← Back
Office with commercial, 7-19 stories
16 EAST 52 STREET
MANHATTAN · Midtown-Times Square · BIN 1035475
💬 Discuss this project
1927Year Built
16Stories
O6Building Class
C5-3Zoning
90,816 sfGross Floor Area
20Units
LL97 Covered12 Open Violations ▸FISP: SWARMP
Office with commercial, 7-19 stories · 7,531 sf lot · 12.06 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneralOther
Permit Issued — active, not yet Signed-off
Roof1p · 4 filings · 16 docs
Floor 14Under Construction26p · 1 filing · 20 docs
Floor 13Under Construction4p · 1 filing · 20 docs
Floor 12Under Construction26p · 1 filing · 20 docs
Floor 111p · 1 filing · 5 docs
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 41p · 1 filing · 5 docs
Floor 3
Floor 2Under Construction11p · 1 filing · 7 docs
Floor 113p · 5 filings · 20 docs
Mezzanine76p · 3 filings · 20 docs
Cellar73p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TRIGON 5222709/22/2026
CENTRAL CONST MANAGEMENT304/09/2026
PLATINUM SERVICES NY903/22/2026
BRIGHT STAR SERVICE403/22/2026
DISH WIRELESS303/22/2026
YATES RESTORATION GROUP L503/22/2026
ARBUS3803/22/2026
OWNER OF 16 E. 52ND ST403/22/2026
TRIGON EQUITIES5403/21/2026
TRIGON 57603/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PDG BUILDING CONSULTANTS LLC LLC2103/21/2026
AMERILAND BROOK LLC203/21/2026
DESARNO ASSOCIATES1603/21/2026
JRK CREATIVE803/21/2026
CH BUILDING CONSULTANTS203/21/2026
CONSTRUCTION PERMIT SERVICES503/21/2026
MUNICIPAL BUILDING CONSULTANTS603/21/2026
C PLUS DESIGN GROUP803/21/2026
GREEN STUDIO403/21/2026
BRITZ ENTERPRISES INC.403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LOWVOLT TECH ENTERPRISESGeneral Contractor1207/08/2026
SPRING SCAFFOLDING LLCGeneral Contractor707/08/2026
DNP BUILDERS LLCGeneral Contractor704/09/2026
PRECISION WORLDWIDEGeneral Contractor707/08/2026
PLATINUM SERVICES NY LLCGeneral Contractor603/21/2026
BRIGHT STAR LIGHTING CORPGeneral Contractor303/21/2026
KLE CONSTRUCTION INCGeneral Contractor303/21/2026
ATLANTA TRA&ENG CO.LLCGeneral Contractor303/21/2026
XH&RC PLBG AND HTG INCPlumbing207/08/2026
MILLER PLUMBING & HTG INCFire Protection207/08/2026
ALPHA CONSTRUCTION PGeneral Contractor208/25/2026
C PLUS DESIGN GROUP INCGeneral Contractor203/21/2026
SQUAN CONSTRUCTION SERVICGeneral Contractor207/08/2026
STELLMAR PLBG & MECH.CORPPlumbing209/22/2026
CHESAKL ENTERPRISES INCGeneral Contractor104/09/2026
COMCELL CONSTRUCTION CORP.General Contractor107/08/2026
SMART PLBG & HTG CORPPlumbing107/08/2026
SOTIRIOS STATHOPOULOSElectrical103/21/2026
SANTORA, FRANKElectrical103/21/2026
MORALES, RICHARDElectrical103/21/2026
MARINA COOLING CORPGeneral Contractor104/09/2026
METALPRO CUSTOM CONSTRUCTElectrical103/21/2026
KRUGER, JAMESElectrical103/21/2026
CONTROL SPEC ELECL SYSTEMElectrical103/22/2026
CMY ELECTRICAL CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HIGH LINE ENGINEERING PC2920108/26/2026
INM ARCHITECT, P.C.3351301/02/2026
CELTIC WAY CONSULTING LLC9780410/06/2025
ALL CITY ENGINEERING PC7115905/07/2025
JKM ARCHITECTURE P.C.8906206/20/2024
RICHARD H. BALSER ENGINEE3028202/09/2024
THE EIPEL ENGINEERING GRO2714102/05/2024
SCHERER DESIGN GROUP7921107/26/2023
RICHARD B. KORNBLAU, AIA3208302/27/2023
KMB DESIGN GROUP, LLC513109/27/2022
Building Lifecycle
All (300)Filed (51)Permit Issued (42)Signed Off (18)Facade (FISP) (6)Violation (40)Inspection (33)Objection (80)Special Inspection (30)
09/21/2026
Permit issued — Sprinklers
M01440828-S1-PL
08/26/2026
Filed — Alteration
Work includes construction of new non-load-bearing gypsum board partitions to create an office, closet, and pantry; installation of door frames & hardware; new millwork an & casework for the pantry; new floor finishes throughout the tenant space.
M01440828-S1
08/24/2026
Permit issued — General Construction
M01440828-I1-GC
08/20/2026
Objection resolved — Resolved
08/08/2026
Filed — Alteration
Work includes construction of new non-load-bearing gypsum board partitions to create an office, closet, and pantry; installation of door frames & hardware; new millwork an & casework for the pantry; new floor finishes throughout the tenant space.
M01440828-I1
08/04/2026
Special inspection requirement — Final
Emily Ruopp
08/04/2026
Special inspection requirement — Post-installed Anchors
Ruslan Nagorny
08/04/2026
Special inspection requirement — Sprinkler Systems
Ruslan Nagorny
08/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ruslan Nagorny
07/16/2026
Objection raised — Other
07/14/2026
Permit issued — General Construction
M01408714-I1-GC
06/26/2026
Filed — Alteration
REPAIRS TO EXTERIOR FACADE. NO CHANGE TO EGRESS, USE OR OCCUPANCY.
M01416237-I1
06/12/2026
Special inspection requirement — Final
Deborah Rojas De Leon
06/10/2026
Filed — Alteration
INTERIOR DEMOLITION OF AN EXISTING OFFICE TENANT SPACE ON THE 2ND FLOOR OF AN EXISTING COMMERCIAL AND OFFICE BUILDING. SELECTIVE REMOVAL OF EXISTING NON-STRUCTURAL PARTITIONS, DOORS, CEILINGS, FINISHES, MILLWORK, AND RELATED INTERIOR ELEMENTS.
M01408714-I1
05/08/2026
Special inspection requirement — Lighting controls
Nikola Martinovic
05/08/2026
Special inspection requirement — Interior lighting power
Nikola Martinovic
05/08/2026
Special inspection requirement — Fire-Resistance Rated Construction
Nikola Martinovic
05/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Nikola Martinovic
05/08/2026
Special inspection requirement — Exterior lighting power
Nikola Martinovic
05/08/2026
Special inspection requirement — Metering
Nikola Martinovic
04/07/2026
Objection resolved — Addressed
04/07/2026
Objection resolved — Addressed
02/10/2026
Objection resolved — Addressed
02/10/2026
Objection resolved — Addressed
02/09/2026
Objection raised — Other
02/09/2026
Objection raised — Other
01/30/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/29/2026
Objection resolved — Addressed
01/29/2026
Objection resolved — Addressed
01/27/2026
Objection raised — Other
01/27/2026
Objection raised — Other
01/27/2026
Objection raised — Other
01/22/2026
Objection raised — Other
01/15/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/12/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/02/2026
Filed — Alteration CO
Change of use from retail to eating and drinking establishment as per plans filed.
M00956935-P1
12/22/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/08/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/17/2025
Permit issued — Mechanical Systems
M01279885-S1-MS
11/07/2025
Signed off — Alteration
Modification of an existing Verizon site on the roof. Replace (10) antennas, (9) RRHs, and (3) cabinets. Install (2) microwave dishes. All work in conformance with TPPN 5/98. No change in use, egress, or occupancy.
M00902695-I1
11/07/2025
Permit issued — Sprinklers
M01279885-S2-EW-SP
11/05/2025
Permit issued — Structural
M01279885-S3-ST
10/24/2025
Permit issued — Sprinklers
M01279885-S2-PL
10/23/2025
Permit issued — General Construction
M01279885-I1-GC
10/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAI HUANG
10/14/2025
Special inspection requirement — Sprinkler Systems
KAI HUANG
10/10/2025
Filed — Alteration
INSTALL STAIRCASE AT 12TH THRU 14TH FLOOR ONLY.
M01279885-P1
10/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/09/2025
Special inspection requirement — Sprinkler Systems
10/07/2025
Objection resolved — Addressed
10/07/2025
Objection resolved — Addressed
10/06/2025
Filed — Alteration
INSTALL STAIRCASE AT 12TH THRU 14TH FLOOR ONLY.
M01279885-S1
10/06/2025
Filed — Alteration
INSTALL STAIRCASE AT 12TH THRU 14TH FLOOR ONLY.
M01279885-S2
10/06/2025
Filed — Alteration
INSTALL STAIRCASE AT 12TH THRU 14TH FLOOR ONLY.
M01279885-S3
10/06/2025
Special inspection requirement — Sprayed fire-resistant materials
KAI HUANG
10/06/2025
Special inspection requirement — Structural Steel - High Strength Bolting
KAI HUANG
10/06/2025
Special inspection requirement — Structural Steel - Welding
KAI HUANG
10/06/2025
Special inspection requirement — Concrete - Cast-In-Place
KAI HUANG
10/06/2025
Special inspection requirement — Post-installed Anchors
KAI HUANG
09/30/2025
Special inspection requirement — Structural Steel - Details
KAI HUANG
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedSTELLMAR PLBG & MECH.CORP09/21/2026
DOB NOWGeneral ConstructionPermit IssuedALPHA CONSTRUCTION & P08/24/2026
DOB NOWGeneral ConstructionSigned-offALPHA CONSTRUCTION & P07/14/2026
DOB NOWMechanical SystemsPermit IssuedMARINA COOLING CORP11/17/2025
DOB NOWSprinklersPermit IssuedHF GROUP PLMBG & SPNKLER11/07/2025
DOB NOWStructuralPermit IssuedCHESAKL ENTERPRISES INC11/05/2025
DOB NOWSprinklersPermit IssuedSMART PLBG & HTG CORP10/24/2025
DOB NOWGeneral ConstructionPermit IssuedVENO INC10/23/2025
DOB NOWSupported ScaffoldPermit IssuedYATES EXTERIOR RESTORATIO08/20/2025
DOB NOWAntennaSigned-offSQUAN CONSTRUCTION SERVIC03/25/2025
DOB NOWConstruction FenceSigned-offDNP BUILDERS LLC03/19/2025
DOB NOWGeneral ConstructionPermit IssuedDNP BUILDERS LLC03/19/2025
DOB NOWSprinklersSigned-offMILLER PLUMBING & HTG INC03/05/2025
DOB NOWConstruction FenceSigned-offDNP BUILDERS LLC02/26/2025
DOB NOWGeneral ConstructionPermit IssuedDNP BUILDERS LLC11/06/2024
DOB NOWMechanical SystemsSigned-offKLE CONSTRUCTION INC10/21/2024
DOB NOWPlumbingSigned-offXH&RC PLBG AND HTG INC08/08/2024
DOB NOWGeneral ConstructionPermit IssuedLOWVOLT TECH ENTERPRISES07/25/2024
DOB NOWConstruction FenceSigned-offLOWVOLT TECH ENTERPRISES05/30/2024
DOB NOWGeneral ConstructionPermit IssuedLOWVOLT TECH ENTERPRISES05/20/2024
DOB NOWPlumbingSigned-offMILLER PLUMBING & HTG INC04/16/2024
DOB NOWPlumbingSigned-offSTELLMAR PLBG & MECH.CORP04/12/2024
DOB NOWMechanical SystemsSigned-offLOWVOLT TECH ENTERPRISES02/29/2024
DOB NOWStructuralSigned-offLOWVOLT TECH ENTERPRISES02/28/2024
DOB NOWPlumbingSigned-offDONATO PLUMBING, INC02/16/2024
DOB NOWPlumbingSigned-offXH&RC PLBG AND HTG INC01/26/2024
DOB NOWGeneral ConstructionPermit IssuedC PLUS DESIGN GROUP INC01/08/2024
DOB NOWAntennaSigned-offSQUAN CONSTRUCTION SERVIC08/23/2023
DOB NOWGeneral ConstructionPermit IssuedLOWVOLT TECH ENTERPRISES07/25/2023
DOB NOWMechanical SystemsSigned-offPRECISION WORLDWIDE03/15/2023
DOB NOWSprinklersSigned-offMETFLOW FIRE CONTROL LLC01/27/2023
DOB NOWMechanical SystemsSigned-offPRECISION WORLDWIDE11/25/2022
DOB NOWAntennaSigned-offATLANTA TRA&ENG CO.LLC10/15/2022
DOB NOWPlumbingSigned-offAQUA PLUMBING & HTNG CORP10/01/2022
DOB NOWMechanical SystemsSigned-offPRECISION WORLDWIDE09/29/2022
DOB NOWSupported ScaffoldSigned-offPLATINUM SERVICES NY LLC12/10/2021
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC06/11/2021
DOB NOWMechanical SystemsSigned-offBRIGHT STAR LIGHTING CORP04/15/2020
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC12/28/2018
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC11/02/2018
+ 52 more permits on file
2 projects · most recent 10/10/2025
Heating and Air Conditioning Systems Air Conditioning Systems Refrigeration Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
10/10/2025Permit IssuedMARINA COOLING CORPHeating and Air Conditioning Systems
Heat / Cool
Daikin RXTQ60TBVJUA 5 tons · Vrf Outdoor ×2
RXS12LVJU 1 tons · Condensing Unit ×1
RXTQ48TAVJU 4 tons · Vrf Outdoor ×1
Johnson Controls DSV300B 25 tons · Vrf Outdoor ×1
05/07/2025Permit IssuedLOWVOLT TECH ENTERPRISESAir Conditioning Systems, Heating and Air Conditioning Systems, Refrigeration Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric PUHY-P120TNU-A 10 tons · Vrf Outdoor ×4
PUHY-P168TNU-A 14 tons · Vrf Outdoor ×3
PUZ-A24NHA7 2 tons · Heat Pump Outdoor ×2
MXZ-SM120TAM 10 tons · Vrf Outdoor ×2
MUZ-WR24NA 2 tons · Heat Pump Outdoor ×1
Ventilation
Greenheck CUE-200HP-VG 3,600 CFM · Exhaust Fan ×3
Cooling
Oxbox J4AC3060B1000AA 5 tons · Condensing Unit ×1
Refrigeration
Heatcraft BCH0008MBACZA0000 8,000 BTU · Condensing Unit ×1
BCH0010MBACZA0000 10,000 BTU · Condensing Unit ×1
BCH0022LBBCZA0200 7,500 BTU · Condensing Unit ×1
Trenton TEZA008H8-HS2D-B 8,000 CFM · Condensing Unit ×1
2 projects · most recent 10/10/2025
Sprinkler System
FiledStatusContractorScope
10/10/2025Permit IssuedHF GROUP PLMBG & SPNKLERSprinkler System
05/07/2025Signed-offMILLER PLUMBING & HTG INCSprinkler System
4 projects · most recent 08/26/2026
Water/Sanitary Gas
FiledStatusContractorScope
08/26/2026Permit IssuedSTELLMAR PLBG & MECH.CORP—
10/10/2025Permit IssuedSMART PLBG & HTG CORPWater/Sanitary
05/07/2025Signed-offSTELLMAR PLBG & MECH.CORPGas, Water/Sanitary
12/05/2024Signed-offXH&RC PLBG AND HTG INCGas
14 projects · most recent 07/08/2026
General Wiring
FiledStatusContractorScope
07/08/2026Permit IssuedWESTSIDE ELECTRIC INCGeneral Wiring
11/03/2025Permit IssuedKINGS ELECTRIC CO., INC.General Wiring
12/17/2024CompleteENNELL GRP ELECTRIC CORPGeneral Wiring
07/01/2024CompleteJEM ELEC'L CONTR. CORP—
02/04/2024CompleteASKO ELEC CONST & MAIN IN—
01/03/2024Permit IssuedOMD ELECTRICAL CORP1 meters, 1 new_meters
01/02/2024CompleteCONTROL SPEC ELECL SYSTEMGeneral Wiring
07/27/2023CompleteC.FALCO ELETL CONT CORPGeneral Wiring
02/03/2023Permit IssuedPOWERONE ELECT'L CONTRG1 meters, 1 new_meters
01/17/2023Permit IssuedVALLEY ELECTRIC OF NY INCGeneral Wiring
11/18/2021Permit IssuedCONDUCTOR ELECL SVCS INC—
05/31/2021CompleteILLUMINOUS ELECTRIC CORP.—
07/17/2018CompleteTOP SHELF ELECTRIC CORP—
01/25/2018CompleteCMY ELECTRICAL CORPGeneral Wiring
1 project · most recent 01/02/2026
Steel Concrete
FiledStatusContractorScope
01/02/2026Permit IssuedDNP BUILDERS LLCSteel, Concrete
1 project · most recent 08/01/2018
Sidewalk Shed
FiledStatusContractorScope
08/01/2018Signed-offSPRING SCAFFOLDING LLCSidewalk Shed
▾Field Inspections (DOB CAP) — 33
DateTypeResultReport
01/30/2026Fail-Final General Construction Non-Directive 14FailView ↗
01/15/2026Fail-Final General Construction Non-Directive 14FailView ↗
01/12/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/22/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/08/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
09/19/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/08/2025Fail-Final CND-Occupancy InspectionFailView ↗
09/04/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/08/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
05/08/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/06/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/04/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/04/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/29/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/09/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/23/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/06/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/07/2024Pass-Final CND-Occupancy InspectionPassView ↗
10/03/2024Pass-Final CND-Occupancy InspectionPassView ↗
09/25/2024Fail-Final CND-Occupancy InspectionFailView ↗
08/29/2024Fail-Final General Construction Non-Directive 14FailView ↗
08/13/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/28/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/20/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
Latest 25 of 33.
▾Special Inspection Requirements (DOB NOW) — 115
DateRequirementInspectorRole
08/04/2026Post-installed AnchorsRuslan Nagornyspecial
08/04/2026FinalEmily Ruoppprogress
08/04/2026Sprinkler SystemsRuslan Nagornyspecial
08/04/2026Fire-Resistant Penetrations and JointsRuslan Nagornyspecial
06/12/2026FinalDeborah Rojas De Leonprogress
05/08/2026MeteringNikola Martinovicenergy_progress
05/08/2026Lighting controlsNikola Martinovicenergy_progress
05/08/2026Interior lighting powerNikola Martinovicenergy_progress
05/08/2026Fire-Resistant Penetrations and JointsNikola Martinovicspecial
05/08/2026Exterior lighting powerNikola Martinovicenergy_progress
05/08/2026Fire-Resistance Rated ConstructionNikola Martinovicprogress
10/14/2025Sprinkler SystemsKAI HUANGspecial
10/14/2025Fire-Resistant Penetrations and JointsKAI HUANGspecial
10/09/2025Fire-Resistant Penetrations and Joints—special
10/09/2025Sprinkler Systems—special
10/06/2025Concrete - Cast-In-PlaceKAI HUANGspecial
10/06/2025Sprayed fire-resistant materialsKAI HUANGspecial
10/06/2025Post-installed AnchorsKAI HUANGspecial
10/06/2025Structural Steel - WeldingKAI HUANGspecial
10/06/2025Structural Steel - High Strength BoltingKAI HUANGspecial
09/30/2025Structural Steel - DetailsKAI HUANGspecial
09/25/2025Structural Stability – Alterations of existing buildingsKAI HUANGspecial
09/25/2025FinalKAI HUANGprogress
09/03/2025Mechanical SystemsKAI HUANGspecial
09/03/2025FinalKAI HUANGprogress
Latest 25 of 115.
▾Documents — 1,115 on file (BIS + DOB NOW)
▸Plans & Drawings51
▸DOB NOWPlans/Sketch46
09/06/2026M00062343-I1Request digital key ↗
09/06/2026M00067660-I1Request digital key ↗
09/06/2026M00062352-I1Request digital key ↗
Showing 3 of 46 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly3
08/22/2026M01037044-P3Request digital key ↗
08/22/2026M01037044-P2Request digital key ↗
08/22/2026M01037044-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/04/2026M00334046-P1Request digital key ↗
Showing 1 of 2 on file for this type
▸Applications & Permits187
▸BISPLAN / WORK APPROVAL APPLICATION105
12/10/2025122006809Open ↗
06/26/2024122006809Open ↗
06/25/2024122006809Open ↗
Showing 3 of 105 on file for this type
▸BISWORK PERMIT APPLICATION81
12/10/2025122006809Open ↗
06/24/2021140886520Open ↗
02/08/2019140744755Open ↗
Showing 3 of 81 on file for this type
▸BISSIDEWALK SHED APPLICATION & PERMIT1
06/22/2021140886520Open ↗
▸Seals & Professional Certifications326
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION111
10/15/2019140744755Open ↗
02/04/2019140744755Open ↗
11/08/2018123149823Open ↗
Showing 3 of 111 on file for this type
▸DOB NOWProgress Inspector Seal & Signature53
09/23/2026M01279885-S1Open ↗
09/19/2026M00956935-I1Open ↗
09/19/2026M00956935-I1Open ↗
Showing 3 of 53 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature51
09/06/2026M00062352-I1Open ↗
09/04/2026M00334046-P1Open ↗
09/04/2026M00334046-I1Open ↗
Showing 3 of 51 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST33
01/26/2018123149832Open ↗
01/26/2018123149823Open ↗
09/28/2017122829760Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature32
09/23/2026M01279885-S1Open ↗
09/19/2026M00956935-I1Open ↗
09/01/2026M00898328-I1Open ↗
Showing 3 of 32 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT22
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
01/26/2018123149832Open ↗
Showing 3 of 22 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
▸BISProfessional and Owner Certification (POC3)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISApplicant / Owner Signature1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment63
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE18
01/26/2018123149832Open ↗
01/26/2018123149823Open ↗
Showing 2 of 18 on file for this type
▸BISSELF-CERT PLUMBING NOTICE16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISSCHEDULE B - PLUMBING10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA8
11/07/2025123192927Open ↗
12/14/2017123310434Open ↗
11/29/2017122009192Open ↗
Showing 3 of 8 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT7
07/21/2017122804439Open ↗
07/19/2017122804439Open ↗
Showing 2 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS3
07/19/2017122804439Open ↗
Showing 1 of 3 on file for this type
▸BISSPRINKLER SYSTEMS1
08/08/2024122006809Open ↗
▸Safety & Tenant Protection7
▸BISTenant Protection Plan and Notes3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWStreet Tree Checklist2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISST-1 Street Tree Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos133
▸BISASBESTOS: CERTIFICATION (DEP ACP5)37
03/19/2018140744755Open ↗
01/26/2018123149823Open ↗
01/26/2018123149832Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report37
09/06/2026M00062352-I1Open ↗
09/04/2026M00334046-P1Open ↗
09/01/2026M00771402-I1Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWOER: Notice to Proceed29
09/06/2026M00062352-I1Open ↗
Showing 1 of 29 on file for this type
▸DOB NOWOER: Notice of Satisfaction11
09/06/2026M00062352-I1Open ↗
Showing 1 of 11 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISASBESTOS INSPECTION REPORT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED3
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
02/05/2018123149832Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION1
05/17/2022140886520Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
04/04/2020140886520Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance71
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS40
10/15/2019140744755Open ↗
10/22/2018122792219Open ↗
10/22/2018122792219Open ↗
Showing 3 of 40 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS16
05/17/2022140886520Open ↗
10/15/2019140744755Open ↗
10/22/2018122792219Open ↗
Showing 3 of 16 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
06/17/2024122006337Open ↗
06/07/2024122006337Open ↗
05/17/2022140886520Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
▸BISNYCECC ANALYSIS2
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
▸BISINTERIOR LIGHTING POWER1
01/14/2025122006337Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY8
01/21/2025122006337Open ↗
06/12/2024122006337Open ↗
06/11/2024122006809Open ↗
Showing 3 of 8 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISMECHANICAL SYSTEMS1
01/14/2025122006337Open ↗
▸Approvals, Objections & Sign-offs75
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST42
02/25/2026122006809Open ↗
01/21/2025122006337Open ↗
06/17/2024102233030Open ↗
Showing 3 of 42 on file for this type
▸BISADMINISTRATIVE OBJECTIONS19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION8
06/14/2024102233030Open ↗
06/14/2024102463709Open ↗
06/14/2024120880859Open ↗
Showing 3 of 8 on file for this type
▸BISFINAL2
02/25/2026122006809Open ↗
01/17/2025122006337Open ↗
▸BISSUPERSEDING LETTER2
12/10/2025122006809Open ↗
Showing 1 of 2 on file for this type
▸BISCCD1-Construction Code Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership90
▸BISCOST AFFIDAVIT86
08/08/2024122006337Open ↗
06/17/2024122006809Open ↗
06/17/2024102233030Open ↗
Showing 3 of 86 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
08/08/2024122006337Open ↗
08/08/2024122006809Open ↗
04/03/2024123310434Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms85
▸BISEFILING COVER SHEET56
02/27/2018123226865Open ↗
01/29/2018123192927Open ↗
01/26/2018123149832Open ↗
Showing 3 of 56 on file for this type
▸BISBOROUGH INTAKE FORM12
11/12/2025122006809Open ↗
05/27/2021140886520Open ↗
10/15/2019140744755Open ↗
Showing 3 of 12 on file for this type
▸BISADDITIONAL INFORMATION12
09/28/2017122829760Open ↗
Showing 1 of 12 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET5
04/04/2020140886520Open ↗
03/19/2018140744755Open ↗
Showing 2 of 5 on file for this type
▸Other Documents8
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION5
01/26/2018123149823Open ↗
Showing 1 of 5 on file for this type
▸DOB NOWProperty Ownership Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISMAINTENANCE INFORMATION1
01/14/2025122006337Open ↗