💬 Discuss this project
1964Year Built
1Stories
Q1Building Class
PARKZoning
58,219 sfGross Floor Area
0Units
LL97 Covered0 Active Violations
Parks / recreation facility · Owner of record: NYC Department of Parks and Recreation · 106,440 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofLincoln Center, Big Apple CircusUnder Construction69p · 8 filings · 17 docs
Floor 2Lincoln CenterUnder Construction1p · 2 filings · 16 docs
Floor 1Lincoln CenterUnder Construction41p · 9 filings · 16 docs
MezzanineLincoln Center1 filing · 20 docs
CellarLincoln CenterUnder Construction11p · 3 filings · 17 docs
Site & exteriorLincoln Center, Big Apple Circus +186p · 30 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Lincoln Center9107/08/2026
NYC Department of Parks and Recreation5610/20/2026
Target403/21/2026
Big Apple Circus203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Moody Nolan508/25/2026
Sherwood Design Engineers508/25/2026
SYNC Architecture3605/05/2026
Exdem Engineering Services504/01/2026
Thornton Tomasetti402/22/2026
Legacy Engineers402/05/2026
ADG Architecture and Design209/11/2023
Andrew Formichella501/06/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Milrose Consultants2603/21/2026
Municipal Building Consultants1803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Arena Event ServicesGeneral Contractor1907/08/2026
Turner Construction CompanyGeneral Contractor810/20/2026
Winick ProductionsGeneral Contractor507/08/2026
Titan Industrial ServiceScaffold307/08/2026
NYFF EventsGeneral Contractor303/21/2026
Titan Industrial ServiceGeneral Contractor207/08/2026
Aspro PlumbingPlumbing109/22/2026
H. & L. ElectricElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LMW Engineering Group279804/01/2026
Socotec Engineering4983302/22/2026
Building Lifecycle
All (265)Filed (69)Permit Issued (30)Signed Off (7)Violation (53)Objection (76)Special Inspection (30)
10/19/2026
Permit issued — General Construction
M01444704-I1-GC
10/13/2026
Signed off — Alteration
Filing herewith civil scope for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occupancy, or egress under this application.
M01314553-S1
10/13/2026
Signed off — Alteration
Filing herewith civil scope for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occupancy, or egress under this application.
M01314553-S2
10/09/2026
Permit issued — Earth Work
M01444704-S2-EA
10/08/2026
Signed off — Alteration
Filing herewith civil scope for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occupancy, or egress under this application.
M01314553-I1
10/01/2026
Signed off — Alteration
Use of mechanical demolition equipment during partial demolition, filed separately under M01299104-S3.
M01299104-S1
10/01/2026
Signed off — Alteration
Use of mechanical demolition equipment during partial demolition, filed separately under M01299104-S3.
M01299104-I1
09/21/2026
Permit issued — Plumbing
M01444704-S1-PL
09/16/2026
Objection resolved — Resolved
09/14/2026
Objection raised — Other
08/25/2026
Filed — Alteration
Filing herewith plumbing scope for replacement of CB grates and drains bodies; tie-ins are filed under separate application(not under this application). The scope proposed here is replacement in kind essentially. No change in use, occupancy, or egress.
M01444704-I1
08/25/2026
Filed — Alteration
Filing herewith plumbing scope for replacement of CB grates and drains bodies; tie-ins are filed under separate application(not under this application). The scope proposed here is replacement in kind essentially. No change in use, occupancy, or egress.
M01444704-S1
08/25/2026
Filed — Alteration
Filing herewith plumbing scope for replacement of CB grates and drains bodies; tie-ins are filed under separate application(not under this application). The scope proposed here is replacement in kind essentially. No change in use, occupancy, or egress.
M01444704-S2
08/14/2026
Special inspection requirement — Final
MARISA HARTE
08/12/2026
Special inspection requirement — Final
Renauld Mitchell
07/27/2026
Objection resolved — Resolved
07/22/2026
Objection raised — Scope
07/20/2026
Filed — Alteration
Filing herewith civil scope for erosion control (with details) for the final conditions of Damrosch Park as per plans.
M01299046-S2
07/20/2026
Filed — Alteration
Filing herewith civil scope for erosion control (with details) for the final conditions of Damrosch Park as per plans.
M01299046-S3
07/17/2026
Filed — Alteration
Filing herewith civil scope for erosion control (with details) for the final conditions of Damrosch Park as per plans.
M01299046-S6
07/17/2026
Filed — Alteration
Filing herewith civil scope for erosion control (with details) for the final conditions of Damrosch Park as per plans.
M01299046-I1
07/01/2026
Special inspection requirement — Final
Renauld Mitchell
06/26/2026
Permit issued — Structural
M01299104-S3-GC-CX
06/24/2026
Special inspection requirement — Final
05/14/2026
Permit issued — Structural
M01349551-S1-GC-CX
05/11/2026
Permit issued — Protection and Mechanical Methods
M01349551-S2-PMM
05/07/2026
Permit issued — General Construction
M01396937-I1-GC
05/05/2026
Filed — No Work
M01397541-I1
05/04/2026
Filed — Alteration
Temporary structures for a groundbreaking ceremony at Damrosch Park. Removed at the end of the programing. No changes to existing structures, use or egress.
M01396937-I1
04/21/2026
Objection resolved — Addressed
04/20/2026
Permit issued — General Construction
M01299104-I1-GC
04/15/2026
Permit issued — Structural
M01349551-I1-ST
04/09/2026
Objection resolved — Resolved
04/02/2026
Permit issued — Protection and Mechanical Methods
M01299104-S4-PMM
04/01/2026
Filed — Alteration
Mechanical Demo Equipment for use during partial interior demo and slab cut (plaza level only) as per plans.
M01349551-S2
04/01/2026
Filed — Alteration
Use of mechanical demolition equipment during partial demolition, filed separately under M01299104-S3.
M01299104-S4
04/01/2026
Filed — Alteration
Mechanical Demo Equipment for use during partial interior demo and slab cut (plaza level only) as per plans.
M01349551-S1
04/01/2026
Filed — Alteration
Use of mechanical demolition equipment during partial demolition, filed separately under M01299104-S3.
M01299104-S3
03/27/2026
Special inspection requirement — Demolition
Jieming Wang
03/27/2026
Special inspection requirement — Demolition
Jieming Wang
03/25/2026
Objection resolved — Resolved
03/25/2026
Objection resolved — Resolved
03/25/2026
Objection resolved — Resolved
03/25/2026
Objection resolved — Resolved
03/25/2026
Objection resolved — Resolved
03/25/2026
Objection resolved — Resolved
03/25/2026
Special inspection requirement — Final
Sagar Beharry
03/19/2026
Objection raised — Other
03/19/2026
Objection raised — Other
03/19/2026
Objection raised — Other
03/16/2026
Permit issued — Protection and Mechanical Methods
M01314553-S3-PMM
03/13/2026
Filed — Alteration
Filing herewith civil scope for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occupancy, or egress under this application.
M01314553-S3
03/10/2026
Objection resolved — Resolved
03/10/2026
Objection resolved — Resolved
03/10/2026
Objection resolved — Resolved
03/10/2026
Objection resolved — Resolved
03/10/2026
Objection resolved — Resolved
03/09/2026
Permit issued — Structural
M01299104-S1-ST
03/09/2026
Objection resolved — Resolved
03/09/2026
Objection resolved — Resolved
Latest 60 of 265 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedTurner Construction Company10/19/2026
DOB NOWEarth WorkPermit IssuedTurner Construction Company10/09/2026
DOB NOWPlumbingPermit IssuedAspro Plumbing09/21/2026
DOB NOWStructuralSigned-offTitan Industrial Service06/26/2026
DOB NOWStructuralPermit IssuedTitan Industrial Service05/14/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedTitan Industrial Service05/11/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions05/07/2026
DOB NOWGeneral ConstructionSigned-offTurner Construction Company04/20/2026
DOB NOWStructuralPermit IssuedTurner Construction Company04/15/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedTitan Industrial Service04/02/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedTitan Industrial Service03/16/2026
DOB NOWStructuralSigned-offTurner Construction Company03/09/2026
DOB NOWEarth WorkSigned-offTurner Construction Company03/02/2026
DOB NOWGeneral ConstructionSigned-offTurner Construction Company02/26/2026
DOB NOWGeneral ConstructionSigned-offTurner Construction Company02/26/2026
DOB NOWGeneral ConstructionPermit IssuedArena Event Services10/07/2025
DOB NOWGeneral ConstructionPermit IssuedWinick Productions08/27/2025
DOB NOWGeneral ConstructionPermit IssuedArena Event Services05/06/2025
DOB NOWGeneral ConstructionPermit IssuedArena Event Services01/23/2025
DOB NOWGeneral ConstructionSigned-offWinick Productions03/01/2024
DOB NOWGeneral ConstructionPermit IssuedArena Event Services10/12/2023
DOB NOWGeneral ConstructionSigned-offNYFF Events09/07/2023
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/09/2023
DOB NOWGeneral ConstructionPermit IssuedWinick Productions10/15/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services10/06/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/08/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/08/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services10/21/2021
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/09/2021
DOB NOWGeneral ConstructionPermit IssuedArena Event Services03/29/2021
BISOTISSUEDBig Top Works10/09/2018
BISOTISSUEDLincoln Center for the PE06/29/2018
BISOTISSUEDBig Top Works10/05/2017
BISOTISSUEDArena Event Services08/31/2017
BISOTISSUEDArena Event Services08/24/2017
BISOTISSUEDLincoln Center for the PE07/18/2017
BISOTISSUEDLincoln Center for the PE07/14/2017
BISOTISSUEDArena Event Services04/03/2017
BISOTISSUEDArena Event Services08/26/2016
BISOTISSUEDLincoln Center for the PE07/15/2016
+ 40 more permits on file
1 project · most recent 02/22/2026
Sprinkler System
FiledStatusContractorScope
02/22/2026——Sprinkler System
3 projects · most recent 08/25/2026
Storm Water/Sanitary
FiledStatusContractorScope
08/25/2026Permit IssuedAspro PlumbingStorm
07/20/2026——Storm
02/22/2026——Storm, Water/Sanitary
5 projects · most recent 10/14/2025
FiledStatusContractorScope
10/14/2025CompleteH. & L. Electric—
10/07/2024CompleteH. & L. Electric—
10/13/2023CompleteH. & L. Electric—
10/04/2019CompleteH. & L. Electric—
10/10/2018CompleteH & L Electric—
5 projects · most recent 08/25/2026
Steel Concrete
FiledStatusContractorScope
08/25/2026Permit IssuedTurner Construction Company3 scope_items
04/01/2026Permit IssuedTitan Industrial Service2 scope_items
04/01/2026Signed-offTitan Industrial Service4 scope_items
03/13/2026Permit IssuedTitan Industrial Service1 scope_items
02/22/2026——Steel, Concrete
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
08/14/2026FinalMARISA HARTEprogress
08/12/2026FinalRenauld Mitchellprogress
07/01/2026FinalRenauld Mitchellprogress
06/24/2026Final—progress
03/27/2026DemolitionJieming Wangspecial
03/27/2026DemolitionJieming Wangspecial
03/25/2026FinalSagar Beharryprogress
02/26/2026DemolitionJieming Wangspecial
01/21/2026FinalJieming Wangprogress
01/21/2026Structural Stability – Alterations of existing buildingsJieming Wangspecial
11/05/2025Finaljason loiselleprogress
11/05/2025FinalJieming Wangprogress
11/05/2025FinalRenauld Mitchellprogress
11/05/2025FinalANDY ENGLER ROTHprogress
11/03/2025FinalANDY ENGLER ROTHprogress
10/07/2025FinalJieming Wangprogress
10/07/2025Structural Stability – Alterations of existing buildingsJieming Wangspecial
10/03/2025Seismic Isolation SystemsMARISA HARTEspecial
10/03/2025Fire-Resistant Penetrations and JointsMARISA HARTEspecial
09/24/2025FinalMARISA HARTEprogress
09/24/2025Standpipe SystemsMARISA HARTEspecial
09/24/2025Sprinkler SystemsMARISA HARTEspecial
09/23/2025FinalMARISA HARTEprogress
09/23/2025Mechanical SystemsMARISA HARTEspecial
04/02/2024FinalANDY ENGLER ROTHprogress
Latest 25 of 33.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Lincoln CenterArts / Culture / EntertainmentCellar, Floors 1, 2, Mezzanine, Roof
Project M01396937 Alteration · Permit Entire · 05/04/2026
Project M01276892 Alteration · Permit Entire · 08/25/2025
Project M01004440 Alteration · LOC Issued · 02/13/2024
Project M08014638 Alteration · Permit Entire · 10/04/2022
Project M08009257 Alteration · Permit Entire · 09/26/2022
Project M00483790 Alteration · Permit Entire · 03/11/2021
Project M01444704 Alteration · Permit Entire · 08/25/2026
Project M01299046 Alteration · Approved · 07/17/2026
Project M01299104 Alteration · Permit Entire · 02/13/2026
Project M01349551 Alteration · Permit Entire · 02/13/2026
Project M01270728 Alteration · Objections · 01/29/2026
Project M01314553 Alteration · Permit Entire · 12/04/2025
Nike- Only BasketballRetail—
Project M00925735 Alteration · LOC Issued · 08/31/2023
Big Apple CircusArts / Culture / Entertainment—
Project M00607864 Alteration · Permit Entire · 10/07/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 798 on file (BIS + DOB NOW)
▸Plans & Drawings66
▸DOB NOWPlans/Sketch38
09/03/2026M00483790-P2Request digital key ↗
09/03/2026M00483790-I1Request digital key ↗
09/03/2026M00483790-P1Request digital key ↗
Showing 3 of 38 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly28
09/05/2026M00166658-I1Request digital key ↗
09/05/2026M00170339-I1Request digital key ↗
09/05/2026M00178431-I1Request digital key ↗
Showing 3 of 28 on file for this type
▸Applications & Permits122
▸BISWORK PERMIT APPLICATION61
09/23/2019123744902Open ↗
10/09/2018123187773Open ↗
06/29/2018122830838Open ↗
Showing 3 of 61 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION61
04/14/2023122830838Open ↗
04/12/2023123744902Open ↗
04/07/2023123744902Open ↗
Showing 3 of 61 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications260
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION86
12/09/2019123187773Open ↗
12/09/2019123187773Open ↗
09/17/2019123744902Open ↗
Showing 3 of 86 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature66
09/05/2026M00166658-I1Open ↗
09/05/2026M00178431-I1Open ↗
09/05/2026M00291510-I1Open ↗
Showing 3 of 66 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST38
09/17/2019123744902Open ↗
10/05/2017123187773Open ↗
07/26/2017123333721Open ↗
Showing 3 of 38 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM26
08/16/2013121746922Open ↗
Showing 1 of 26 on file for this type
▸DOB NOWProgress Inspector Seal & Signature19
09/26/2026M00483790-P3Open ↗
09/23/2026M01444704-I1Open ↗
09/23/2026M01349551-I1Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT16
09/17/2019123744902Open ↗
10/05/2017123187773Open ↗
07/26/2017123333721Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/23/2026M01349551-I1Open ↗
09/19/2026M01299104-S1Open ↗
08/29/2026M01349551-S1Open ↗
Showing 3 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSELF-CERT PLUMBING NOTICE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISST-1 Street Tree Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTREET TREE SUPPORTING DOCUMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos41
▸DOB NOWDEP ACP-5: Asbestos Assessment Report22
08/26/2026M01444704-I1Open ↗
08/26/2026M01444704-S2Open ↗
08/26/2026M01444704-S1Open ↗
Showing 3 of 22 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISASBESTOS-CERTIFICATION (DEP ACP5)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
08/15/2013140106702Open ↗
▸Inspections & Test Reports15
▸BISTECHNICAL REPORT: RESPONSIBILITY12
04/14/2023122830838Open ↗
04/13/2023123744902Open ↗
04/07/2023123744902Open ↗
Showing 3 of 12 on file for this type
▸BISConcrete Design Mix - 2008 CODE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs158
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter59
09/03/2026M00524774-I1Open ↗
09/03/2026M00622345-I1Open ↗
09/03/2026M00639401-I1Open ↗
Showing 3 of 59 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST37
04/14/2023123744902Open ↗
12/22/2020122876156Open ↗
11/24/2020123061916Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)26
08/26/2026M01444704-I1Open ↗
08/26/2026M01444704-S2Open ↗
08/26/2026M01444704-S1Open ↗
Showing 3 of 26 on file for this type
▸BISADMINISTRATIVE OBJECTIONS23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION12
09/09/2016122876156Open ↗
06/17/2014120451849Open ↗
Showing 2 of 12 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership56
▸BISCOST AFFIDAVIT56
08/07/2015120411358Open ↗
10/28/2014122090003Open ↗
09/25/2014120462935Open ↗
Showing 3 of 56 on file for this type
▸Filing & Intake Forms53
▸BISEFILING COVER SHEET41
09/17/2019123744902Open ↗
10/05/2017123187773Open ↗
07/26/2017123333721Open ↗
Showing 3 of 41 on file for this type
▸BISADDITIONAL INFORMATION7
09/17/2019123744902Open ↗
10/12/2018123187773Open ↗
07/26/2017123333721Open ↗
Showing 3 of 7 on file for this type
▸BISeFiling Job Application Cover Sheet3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISBOROUGH INTAKE FORM2
12/09/2019123187773Open ↗
10/04/2017123333721Open ↗
▸Other Documents16
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION6
10/04/2017123333721Open ↗
08/15/2013140106702Open ↗
Showing 2 of 6 on file for this type
▸DOB NOWPlot Diagram2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPARTIAL DEMO: 10-DAY Notice2
08/18/2026M01299104-S3Open ↗
08/13/2026M01299104-S1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWProof of Historic Building1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWSite Survey: Initial1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWAdjoining Owners Notification1
08/13/2026M01314553-S1Open ↗