← Back
Primarily 2 family with 1 store or office
155 WYTHE AVENUE
BROOKLYN · Williamsburg · BIN 3062047
💬 Discuss this project
1899Year Built
3Stories
S2Building Class
M1-2/R6AZoning
3,109 sfGross Floor Area
3Units
Rent Stabilized7 Open Violations ▸FDNY Report ↗
Primarily 2 family with 1 store or office · 2,500 sf lot · 1.24 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof3p · 2 filings · 20 docs
Penthouse2p · 1 filing · 20 docs
Floor 34p · 2 filings · 20 docs
Floor 24p · 4 filings · 20 docs
Floor 11p · 1 filing · 17 docs
Cellar6p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
UMF CONTRACTING203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GCF CONSULTING ENGINEERS1111/21/2025
R.J. MCGEE ENGINEERING, PLLC109/11/2025
SPACECUTTER407/23/2025
RAS PE CONSULTING ENGINEERS202/24/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NEXUS CONSULTING NYC, INC1603/21/2026
PAUL FUSCO CONSULTING403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ISLAND INTERIORS DESIGNGeneral Contractor807/08/2026
EXPERT FIRE SPRINKLER,LLCFire Protection207/08/2026
DARBY CONSTRUCTION SVC LLGeneral Contractor207/08/2026
TRI CITY CONSTRUCTION CORGeneral Contractor107/08/2026
ARANDA PLBG & HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GFC CONSULTING ENGINEER P41271111/21/2025
METROPOLITAN MECHANICAL C2277209/11/2025
TRIANGLE INSPECTION & TES7495202/24/2025
Building Lifecycle
All (110)Filed (18)Permit Issued (13)Signed Off (7)Violation (19)Inspection (5)Objection (18)Special Inspection (30)
05/06/2026
Violation issued (HPD, open)
A
02/13/2026
Signed off — Alteration
Mechanical work associated with the renovation/conversion from 3 family 2 family residence with mix use, vertical and horizontal enlargement
B00651828-I1
11/24/2025
Objection raised — Other
11/24/2025
Objection resolved — Addressed
11/24/2025
Special inspection requirement — Final
Giap Flores
11/24/2025
Special inspection requirement — HVAC-R and service water heating equipment
Giap Flores
11/24/2025
Special inspection requirement — HVAC-R and service water heating system controls
Giap Flores
11/24/2025
Special inspection requirement — Maintenance information
Giap Flores
11/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Giap Flores
11/24/2025
Special inspection requirement — Mechanical Systems
Giap Flores
11/24/2025
Special inspection requirement — Shutoff dampers
Giap Flores
11/24/2025
Special inspection requirement — Duct leakage testing, insulation and design
Giap Flores
11/24/2025
Special inspection requirement — Fireplaces
Giap Flores
11/21/2025
Filed — Alteration
Mechanical work associated with the renovation/conversion from 3 family 2 family residence with mix use, vertical and horizontal enlargement
B00651828-P4
11/21/2025
Violation issued (HPD, closed)
I
11/10/2025
Special inspection requirement — Shutoff dampers
Giap Flores
11/10/2025
Special inspection requirement — Duct leakage testing, insulation and design
Giap Flores
11/10/2025
Special inspection requirement — Maintenance information
Giap Flores
11/10/2025
Special inspection requirement — HVAC-R and service water heating equipment
Giap Flores
11/10/2025
Special inspection requirement — Fireplaces
Giap Flores
11/10/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Giap Flores
11/10/2025
Special inspection requirement — Mechanical Systems
Giap Flores
11/10/2025
Special inspection requirement — HVAC-R and service water heating system controls
Giap Flores
11/10/2025
Special inspection requirement — Final
Giap Flores
09/30/2025
Signed off — Alteration
INTERIOR ALTERATIONS TO EXISTING GROUND FLOOR COMMERCIAL SPACE. NO CHANGE TO USE, OCCUPANCY OR EGRESS
B01256610-S1
09/29/2025
Signed off — Alteration
INTERIOR ALTERATIONS TO EXISTING GROUND FLOOR COMMERCIAL SPACE. NO CHANGE TO USE, OCCUPANCY OR EGRESS
B01256610-I1
09/15/2025
Permit issued — Mechanical Systems
B01256610-S1-MS
09/11/2025
Filed — Alteration
INTERIOR ALTERATIONS TO EXISTING GROUND FLOOR COMMERCIAL SPACE. NO CHANGE TO USE, OCCUPANCY OR EGRESS
B01256610-S1
09/03/2025
Special inspection requirement — Maintenance information
PATRICK MCDONALD
09/03/2025
Special inspection requirement — HVAC-R and service water heating system controls
PATRICK MCDONALD
09/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
PATRICK MCDONALD
09/03/2025
Special inspection requirement — Final
PATRICK MCDONALD
09/03/2025
Special inspection requirement — Post-installed Anchors
PATRICK MCDONALD
09/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PATRICK MCDONALD
09/03/2025
Special inspection requirement — Tenant Protection Plan Compliance
PATRICK MCDONALD
09/03/2025
Special inspection requirement — Mechanical Systems
PATRICK MCDONALD
08/19/2025
Objection resolved — Addressed
08/01/2025
Permit issued — General Construction
B01256610-I1-GC
07/28/2025
Special inspection requirement — Tenant Protection Plan Compliance
PATRICK MCDONALD
07/23/2025
Filed — Alteration
INTERIOR ALTERATIONS TO EXISTING GROUND FLOOR COMMERCIAL SPACE. NO CHANGE TO USE, OCCUPANCY OR EGRESS
B01256610-I1
07/16/2025
Special inspection requirement — Fire-Resistance Rated Construction
Alex Gil
07/16/2025
Special inspection requirement — Final
Alex Gil
07/16/2025
Special inspection requirement — Lighting controls
Alex Gil
07/10/2025
Signed off — Alteration
Installation of fence in front of property
B00640758-I1
07/08/2025
Signed off — Alteration
plumbing work associate with the vertical and horizontal enlargement of property, Change in dwelling units from 3 to 2.
B00644620-I1
06/11/2025
Violation issued (HPD, open)
A
04/11/2025
Filed — Alteration
plumbing work associate with the vertical and horizontal enlargement of property, Change in dwelling units from 3 to 2.
B00644620-P4
04/08/2025
Signed off — Alteration
STRUCTURAL WORK ASSOCIATED WITH THE VERTICAL AND HORIZONTAL ENLARGEMENT OF BUILDINGS.CHANGE IN OCCUPACNCY, EGRESS AND USE
B00409955-I1
04/01/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/24/2025
Filed — Alteration
STRUCTURAL WORK ASSOCIATED WITH THE VERTICAL AND HORIZONTAL ENLARGEMENT OF BUILDINGS.CHANGE IN OCCUPACNCY, EGRESS AND USE
B00409955-P1
02/12/2025
Objection resolved — Addressed
02/04/2025
Objection raised — Scope
01/30/2025
Filed — Alteration
plumbing work associate with the vertical and horizontal enlargement of property, Change in dwelling units from 3 to 2.
B00644620-P3
01/28/2025
Signed off — Alteration
SPRINKLER ASSOCIATED WITH VERTICAL AND HORIZONTAL ENLARGEMENT,
B00651883-I1
01/28/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/21/2024
Filed — Alteration
SPRINKLER ASSOCIATED WITH VERTICAL AND HORIZONTAL ENLARGEMENT,
B00651883-P2
12/11/2024
Objection resolved — Addressed
12/11/2024
Objection resolved — Addressed
12/11/2024
Objection resolved — Addressed
11/29/2024
Violation issued (HPD, closed)
I
Latest 60 of 110 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offDARBY CONSTRUCTION SVC LL09/15/2025
DOB NOWGeneral ConstructionSigned-offDARBY CONSTRUCTION SVC LL08/01/2025
DOB NOWSprinklersSigned-offEXPERT FIRE SPRINKLER,LLC06/06/2024
DOB NOWPlumbingSigned-offARANDA PLBG & HTG CORP05/13/2024
DOB NOWConstruction FenceSigned-offTRI CITY CONSTRUCTION COR03/22/2024
DOB NOWSprinklersSigned-offEXPERT FIRE SPRINKLER,LLC08/25/2023
DOB NOWStructuralSigned-offISLAND INTERIORS DESIGN06/20/2023
DOB NOWMechanical SystemsSigned-offISLAND INTERIORS DESIGN03/28/2023
DOB NOWMechanical SystemsSigned-offISLAND INTERIORS DESIGN01/17/2023
DOB NOWConstruction FenceSigned-offISLAND INTERIORS DESIGN12/30/2022
DOB NOWStructuralSigned-offISLAND INTERIORS DESIGN06/02/2022
DOB NOWMechanical SystemsSigned-offISLAND INTERIORS DESIGN01/16/2022
DOB NOWConstruction FenceSigned-offISLAND INTERIORS DESIGN12/10/2021
BIS—ISSUEDTRI CITY CONSTRUCTION COR12/05/2024
BIS—ISSUEDTRI CITY CONSTRUCTION COR10/07/2024
BIS—ISSUEDTRI CITY CONSTRUCTION COR01/08/2024
BIS—ISSUEDTRI CITY CONSTRUCTION COR01/08/2024
BIS—ISSUEDTRI CITY CONSTRUCTION COR12/14/2023
BIS—ISSUEDDFE CONTRACTOR LLC12/06/2023
BIS—ISSUEDDFE CONTRACTOR LLC12/06/2023
BIS—ISSUEDDFE CONTRACTOR LLC12/06/2023
BIS—ISSUEDISLAND INTERIORS DESIGN08/08/2023
BIS—ISSUEDISLAND INTERIORS DESIGN08/08/2023
BIS—ISSUEDISLAND INTERIORS DESIGN08/02/2022
BIS—ISSUEDISLAND INTERIORS DESIGN08/02/2022
BIS—ISSUEDISLAND INTERIORS DESIGN01/26/2022
BIS—ISSUEDISLAND INTERIORS DESIGN01/25/2022
BISEQISSUEDUMF CONTRACTING CORP11/19/2014
3 projects · most recent 08/13/2025
General Wiring
FiledStatusContractorScope
08/13/2025CompleteNASH ELECTRIC SERVICES INGeneral Wiring
02/20/2025CompleteLINPHILL ELEC'L CONTR.General Wiring
08/30/2023CompleteLINPHILL ELEC'L CONTR.General Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
04/01/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/28/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/04/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/22/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/22/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 66
DateRequirementInspectorRole
11/24/2025FinalGiap Floresprogress
11/24/2025Duct leakage testing, insulation and designGiap Floresenergy_progress
11/24/2025HVAC-R and service water heating equipmentGiap Floresenergy_progress
11/24/2025HVAC-R and service water piping design and insulationGiap Floresenergy_progress
11/24/2025FireplacesGiap Floresenergy_progress
11/24/2025Shutoff dampersGiap Floresenergy_progress
11/24/2025Maintenance informationGiap Floresenergy_progress
11/24/2025Mechanical SystemsGiap Floresspecial
11/24/2025HVAC-R and service water heating system controlsGiap Floresenergy_progress
11/10/2025FireplacesGiap Floresenergy_progress
11/10/2025HVAC-R and service water heating equipmentGiap Floresenergy_progress
11/10/2025Maintenance informationGiap Floresenergy_progress
11/10/2025Duct leakage testing, insulation and designGiap Floresenergy_progress
11/10/2025Shutoff dampersGiap Floresenergy_progress
11/10/2025HVAC-R and service water piping design and insulationGiap Floresenergy_progress
11/10/2025HVAC-R and service water heating system controlsGiap Floresenergy_progress
11/10/2025FinalGiap Floresprogress
11/10/2025Mechanical SystemsGiap Floresspecial
09/03/2025Maintenance informationPATRICK MCDONALDenergy_progress
09/03/2025Mechanical SystemsPATRICK MCDONALDspecial
09/03/2025Tenant Protection Plan CompliancePATRICK MCDONALDspecial
09/03/2025Fire-Resistant Penetrations and JointsPATRICK MCDONALDspecial
09/03/2025Post-installed AnchorsPATRICK MCDONALDspecial
09/03/2025FinalPATRICK MCDONALDprogress
09/03/2025HVAC-R and service water piping design and insulationPATRICK MCDONALDenergy_progress
Latest 25 of 66.
▾Documents — 287 on file (BIS + DOB NOW)
▸Plans & Drawings17
▸DOB NOWPlans/Sketch15
08/31/2026B00644620-I1Request digital key ↗
08/31/2026B00644620-P1Request digital key ↗
08/31/2026B00644620-P4Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Structural2
08/22/2026B00409955-I1Request digital key ↗
08/22/2026B00409955-P1Request digital key ↗
▸Applications & Permits55
▸BISPLAN / WORK APPROVAL APPLICATION36
05/14/2025321590104Open ↗
05/09/2025321590104Open ↗
05/02/2025321590104Open ↗
Showing 3 of 36 on file for this type
▸BISWORK PERMIT APPLICATION17
01/08/2024321590104Open ↗
01/08/2024321590104Open ↗
12/15/2023321590104Open ↗
Showing 3 of 17 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
02/23/2024340907585Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
03/27/2024321590104Open ↗
▸Zoning, Tax Lot & Property Records6
▸BISZONING DIAGRAM3
04/24/2025321590104Open ↗
11/06/2023321590104Open ↗
09/02/2021321590104Open ↗
▸BISADDRESS - NEW HOUSE NUMBER APPROVED1
02/10/2010320123086Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
03/31/2021321590104Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
03/31/2021321590104Open ↗
▸Seals & Professional Certifications92
▸DOB NOWProgress Inspector Seal & Signature43
09/23/2026B01256610-S1Open ↗
09/23/2026B01256610-S1Open ↗
09/01/2026B00644620-I1Open ↗
Showing 3 of 43 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature23
09/23/2026B01256610-S1Open ↗
09/01/2026B00644620-I1Open ↗
08/29/2026B00644620-P4Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature17
08/31/2026B00644620-P3Open ↗
08/31/2026B00644620-I1Open ↗
08/31/2026B00644620-P1Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
01/03/2022321590104Open ↗
11/10/2021321590104Open ↗
02/10/2010320123086Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
01/31/2024340907585Open ↗
11/17/2014340207804Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
11/17/2014340207804Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
01/31/2024340907585Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/17/2014340207804Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
01/28/2010320123086Open ↗
▸Safety & Tenant Protection25
▸DOB NOWHPD-1: Anti-Harassment Area Checklist18
08/31/2026B00651883-P1Open ↗
08/13/2026B00644620-P4Open ↗
08/13/2026B01256610-I1Open ↗
Showing 3 of 18 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
01/03/2022321590104Open ↗
▸BISBPP: STREET TREES SITE PLAN1
01/31/2024340907585Open ↗
▸BISSTREET TREE CHECKLIST1
06/08/2021321590104Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
02/13/2025321590104Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
09/04/2025340907585Open ↗
▸BISANTI-HARASSMENT AREA CHECKLIST1
06/08/2021321590104Open ↗
▸DOB NOWCertificate of No Harassment1
08/13/2026B01256610-I1Open ↗
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/21/2026B01256610-I1Open ↗
08/21/2026B01256610-S1Open ↗
08/13/2026B00409955-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/31/2026B00644620-I1Open ↗
08/31/2026B00651883-I1Open ↗
08/31/2026B00651828-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
01/03/2022321590104Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
01/07/2022321590104Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
01/03/2022321590104Open ↗
11/10/2021321590104Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
01/07/2022321590104Open ↗
06/08/2021321590104Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026B00644620-I1Open ↗
08/13/2026B00651828-I1Open ↗
▸BISLIGHTING IN DWELLING UNITS1
06/10/2025321590104Open ↗
▸BISLIGHTING CONTROLS1
06/10/2025321590104Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
06/10/2025321590104Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00651828-I1Open ↗
▸Inspections & Test Reports14
▸BISTECHNICAL REPORT: RESPONSIBILITY6
06/17/2025321590104Open ↗
06/12/2025321590104Open ↗
06/11/2025321590104Open ↗
Showing 3 of 6 on file for this type
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
03/07/2022321590104Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
10/03/2024321590104Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
06/17/2025321590104Open ↗
▸BISMASONRY1
10/03/2024321590104Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
01/03/2022321590104Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
01/03/2022321590104Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
10/03/2024321590104Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
06/04/2025321590104Open ↗
▸Approvals, Objections & Sign-offs27
▸BISSCHEDULE A - OCCUPANCY / USE17
04/18/2025321590104Open ↗
03/26/2025321590104Open ↗
02/06/2025321590104Open ↗
Showing 3 of 17 on file for this type
▸BISSUPERSEDING LETTER5
01/08/2024321590104Open ↗
01/08/2024321590104Open ↗
12/15/2023321590104Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
08/27/2024321590104Open ↗
12/15/2023321590104Open ↗
07/15/2021321590104Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
01/28/2010320123086Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
05/29/2025340907585Open ↗
▸Cost, Insurance & Ownership9
▸BISPROJECT-SPECIFIC GL INSURANCE6
01/08/2024321590104Open ↗
12/15/2023321590104Open ↗
12/07/2023321590104Open ↗
Showing 3 of 6 on file for this type
▸BISCOST AFFIDAVIT1
07/15/2021321590104Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
12/15/2023321590104Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE1
12/29/2021321590104Open ↗
▸Filing & Intake Forms17
▸BISADDITIONAL INFORMATION10
04/14/2025321590104Open ↗
08/27/2024321590104Open ↗
11/16/2023321590104Open ↗
Showing 3 of 10 on file for this type
▸BISBOROUGH INTAKE FORM3
01/08/2024321590104Open ↗
01/08/2024321590104Open ↗
12/15/2023321590104Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
01/31/2024340907585Open ↗
11/17/2014340207804Open ↗
▸BISEFILING COVER SHEET2
11/19/2020321590104Open ↗
01/28/2010320123086Open ↗
▸Other Documents5
▸BISPlot Diagram2
02/10/2010320123086Open ↗
07/15/2021321590104Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
07/15/2021321590104Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
03/27/2024340907585Open ↗
▸BISTCO REJECTED.1
06/17/2025321590104Open ↗