| Owner | Filings | Most Recent |
|---|---|---|
| CBRE | 596 | 03/21/2026 |
| JLL | 94 | 03/22/2026 |
| Jones Lang Lasalle | 29 | 07/08/2026 |
| HIR REAL ESTATE | 6 | 03/21/2026 |
| M BHUIYAN CONSTRUCTION C | 4 | 03/21/2026 |
| Mount Sinai Health System | 3 | 04/09/2026 |
| MOUNT SINAI QUEENS | 3 | 03/22/2026 |
| RXR REALTY | 2 | 09/13/2026 |
| CRAVER CORP | 2 | 03/21/2026 |
| STARBUCKS | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NEW YORK DESIGN ARCHITECTS, LLP | 2 | 08/10/2026 |
| VOCON | 1 | 07/28/2025 |
| PATTI & ANTHES CONSULTING ENGINEERS | 3 | 07/24/2025 |
| SEVERUD ASSOCIATES | 1 | 02/11/2025 |
| HLW INTERNATIONAL | 2 | 12/10/2023 |
| POLISE CONSULTING ENGINEER | 2 | 02/20/2023 |
| DESIGN REPUBLIC | 1 | 02/16/2023 |
| THOMAS VELTRE P.E., P.C. | 1 | 10/27/2022 |
| VIRALINE ARCHITECTURE LLP | 2 | 03/21/2022 |
| MOROZOV | 3 | 01/07/2022 |
| ROBERT DERECTOR ASSOCIATES | 7 | 01/02/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| RIZZO GROUP | 4 | 03/21/2026 |
| HS DESIGN STUDIO | 2 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 2 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 8 | 03/21/2026 |
| DVA Advisors | 4 | 03/21/2026 |
| EA DESIGN GROUP | 2 | 03/21/2026 |
| J CALLAHAN CONSULTING | 10 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RXR CONSTRUCTION SERV LLC | General Contractor | 9 | 07/08/2026 |
| JOHN GALLIN & SON, INC | General Contractor | 4 | 07/08/2026 |
| KING ROSE OF NY, INC | General Contractor | 4 | 07/08/2026 |
| PHILIP GOEHRING | Electrical | 4 | 03/21/2026 |
| UNITY CONSTRUCTION GROUP | General Contractor | 3 | 07/08/2026 |
| LEVINE, GEORGE | Fire Protection | 2 | 03/21/2026 |
| KABACK SERVICE, INC | General Contractor | 2 | 03/21/2026 |
| LAB PLBG & HTG CO INC | Plumbing | 2 | 07/08/2026 |
| RAEL AUTOMATIC SPR.CO INC | Fire Protection | 2 | 06/28/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 2 | 07/08/2026 |
| NICHOLAS STEFANOU | Electrical | 2 | 03/21/2026 |
| HENEGAN CONSTRUCTION CO., | General Contractor | 2 | 03/21/2026 |
| LCS PLUMBING&CONSULT INC | Plumbing | 1 | 07/08/2026 |
| MJH ENERGY CONSULTING INC | Plumbing | 1 | 07/08/2026 |
| BERTIE, ROBERT | Electrical | 1 | 03/21/2026 |
| PSI PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| CARBONE JOHN | Electrical | 1 | 03/21/2026 |
| FIVE STAR PLUMB & HEATING | Electrical | 1 | 03/21/2026 |
| JAIME, WILTON | Electrical | 1 | 03/21/2026 |
| JOHN CARBONE | Electrical | 1 | 03/21/2026 |
| SMALLS ELEC'L CONSTR. INC | Electrical | 1 | 03/22/2026 |
| ACCURATE MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| AGGRESSIVE FIRE PROT LLC | Fire Protection | 1 | 07/08/2026 |
| ABSOLUTE FIRE BARRIER SE* | General Contractor | 1 | 04/09/2026 |
| CAULDWELL WINGATE CO LLC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AKS ARCHITECTURAL & ENGIN | 1957 | 1 | 08/10/2026 |
| CODEGREEN | 510 | 4 | 07/28/2025 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 1 | 02/11/2025 |
| MILROSE CONSULTANTS LLC | 2003 | 2 | 02/20/2023 |
| THOMAS VELTRE, P.E, P.C. | 459 | 1 | 10/27/2022 |
| ALTERA ENGINEERING | 2646 | 2 | 01/07/2022 |
| ALAN MARGOLIN & ASSOC | 423 | 6 | 01/02/2020 |
| BEYOND ARCH LLC | 3600 | 2 | 12/04/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | RXR CONSTRUCTION SERV LLC | 04/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | RXR CONSTRUCTION SERV LLC | 04/01/2026 |
| DOB NOW | General Construction | Permit Issued | RXR CONSTRUCTION SERV LLC | 08/13/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | RXR CONSTRUCTION SERV LLC | 08/12/2025 |
| DOB NOW | Sprinklers | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 08/07/2025 |
| DOB NOW | Sprinklers | Permit Issued | RAEL AUTOMATIC SPR.CO INC | 08/07/2025 |
| DOB NOW | Plumbing | Signed-off | MJH ENERGY CONSULTING INC | 08/07/2025 |
| DOB NOW | General Construction | Permit Issued | RXR CONSTRUCTION SERV LLC | 08/07/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | CENTRAL CONSTRUCTION MGMT | 04/04/2025 |
| DOB NOW | Structural | Signed-off | ABSOLUTE FIRE BARRIER SE* | 03/20/2025 |
| DOB NOW | General Construction | Signed-off | JOHN GALLIN SON | 09/07/2023 |
| DOB NOW | General Construction | Signed-off | JOHN GALLIN SON | 04/14/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ACCURATE MECHANICAL INC | 04/13/2023 |
| DOB NOW | General Construction | Signed-off | ATTENTION TO DETAIL P&H.I | 04/10/2023 |
| DOB NOW | General Construction | Signed-off | HENEGAN CONSTRUCTION CO., | 03/14/2023 |
| DOB NOW | General Construction | Signed-off | UNITY CONSTRUCTION GROUP | 02/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | UNITY CONSTRUCTION GROUP | 02/21/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | KABACK SERVICE | 10/28/2022 |
| DOB NOW | Plumbing | Signed-off | PSI PLUMBING INC | 01/29/2022 |
| DOB NOW | Sprinklers | Signed-off | AGGRESSIVE FIRE PROT LLC | 01/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KING ROSE OF NY, INC | 01/21/2022 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 01/21/2022 |
| DOB NOW | Plumbing | Signed-off | LAB PLBG & HTG CO INC | 03/19/2021 |
| DOB NOW | Mechanical Systems | Signed-off | JOHN GALLIN SON | 08/28/2020 |
| DOB NOW | Sprinklers | Signed-off | ABCO-PEERLESS SPRKLR CORP | 12/04/2019 |
| DOB NOW | Mechanical Systems | Signed-off | CAULDWELL WINGATE CO LLC | 08/19/2019 |
| DOB NOW | Plumbing | Signed-off | LAB PLBG & HTG CO INC | 08/14/2019 |
| DOB NOW | Sprinklers | Signed-off | ABCO-PEERLESS SPRKLR CORP | 08/09/2019 |
| BIS | OT | ISSUED | OCEAN PACIFIC INTERIORS * | 02/17/2021 |
| BIS | OT | ISSUED | JOHN GALLIN & SON, INC | 08/20/2020 |
| BIS | OT | ISSUED | OCEAN PACIFIC INTERIORS * | 08/12/2020 |
| BIS | OT | ISSUED | JOHN GALLIN & SON, INC | 11/26/2019 |
| BIS | SP | ISSUED | TOWER FIRE PROTECTION INC | 11/06/2019 |
| BIS | OT | ISSUED | CAULDWELL WINGATE CO LLC | 10/02/2019 |
| BIS | OT | ISSUED | JOHN GALLIN & SON, INC | 09/23/2019 |
| BIS | MH | ISSUED | JT MAGEN & COMPANY INC | 11/13/2018 |
| BIS | OT | ISSUED | JT MAGEN & COMPANY INC | 11/08/2018 |
| BIS | OT | ISSUED | CORE STATES CONSTRUCTION | 10/23/2018 |
| BIS | PL | ISSUED | ASHLAND PLUMBING CORP | 04/17/2018 |
| BIS | SP | ISSUED | SIRINA FIRE PROT CORP | 04/17/2018 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/10/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool Trane GEHK15031 13 tons ×1 |
| 10/09/2019 | — | — | Associated Ducts and Piping | Ducts & Piping Ruskin IBD2 1 tons ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2022 | Signed-off | AGGRESSIVE FIRE PROT LLC | 6 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | — | — | Water/Sanitary |
| 08/05/2019 | Signed-off | LAB PLBG & HTG CO INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2025 | Permit Issued | KLEINKNECHT ELEC. CO.,INC | General Wiring |
| 07/02/2024 | Complete | THANASI ELECTRICAL, LLC | General Wiring |
| 03/01/2024 | Complete | P.E. STONE INC | General Wiring |
| 04/25/2023 | Permit Issued | SMALLS ELEC'L CONSTR. INC | 1 meters, 1 new_meters |
| 04/24/2023 | Complete | P.E. STONE INC | General Wiring |
| 04/11/2023 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 03/08/2023 | Complete | CEDAR ELEC'L CONT'RS INC. | — |
| 01/31/2023 | Complete | KYL ELECTRIC LLC | General Wiring |
| 05/04/2021 | Complete | NEE ELECTRICAL, LLC | General Wiring |
| 06/19/2020 | Permit Issued | APPROVED ELECTRIC CORP. | General Wiring |
| 04/28/2020 | Permit Issued | H. & L. ELECTRIC INC | General Wiring |
| 02/12/2020 | Complete | DEMAND ELECTRIC INC | — |
| 10/25/2019 | Complete | DEMAND ELECTRIC INC | — |
| 08/13/2019 | Permit Issued | PREMIER ELECTRIC, INC | General Wiring |
| 06/26/2019 | Permit Issued | FREEDOM ELECTL & DATA INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Permit Issued | CENTRAL CONSTRUCTION MGMT | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/08/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/16/2026 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 03/03/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/03/2026 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 02/24/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/24/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/24/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/24/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 10/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/10/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/03/2023 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 07/20/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/17/2023 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/08/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/06/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/05/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/11/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/09/2025 | Sprinkler Systems | HATIM ELSAID | special |
| 07/09/2025 | Post-installed Anchors | HATIM ELSAID | special |
| 07/09/2025 | Fire-Resistant Penetrations and Joints | HATIM ELSAID | special |
| 07/09/2025 | Standpipe Systems | HATIM ELSAID | special |
| 07/07/2025 | Mechanical Systems | HATIM ELSAID | special |
| 07/07/2025 | Final | HATIM ELSAID | progress |
| 07/07/2025 | Post-installed Anchors | HATIM ELSAID | special |
| 07/07/2025 | Post-installed Anchors | HATIM ELSAID | special |
| 07/07/2025 | Fire-Resistant Penetrations and Joints | HATIM ELSAID | special |
| 01/22/2025 | Structural Steel - Welding | JONAR MADRIAGA | special |
| 01/22/2025 | Final | JONAR MADRIAGA | progress |
| 01/22/2025 | Post-installed Anchors | JONAR MADRIAGA | special |
| 01/22/2025 | Structural Steel - High Strength Bolting | JONAR MADRIAGA | special |
| 01/22/2025 | Structural Steel - Details | JONAR MADRIAGA | special |
| 12/12/2023 | Final | Lisa Knip | progress |
| 11/13/2023 | Final | Lisa Knip | progress |
| 02/08/2023 | Final | Christopher Drutjons | progress |
| 06/08/2022 | Mechanical Systems | Thomas Veltre | special |
| 06/08/2022 | Final | Thomas Veltre | progress |
| 03/23/2022 | Final | James Vira | progress |
| 03/11/2022 | Final | James Vira | progress |
| 11/19/2021 | Sprinkler Systems | Dmitriy Morozov | special |
| 11/19/2021 | Fire-Resistant Penetrations and Joints | Dmitriy Morozov | special |
| 01/03/2020 | HVAC and service water heating equipment | Young Suh | energy_progress |
| 01/03/2020 | Smoke Control Systems Testing | Young Suh | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Starbucks | Restaurant / Food Service | Floor 1 | Project M01436982 Project M01436993 |
| Wells Fargo | Office | Floors 15, 16, 18, 24–27, 31, 32, 35–42 | Project M00818613 |
| UniCredit | Office | Floors 29, 30 | Project M00823389 Project M00823414 Project M00823383 |