← Back
School or academy
16 JONES STREET
MANHATTAN · BIN 1010140
💬 Discuss this project
1928Year Built
3Stories
W3Building Class
R6Zoning
5,524 sfGross Floor Area
2Units
2 Open Violations ▸
School or academy · Owner of record: CO-OP SETTLEMENT INC · 3,105 sf lot · 1.78 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Bulkhead1p · 1 filing · 12 docs
Floor 21p · 1 filing · 12 docs
Floor 1Under Construction28p · 4 filings · 20 docs
CellarUnder Construction3p · 2 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GREENWICH HOUSE1707/08/2026
RAFI SHAHRIAR 5H ENGINEER103/22/2026
AVENTADOR CONSTRUCTION IN103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LILKER ASSOCIATES CONSULTING ENGINE501/27/2026
WW ENGINEERING PLLC612/22/2025
OGAWA DEPARDON405/31/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.3003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CROWN PLUMBING INCPlumbing407/08/2026
SAMIRO SERVICES INCGeneral Contractor203/21/2026
REAZ MOHAMMEDElectrical103/21/2026
MAGIC MECHANICAL INCPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
WW ENGINEERING PLLC7502212/22/2025
PROJECT TACTICAL SOLUTION5859102/24/2025
Building Lifecycle
All (100)Filed (15)Permit Issued (6)Violation (15)Inspection (19)Objection (15)Special Inspection (30)
08/28/2026
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
07/13/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/08/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/01/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/20/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/16/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/13/2026
Inspection — Certified StandPipe-Fire Pump (SD)-Fire Pump Test
Certified
View inspection ↗
03/13/2026
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
03/05/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/27/2026
Filed — Alteration
Plumbing work as shown on drawings filed herewith.
M01144288-P3
01/08/2026
Permit issued — Plumbing
M00775308-I1-PL
01/08/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/08/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/02/2026
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
01/02/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
12/22/2025
Filed — Alteration
M00775288-P1
12/16/2025
Special inspection requirement — Heating Systems
Wing Wong
12/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Wing Wong
12/05/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
11/20/2025
Filed — Alteration
Plumbing work as shown on drawings filed herewith.
M01144288-P2
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/14/2025
Filed — Alteration
Plumbing work as shown on drawings filed herewith.
M01144288-P1
10/02/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/08/2025
Permit issued — Mechanical Systems
M01144514-I1-MS
08/11/2025
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
07/24/2025
Permit issued — Plumbing
M01144288-I1-PL
07/24/2025
Objection resolved — Addressed
07/23/2025
Objection raised — Admin
07/11/2025
Objection resolved — Addressed
03/14/2025
Objection raised — Admin
02/24/2025
Filed — Alteration
Mechanical work as shown on drawings filed herewith.
M01144514-I1
02/24/2025
Filed — Alteration
Plumbing work as shown on drawings filed herewith.
M01144288-I1
11/20/2024
Special inspection requirement — Chimneys and vents
Max Lee
11/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Max Lee
11/19/2024
Special inspection requirement — Final
Max Lee
11/19/2024
Special inspection requirement — Mechanical Systems
Max Lee
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/09/2024
Permit issued — Boiler Equipment
M00775288-I1-BE
07/23/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/18/2024
Permit issued — Plumbing
M00775308-I1-PL
01/18/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/05/2024
Special inspection requirement — Insulation placement and R values
01/05/2024
Special inspection requirement — Interior lighting power
01/05/2024
Special inspection requirement — Metering
01/05/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
01/05/2024
Special inspection requirement — Fenestration areas
01/05/2024
Special inspection requirement — Air barrier - visual inspection
01/05/2024
Special inspection requirement — Fenestration air leakage
08/04/2023
Permit issued — Plumbing
M00775308-I1-PL
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/08/2023
Objection raised — Other
06/08/2023
Objection raised — Other
06/02/2023
Objection raised — Other
06/02/2023
Objection raised — Other
05/31/2023
Filed — Alteration CO
Vertical enlargement, and cellar enlargement of existing non-profit community facility as shown on drawings filed herewith.
M00816347-S7
05/31/2023
Filed — Alteration CO
Vertical enlargement, and cellar enlargement of existing non-profit community facility as shown on drawings filed herewith.
M00816347-S6
05/31/2023
Filed — Alteration CO
Vertical enlargement, and cellar enlargement of existing non-profit community facility as shown on drawings filed herewith.
M00816347-S8
05/25/2023
Special inspection requirement — Structural Steel - High Strength Bolting
05/25/2023
Special inspection requirement — Structural Steel - Welding
Latest 60 of 100 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedCROWN PLUMBING INC01/08/2026
DOB NOWMechanical SystemsPermit IssuedSAMIRO SERVICES INC09/08/2025
DOB NOWPlumbingPermit IssuedMAGIC MECHANICAL INC07/24/2025
DOB NOWBoiler EquipmentSigned-offCROWN PLUMBING INC09/09/2024
DOB NOWPlumbingPermit IssuedCROWN PLUMBING INC07/18/2024
DOB NOWPlumbingPermit IssuedCROWN PLUMBING INC08/04/2023
BISOTISSUEDAVENTADOR CONSTRUCTION IN03/09/2020
BISOTISSUEDAVENTADOR CONSTRUCTION IN03/09/2020
BISOTISSUEDAVENTADOR CONSTRUCTION IN03/09/2020
BISOTISSUEDAVENTADOR CONSTRUCTION IN12/26/2018
BISMHISSUEDRETCON MECHANICAL CORP08/20/2012
BISBLISSUEDJ JEKOWSKY & SONS03/16/1999
BISPLISSUEDJ JEKOWSKY & SONS03/16/1999
3 projects · most recent 01/16/2026
General Wiring
FiledStatusContractorScope
01/16/2026Permit IssuedTHE METRO GROUP ELECTRIC—
09/08/2025Permit IssuedTruephase Electrical ContractorsGeneral Wiring
09/21/2023Permit IssuedJ & Y ELECTRIC AND INTER*General Wiring
▾Field Inspections (DOB CAP) — 19
DateTypeResultReport
08/28/2026Pass-Final PL - More than 10 Requested FloorsPassView ↗
07/13/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/01/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/20/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/16/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/13/2026Certified StandPipe-Fire Pump (SD)-Fire Pump TestCertifiedView ↗
03/13/2026Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
03/05/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/08/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/02/2026Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
01/02/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/05/2025Pass-Final Boiler Equipment InspectionPassView ↗
11/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/02/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/11/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
07/23/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/18/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 55
DateRequirementInspectorRole
12/16/2025Heating SystemsWing Wongspecial
12/16/2025Fire-Resistant Penetrations and JointsWing Wongspecial
11/20/2024Chimneys and ventsMax Leespecial
11/20/2024Fire-Resistant Penetrations and JointsMax Leespecial
11/19/2024FinalMax Leeprogress
11/19/2024Mechanical SystemsMax Leespecial
01/05/2024Insulation placement and R values—energy_progress
01/05/2024Interior lighting power—energy_progress
01/05/2024Metering—energy_progress
01/05/2024Fenestration and door U-factor and product ratings—energy_progress
01/05/2024Fenestration areas—energy_progress
01/05/2024Air barrier - visual inspection—energy_progress
01/05/2024Fenestration air leakage—energy_progress
05/25/2023Structural Steel - High Strength Bolting—special
05/25/2023Structural Steel - Welding—special
05/25/2023Subgrade Inspections—special
05/25/2023Masonry—special
05/25/2023Structural Cold-Formed Steel—special
05/25/2023Concrete - Cast-In-Place—special
05/25/2023Masonry—special
05/25/2023Structural Steel - Welding—special
05/25/2023Subgrade Inspections—special
05/25/2023Structural Cold-Formed Steel—special
05/25/2023Structural Steel - High Strength Bolting—special
05/25/2023Post-installed Anchors—special
Latest 25 of 55.
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
09/01/2026M00775288-P1Request digital key ↗
09/01/2026M00775288-I1Request digital key ↗
09/01/2026M00775308-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits24
▸BISPLAN / WORK APPROVAL APPLICATION12
03/23/2020123446976Open ↗
02/13/2019123446976Open ↗
02/13/2019123446976Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION6
03/11/2020123446976Open ↗
03/11/2020123446976Open ↗
03/10/2020123446976Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLPC Approval/Permit6
08/13/2026M01144288-P2Open ↗
08/13/2026M01144288-I1Open ↗
08/13/2026M01144288-P1Open ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records3
▸BISZONING DIAGRAM2
11/29/2018123446976Open ↗
03/30/2018123446976Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
11/29/2018123446976Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/01/2026M00775288-P1Open ↗
09/01/2026M00775288-I1Open ↗
08/24/2026M01144514-I1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
09/06/2019123446976Open ↗
12/26/2018123446976Open ↗
12/26/2018123446976Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/25/2026M01144514-I1Open ↗
08/24/2026M00775288-P1Open ↗
08/24/2026M00775288-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/25/2026M01144514-I1Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/30/2018123446976Open ↗
▸Safety & Tenant Protection6
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE4
12/26/2018123446976Open ↗
12/26/2018123446976Open ↗
12/26/2018123446976Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
12/26/2018123446976Open ↗
▸BISSTREET TREE CHECKLIST1
12/26/2018123446976Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
09/01/2026M00775288-I1Open ↗
09/01/2026M00775288-P1Open ↗
08/24/2026M01144514-I1Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
12/26/2018123446976Open ↗
11/29/2018123446976Open ↗
07/30/2018123446976Open ↗
Showing 3 of 5 on file for this type
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
12/26/2018123446976Open ↗
09/11/2018123446976Open ↗
08/03/2012121169378Open ↗
▸BISTR8: Energy Code Progress Inspections1
08/20/2012121169378Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
12/26/2018123446976Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
11/16/2018123446976Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
12/26/2018123446976Open ↗
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
11/16/2018123446976Open ↗
▸Approvals, Objections & Sign-offs12
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
09/01/2026M00775288-P1Open ↗
09/01/2026M00775288-I1Open ↗
08/13/2026M01144514-I1Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS APPROVAL2
11/16/2018123446976Open ↗
08/03/2012121169378Open ↗
▸BISLANDMARKS SIGNOFF1
09/11/2018123446976Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
08/03/2012121169378Open ↗
▸Cost, Insurance & Ownership5
▸BISPROJECT-SPECIFIC GL INSURANCE3
03/10/2020123446976Open ↗
12/26/2018123446976Open ↗
12/26/2018123446976Open ↗
▸BISCOST AFFIDAVIT2
03/30/2018123446976Open ↗
08/03/2012121169378Open ↗
▸Filing & Intake Forms12
▸BISEFILING COVER SHEET6
09/27/2018123446976Open ↗
09/26/2018123446976Open ↗
03/30/2018123446976Open ↗
Showing 3 of 6 on file for this type
▸BISBOROUGH INTAKE FORM4
03/23/2020123446976Open ↗
02/13/2019123446976Open ↗
02/13/2019123446976Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION2
02/07/2020123446976Open ↗
02/28/2019123446976Open ↗
▸Other Documents13
▸DOB NOWProof of Historic Building8
08/13/2026M01144514-I1Open ↗
08/13/2026M01144288-I1Open ↗
08/13/2026M01144288-P2Open ↗
Showing 3 of 8 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
11/29/2018123446976Open ↗
09/05/2018123446976Open ↗
03/30/2018123446976Open ↗
Showing 3 of 4 on file for this type
▸BISPLOT DIAGRAM1
03/30/2018123446976Open ↗