150 MONROE STREET
BROOKLYN · BIN 3051302
💬 Discuss this project
1899Year Built
3Stories
C0Building Class
R6BZoning
3,600 sfGross Floor Area
3Units
Rent Stabilized7 Open Violations ▸
Three families · Owner of record: 150 MONROE LLC · 1,980 sf lot · 1.82 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalFire Protection
Floor 37p · 3 filings · 20 docs
Floor 22p · 1 filing · 17 docs
Floor 13p · 2 filings · 20 docs
Cellar5p · 3 filings · 20 docs
Sub-Basement2p · 1 filing · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
521 BROADWAY GROUP1209/14/2026
150 MONROE LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/11/2025$1.8M—Private party → 150 MONROE LLC$500/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STRUCTURAL ENGINEERING INTEGRATED105/06/2026
ADAL ENGINEERING PLLC512/30/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MK MANAGMENT AND MAINTENANCEGeneral Contractor407/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ADAL ENGINEERING PLLC4205210/29/2025
Building Lifecycle
All (70)Filed (6)Permit Issued (2)Violation (19)Objection (25)Special Inspection (18)
07/27/2026
Objection resolved — Resolved
07/27/2026
Objection resolved — Resolved
07/09/2026
Objection resolved — Resolved
06/22/2026
Objection resolved — Resolved
06/22/2026
Objection resolved — Resolved
06/22/2026
Objection resolved — Resolved
05/20/2026
Objection raised — Scope
05/20/2026
Objection raised — Scope
05/19/2026
Objection raised — Scope
05/19/2026
Objection raised — Scope
05/19/2026
Objection raised — Scope
05/19/2026
Objection raised — Scope
05/06/2026
Filed — Alteration CO
FOUNDATION WORK FOR ENLARGEMENT OF THE EXISTING BUILDING AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01288778-S1
01/30/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
01/30/2026
Special inspection requirement — Concrete - Cast-In-Place
01/30/2026
Special inspection requirement — Subgrade Inspections
01/30/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
01/13/2026
Special inspection requirement — Final
01/13/2026
Special inspection requirement — Footing and Foundation
12/30/2025
Filed — Alteration
B01314888-I1
12/09/2025
Objection resolved — Addressed
12/09/2025
Objection resolved — Addressed
12/09/2025
Objection resolved — Addressed
12/09/2025
Objection resolved — Addressed
12/09/2025
Objection resolved — Addressed
11/19/2025
Violation issued (HPD, closed)
I
11/18/2025
Objection raised — Zoning
11/18/2025
Objection raised — Zoning
11/18/2025
Objection raised — Scope
11/18/2025
Objection raised — Scope
11/18/2025
Objection raised — Cost
11/18/2025
Objection raised — Zoning
11/18/2025
Objection raised — Fire_Protection
11/18/2025
Objection raised — Zoning
10/31/2025
Filed — Alteration CO
FOUNDATION WORK FOR ENLARGEMENT OF THE EXISTING BUILDING AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01288778-I1
10/31/2025
Special inspection requirement — Final
Dariusz Makara
10/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dariusz Makara
10/31/2025
Special inspection requirement — Energy Code Compliance Inspections
Dariusz Makara
10/29/2025
Filed — Alteration
Interior demolition of exist 3 fam building cell, basement, 1st 2nd and 3rd floor to include removal of fit outs and non-load bearing partitions as per plans attached herewith. No change in use, egress and occupancy.
B01188575-P1
07/31/2025
Special inspection requirement — Energy Code Compliance Inspections
Dariusz Makara
07/31/2025
Special inspection requirement — Lighting controls
Dariusz Makara
07/31/2025
Special inspection requirement — Insulation placement and R values
Dariusz Makara
07/31/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Dariusz Makara
07/31/2025
Special inspection requirement — Interior lighting power
Dariusz Makara
07/31/2025
Special inspection requirement — Lighting in dwelling units
Dariusz Makara
07/31/2025
Special inspection requirement — Final
Dariusz Makara
07/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dariusz Makara
07/14/2025
Permit issued — General Construction
B01188575-S3-GC
07/02/2025
Filed — Alteration
Interior demolition of exist 3 fam building cell, basement, 1st 2nd and 3rd floor to include removal of fit outs and non-load bearing partitions as per plans attached herewith. No change in use, egress and occupancy.
B01188575-S3
06/10/2025
Violation issued (HPD, closed)
A
04/01/2025
Permit issued — General Construction
B01188575-I1-GC
03/28/2025
Filed — Alteration
Interior demolition of exist 3 fam building cell, basement, 1st 2nd and 3rd floor to include removal of fit outs and non-load bearing partitions as per plans attached herewith. No change in use, egress and occupancy.
B01188575-I1
03/03/2025
Special inspection requirement — Final
Dariusz Makara
04/11/2024
Violation issued (HPD, closed)
A
11/20/2023
Violation issued (HPD, closed)
I
03/24/2023
Violation issued (HPD, closed)
A
11/09/2022
Violation issued (HPD, closed)
I
03/01/2022
Violation issued (HPD, closed)
I
03/01/2022
Violation issued (HPD, closed)
A
04/12/2021
Violation issued (HPD, closed)
I
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMK MANAGMENT AND MAINTENA07/14/2025
DOB NOWGeneral ConstructionPermit IssuedMK MANAGMENT AND MAINTENA04/01/2025
1 project · most recent 12/19/2025
General Wiring
FiledStatusContractorScope
12/19/2025Permit IssuedEXECUTIVE ELECTL SER INCGeneral Wiring
1 project · most recent 05/06/2026
FiledStatusContractorScope
05/06/2026——2 scope_items
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
01/30/2026Structural Stability – Alterations of existing buildings—special
01/30/2026Concrete - Cast-In-Place—special
01/30/2026Subgrade Inspections—special
01/30/2026Subsurface Investigations (Borings/Test Pits)—special
01/13/2026Final—progress
01/13/2026Footing and Foundation—progress
10/31/2025FinalDariusz Makaraprogress
10/31/2025Fire-Resistant Penetrations and JointsDariusz Makaraspecial
10/31/2025Energy Code Compliance InspectionsDariusz Makaraprogress
07/31/2025Energy Code Compliance InspectionsDariusz Makaraprogress
07/31/2025Lighting controlsDariusz Makaraenergy_progress
07/31/2025Insulation placement and R valuesDariusz Makaraenergy_progress
07/31/2025Fenestration and door U-factor and product ratingsDariusz Makaraenergy_progress
07/31/2025Interior lighting powerDariusz Makaraenergy_progress
07/31/2025Lighting in dwelling unitsDariusz Makaraenergy_progress
07/31/2025FinalDariusz Makaraprogress
07/31/2025Fire-Resistant Penetrations and JointsDariusz Makaraspecial
03/03/2025FinalDariusz Makaraprogress
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/21/2026B01188575-P1Request digital key ↗
08/21/2026B01188575-I1Request digital key ↗
08/21/2026B01188575-S3Request digital key ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/17/2026B01288778-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01288778-I1Open ↗
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature6
09/19/2026B01188575-I1Open ↗
08/26/2026B01188575-S3Open ↗
08/26/2026B01188575-S3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/21/2026B01188575-S3Open ↗
08/21/2026B01188575-P1Open ↗
08/21/2026B01188575-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026B01188575-S3Open ↗
08/23/2026B01188575-P1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026B01288778-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/21/2026B01188575-S3Open ↗
08/21/2026B01188575-P1Open ↗
08/21/2026B01188575-I1Open ↗
Showing 3 of 6 on file for this type
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/14/2026B01288778-S1Open ↗
▸DOB NOWSOIL REPORT1
08/14/2026B01288778-S1Open ↗
▸Other Documents5
▸DOB NOWProperty Ownership Certification1
08/13/2026B01288778-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01288778-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01288778-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/20/2026B01288778-S1Open ↗
▸DOB NOWPlot Diagram1
08/14/2026B01288778-S1Open ↗