469683Open ↗
07/07/2022340797472Open ↗
Showing 3 of 40 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY25
03/14/2025321039238Open ↗
10/25/2023340794830Open ↗
02/15/2023321469683Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.21
09/01/2026B00454452-I1Open ↗
09/01/2026B00454251-I1Open ↗
09/01/2026B00479043-I1Open ↗
Showing 3 of 21 on file for this type
▸BISTECHNICAL REPORT: ENERGY10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISTR8: Energy Code Progress Inspections6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)6
10/12/2023340794830Open ↗
03/22/2023321469683Open ↗
12/10/2021321527111Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS4
01/28/2021340797472Open ↗
12/16/2020340794830Open ↗
12/14/2020340794723Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Inspections & Test Reports55
▸BISTECHNICAL REPORT: RESPONSIBILITY52
03/14/2025321039238Open ↗
10/25/2023340794830Open ↗
02/15/2023321469683Open ↗
Showing 3 of 52 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
12/18/2020340794830Open ↗
▸Approvals, Objections & Sign-offs473
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter255
09/18/2026B01453633-I1Open ↗
09/03/2026B00036272-I1Open ↗
09/01/2026B00427084-P1Open ↗
Showing 3 of 255 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST112
07/23/2025321472143Open ↗
02/20/2024321725068Open ↗
10/26/2023340794830Open ↗
Showing 3 of 112 on file for this type
▸BISADMINISTRATIVE OBJECTIONS52
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 52 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION28
12/07/2023321496671Open ↗
10/26/2023340794830Open ↗
Showing 2 of 28 on file for this type
▸DOB NOWDEP Variance (V5) letter22
09/01/2026B00479803-I1Open ↗
Showing 1 of 22 on file for this type
▸BISFINAL2
10/20/2023340794830Open ↗
03/30/2022321496671Open ↗
▸BISCONSTRUCTION CODE DETERMINATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Cost, Insurance & Ownership273
▸BISCOST AFFIDAVIT264
02/15/2023321469683Open ↗
02/10/2023321469683Open ↗
09/30/2022321472143Open ↗
Showing 3 of 264 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW39
03/11/2025321472143Open ↗
02/16/2024321725068Open ↗
10/18/2023340794830Open ↗
Showing 3 of 9 on file for this type
▸Filing & Intake Forms343
▸BISEFILING COVER SHEET146
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 146 on file for this type
▸BISADDITIONAL INFORMATION105
04/14/2023321469683Open ↗
07/27/2022321465525Open ↗
09/15/2021321543512Open ↗
Showing 3 of 105 on file for this type
▸BISBOROUGH INTAKE FORM81
02/17/2021340511315Open ↗
Showing 1 of 81 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET11
01/28/2021340797472Open ↗
12/16/2020340794830Open ↗
12/14/2020340794723Open ↗
Showing 3 of 11 on file for this type
▸Other Documents31
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISLAA - Supporting Documentation4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISFEE EXEMPTION DOCUMENTATION2
12/16/2020340794830Open ↗
Showing 1 of 2 on file for this type
▸BISSD/SP FIRE PUMP TEST : FP-862
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWSite Survey: Initial2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWManufacturer's Specifications2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWCalculations2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlot Diagram2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWWaiver Document1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type