RoofUnder Construction14p · 8 filings · 20 docs
ArchitectureEquipmentMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems
HEREWITH FILING FOR MODIFICATIONS TO THE Existing MECHANICAL SYSTEM ON THE ROOF AS PER PLANS. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
10 documents · 1 drawing sheet
FACADE REPAIRS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
On file for this project
9 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLD EQUIPMENT.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Penthouse13p · 12 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Sprinklers
Project M00265262Permit Issued · 02/23/2022
SPRINKLER MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. CONSTRUCTION FLOORS 16,20, PENTHOUSE (RENTAL FLOORS 17, 21,22)
RENOVATION OF EXISTING PENTHOUSE AND ROOF INCLUDING RELATED CONSTRUCTION AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OF OCCUPANCY UNDER THIS APPLICATION
On file for this project
13 documents · 1 drawing sheet
RENOVATION OF EXISTING PENTHOUSE AND ROOF AS INDICATED ON THE DRAWINGS FILED HEREIN INCLUDING INSTALLATION OF NEW PLUMBING FIXTURES.NO CHANGE IN USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
On file for this project
10 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 224p · 3 filings · 20 docs
Fire ProtectionPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 1 drawing sheet
PLUMBING MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. CONSTRUCTION FLOORS 16,20, PENTHOUSE (RENTAL FLOORS 17, 21,22)
On file for this project
3 documents · 1 drawing sheet
installation of temp loop and removal of existing sprinkler heads as shown on plans filed herewith. no change in use, egress of occupancy under this application.
On file for this project
4 documents · 2 drawing sheets
Floor 216p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 3 drawing sheets
Herewith filing for modifications to existing mechanical systems on floors 4 thru 7, 17, & 21 as indicated on plans.
On file for this project
19 documents · 1 drawing sheet
INSTALLATION OF MECHANICAL DUCTWORK AND AIR TERMINAL DEVISES AS PER DRAWINGS HEREIN. APPROX 13,000 SF. THERE IS NO CHANGE IN OCCUPACNY, USE, OR EGRESS.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 2015p · 10 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Sprinklers
Installation of new plumbing fixtures on 20th Floor and Penthouse Level as per plans filed. There is no change in occupancy, use, or egress.
On file for this project
5 documents · 2 drawing sheets
Installation of new sprinkler heads as per plans filed. There is no change in occupancy, use, or egress.
On file for this project
12 documents · 2 drawing sheets
INTERIOR RENOVATION OF 21ST AND 22ND FLOOR AS PER DRAWINGS. NO CHANGES TO USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 4 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 19Under Construction15p · 5 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Sprinklers
MODIFICATIONS TO SPRINKLER SYSTEM AS PER PLANS FILED HEREWITH.
On file for this project
11 documents · 3 drawing sheets
Herewith filing for installation of temporary partitions and doors surrounding and modifications to existing accessory stair on the 18th, 19th and 20th floors as indicated on plans. No change in use, occupancy, or egress.
On file for this project
9 documents · 5 drawing sheets
PLUMBING WORK AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 18Under Construction15p · 5 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Sprinklers
MODIFICATIONS TO SPRINKLER SYSTEM AS PER PLANS FILED HEREWITH.
On file for this project
11 documents · 5 drawing sheets
Herewith filing for installation of temporary partitions and doors surrounding and modifications to existing accessory stair on the 18th, 19th and 20th floors as indicated on plans. No change in use, occupancy, or egress.
On file for this project
9 documents · 1 drawing sheet
PLUMBING WORK AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 1719p · 8 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 3 drawing sheets
Herewith filing for modifications to existing mechanical systems on floors 4 thru 7, 17, & 21 as indicated on plans.
On file for this project
19 documents · 1 drawing sheet
INSTALLATION OF NEW PLUMBING FIXTURES AND ASSOCIATED PIPING AS PER DRAWIGNSHEREIN. APPROX. 12000 SF. NO CHANGE TOUSE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 161p · 3 filings · 3 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Sprinklers
Project M00265262Permit Issued · 02/23/2022
SPRINKLER MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. CONSTRUCTION FLOORS 16,20, PENTHOUSE (RENTAL FLOORS 17, 21,22)
PLUMBING MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. CONSTRUCTION FLOORS 16,20, PENTHOUSE (RENTAL FLOORS 17, 21,22)
On file for this project
3 documents · 1 drawing sheet
Project M00265153Permit Issued · 03/04/2020
MECHANICAL WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. CONSTRUCTION FLOORS 16,20, PENTHOUSE (RENTAL FLOORS 17, 21,22)
Floor 151p · 1 filing · 4 docs
Fire Protection
installation of temp loop and removal of existing sprinkler heads as shown on plans filed herewith. no change in use, egress of occupancy under this application.
On file for this project
4 documents · 1 drawing sheet
Floor 1412p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
INSTALLATION OF NEW PLUMBING FIXTURES AND ASSOCIATED PIPING AS PER DRAWIGNS HEREIN. APPROX.13000SF. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 2 drawing sheets
INSTALLATION OF FIRE PROTECTION SYSTEME QUIPMENT AS PER DRAWIGNS HEREIN. APPROX. 13000SF. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 1 drawing sheet
REMOVAL AND INSTALLATION OF MECHANICAL EQUIPMENT AS PER DRAWIGNSHEREIN. APPROX. 13000SF. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
26 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 13
Floor 123p · 3 filings · 14 docs
Fire ProtectionMechanicalPlumbing
HEREWITH FILING SPRINKLER MODIFICATION OF EXISTING SPRINKLER SYSTEM ON THE 12TH FL. NO CHANGE IN USE, OCCUPANCY OR EGRESS FILED UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
HEREWITH FILING MECHANICAL WORK ASSOCIATED WITH AN INTERIOR FIT OUT. SCOPE INCLUDES CONSTRUCTION OF INTERIOR NON-BEARING PARTITIONS AND DOORS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.FILED UNDER THIS APPLICATION
On file for this project
8 documents · 1 drawing sheet
HEREWITH FILING OF PLUMBING WORK ASSOCIATED WITH AN INTERIOR FIT OUT. SCOPE INCLUDES INSTALLATION OF NEW PLUMBING FIXTURES.
On file for this project
3 documents · 1 drawing sheet
Floor 113p · 3 filings · 8 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems
HEREWITH FILING PLUMBING DEMOLITION (INTERIOR) WORK ON THE 11TH FLOOR. SCOPE : CAP AND REMOVAL OF EXISTING FIXTURES AS INDICATED ON THE DRAWINGS FILED HEREIN. NO CHANGE IN USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
HEREWITH FILING SPRINKLER MODIFICATION OF EXISTING SPRINKLER SYSTEM ON THE 11TH FL.THE SCOPE OF WORK INCLUDED THE REMOVAL OF EXISTING HEADS AND INSTALLATION OF NEW TEMP. LOOP AS INDICATED ON THE DRAWINGS FILED HEREIN NO CHANGE IN USE, OCCUPANCY OR EGRESS
On file for this project
5 documents · 2 drawing sheets
Project M00262765Permit Issued · 02/14/2020
HEREWITH FILING MECHANICAL WORK ASSOCIATED WITH AN ALT I APPLICATION FOR INTERIOR FIT OUT AND INCREASE OF OCCUPANCY. SCOPE INCLUDES INSTALLATION OF NEW EXHAUST FANS, AIR COOLING AND HEATING UNITS, ETC. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Floor 107p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
HEREWITH FILING SPRINKLER MODIFICATION OF EXISTING SPRINKLER SYSTEM ON THE 10TH FL. BO CHANGE IN USE, OCCUPANCY OR EGRESS FILED UNDER THIS APPLICATION.
On file for this project
5 documents · 2 drawing sheets
INSTALLATION OF NEW TEMP LOOP ON 10TH FL. NO CHANGE IN USE, OCCUPANCY OR EGRESS FILED UNDER THIS APPLICATION.
On file for this project
4 documents · 2 drawing sheets
HEREWITH FILING INTERIOR FIT OUT. SCOPE INCLUDES INSTALLATION OF NEW METAL DECK PER THE DRAWINGS FILED HEREIN. NO CHANGE IN USE, OCCUPANCY OR EGRESS FILED UNDER THIS APPLICATION.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 97p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbing
SPRINKLER WORK RELATED TO INSTALLATION OF NEW SPRINKLER HEADS AT 9TH FLOOR AND DEMO OF EXISTING TEMP LOOP AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
10 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY SPRINKLER LOOP AND REMOVAL OF EXISTING SPRINKLER HEADS ON ASSOCIATED PIPING. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
4 documents · 2 drawing sheets
PLUMBING MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 8
Floor 710p · 5 filings · 20 docs
Fire ProtectionGeneralMechanicalPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 7 drawing sheets
Herewith filing for modifications to existing mechanical systems on floors 4 thru 7, 17, & 21 as indicated on plans.
On file for this project
19 documents · 1 drawing sheet
APPLICATION FILED HEREWITH FOR INSTALLATION OF SPRINKLER TEMP LOOP AND REMOVAL OF SPRINKLER HEADS AT FLOORS 4-7, AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 68p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 5 drawing sheets
Herewith filing for modifications to existing mechanical systems on floors 4 thru 7, 17, & 21 as indicated on plans.
On file for this project
19 documents · 1 drawing sheet
APPLICATION FILED HEREWITH FOR INSTALLATION OF SPRINKLER TEMP LOOP AND REMOVAL OF SPRINKLER HEADS AT FLOORS 4-7, AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 57p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 3 drawing sheets
Herewith filing for modifications to existing mechanical systems on floors 4 thru 7, 17, & 21 as indicated on plans.
On file for this project
19 documents · 1 drawing sheet
APPLICATION FILED HEREWITH FOR INSTALLATION OF SPRINKLER TEMP LOOP AND REMOVAL OF SPRINKLER HEADS AT FLOORS 4-7, AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 47p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Herewith filing for modifications to existing plumbing, sprinkler and standpipe systems on 4th thru 7th, 17th, and 21st floors as indicated on plans.
On file for this project
20 documents · 3 drawing sheets
Herewith filing for modifications to existing mechanical systems on floors 4 thru 7, 17, & 21 as indicated on plans.
On file for this project
19 documents · 1 drawing sheet
APPLICATION FILED HEREWITH FOR INSTALLATION OF SPRINKLER TEMP LOOP AND REMOVAL OF SPRINKLER HEADS AT FLOORS 4-7, AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 3
Floor 22p · 2 filings · 13 docs
Fire ProtectionStructural
RENOVATION OF EXISTING LOBBY INCLUDING THE INSTALLATION OF NEW REVOLVING DOOR AND NEW ENTRANCE AWNING PER THE DRAWINGS FILED HEREIN. NO CHANGE IN USE, OCCUPANCY OR EGRESS FILED UNDER THIS APPLICATION.
On file for this project
6 documents · 1 drawing sheet
HEREWITH FILING SPRINKLER MODIFICATION OF EXISTING SPRINKLER SYSTEM IN PENTHOUSE AND ROOF TO INCLUDE TEMPORARY INSTALL COVERAGE OF 1 HEAD
On file for this project
7 documents · 1 drawing sheet
Floor 14p · 5 filings · 20 docs
Fire ProtectionMechanicalStructural
Infill of center bay of existing stair opening, infill of southeast stair opening, partial demo and infill of first floor and built-up floor for ADA accessible entrance, and structural support for new marquee. No change to use, egress or occupancy.
On file for this project
11 documents · 1 drawing sheet
Modification to existing standpipe and Sprinkler system. There is no change in occupancy, use, or egress.
On file for this project
21 documents · 1 drawing sheet
HEREWITH FILING SPRINKLER MODIFICATION OF EXISTING SPRINKLER SYSTEM AT FIRST FLOOR, LOBBY. NO CHANGE IN EGRESS FILED UNDER THIS APPLICATION
On file for this project
17 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Cellar2p · 1 filing · 10 docs
Plumbing
HEREWITH FILING OF PLUMBING WORK ASSOCIATED WITH AN INTERIOR FIT OUT. SCOPE INCLUDES CONSTRUCTION OF INTERIOR NON-BEARING PARTITIONS AND DOORS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
10 documents · 2 drawing sheets