| Owner | Filings | Most Recent |
|---|---|---|
| 160 E 35 OWNER INC | 1 | 03/22/2026 |
| E35 OWNER | 18 | 03/21/2026 |
| BLESSED TRINITY CHURCH | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/28/2017 | $8.2M | — | CONGREGATION FOR THE LIGHT, INC. → 160 E35 OWNER INC. | $717/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CELESTE UMPIERRE ARCHITECT | 8 | 08/02/2023 |
| POLISE CONSULTING ENGINEERS DPC | 5 | 12/21/2021 |
| ASHRAF CORP | 1 | 01/22/2020 |
| GACE DPC | 1 | 12/10/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| METROPOLIS GROUP INC | 24 | 03/21/2026 |
| DVA Advisors | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CENTRAL INTERIORS, INC | General Contractor | 14 | 07/08/2026 |
| HYDRONIC CONCEPTS NY P&H | Plumbing | 5 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 4 | 03/21/2026 |
| BASIL, OMAR | Electrical | 1 | 03/21/2026 |
| LEVINE, GARY | Electrical | 1 | 03/21/2026 |
| MOSCATI, MICHAEL | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACE STRUCTURAL ENGINEERIN | 496 | 13 | 08/02/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | HYDRONIC CONCEPTS NY P&H | 01/06/2022 |
| DOB NOW | Plumbing | Signed-off | HYDRONIC CONCEPTS NY P&H | 12/10/2021 |
| DOB NOW | Structural | Signed-off | CENTRAL INTERIORS, INC | 09/29/2021 |
| DOB NOW | Mechanical Systems | Signed-off | CENTRAL INTERIORS, INC | 09/23/2021 |
| DOB NOW | General Construction | Permit Issued | CENTRAL INTERIORS, INC | 08/13/2021 |
| DOB NOW | Structural | Signed-off | CENTRAL INTERIORS, INC | 05/10/2021 |
| DOB NOW | Mechanical Systems | Signed-off | CENTRAL INTERIORS, INC | 04/16/2021 |
| DOB NOW | Supported Scaffold | Signed-off | EVEREST SCAFFOLDING INC | 01/19/2021 |
| DOB NOW | Plumbing | Signed-off | HYDRONIC CONCEPTS NY P&H | 10/13/2020 |
| DOB NOW | Mechanical Systems | Signed-off | CENTRAL INTERIORS, INC | 10/08/2020 |
| DOB NOW | Structural | Signed-off | CENTRAL INTERIORS, INC | 10/08/2020 |
| DOB NOW | Supported Scaffold | Signed-off | EVEREST SCAFFOLDING INC | 01/23/2020 |
| DOB NOW | Structural | Signed-off | CENTRAL INTERIORS, INC | 12/21/2019 |
| DOB NOW | Mechanical Systems | Signed-off | CENTRAL INTERIORS, INC | 12/05/2019 |
| DOB NOW | Plumbing | Signed-off | HYDRONIC CONCEPTS NY P&H | 09/25/2019 |
| DOB NOW | Plumbing | Signed-off | HYDRONIC CONCEPTS NY P&H | 08/23/2019 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/21/2021 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/21/2021 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/21/2021 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/21/2021 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/21/2021 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 04/08/2021 |
| BIS | EQ | ISSUED | CUSTOM GLASSWORKS LLC | 10/29/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 10/20/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/30/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/30/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/30/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 06/10/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 06/10/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 06/10/2020 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 09/03/2019 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 07/26/2019 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 04/10/2019 |
| BIS | OT | ISSUED | CENTRAL INTERIORS, INC | 11/15/2018 |
| BIS | EQ | ISSUED | L AND B CONSTRUCTION NY INC | 07/29/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2021 | Complete | WEBSITE ELECTRIC CORP. | General Wiring |
| 04/06/2021 | Complete | JAM ELECTRICAL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/23/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/05/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/25/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/27/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/04/2022 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 03/30/2022 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/15/2023 | Air barrier continuity plan testing | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Lighting controls | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Fire-Resistant Penetrations and Joints | ANTHONY UGBEBOR | special |
| 08/15/2023 | Fire-Resistance Rated Construction | ANTHONY UGBEBOR | progress |
| 08/15/2023 | Energy Code Compliance Inspections | ANTHONY UGBEBOR | progress |
| 08/15/2023 | Metering | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Fenestration areas | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Fenestration and door U-factor and product ratings | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Fenestration air leakage | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Interior lighting power | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Air barrier - visual inspection | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Maintenance information | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Insulation placement and R values | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Electrical motors and elevators | ANTHONY UGBEBOR | energy_progress |
| 08/15/2023 | Exterior lighting power | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Lighting controls | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Energy Code Compliance Inspections | ANTHONY UGBEBOR | progress |
| 08/02/2023 | Fire-Resistance Rated Construction | ANTHONY UGBEBOR | progress |
| 08/02/2023 | Fenestration areas | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Metering | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Air barrier continuity plan testing | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Insulation placement and R values | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Exterior lighting power | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Fenestration and door U-factor and product ratings | ANTHONY UGBEBOR | energy_progress |
| 08/02/2023 | Fenestration air leakage | ANTHONY UGBEBOR | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Khimji Foundation | Office | Cellar, Floors 1–5 | Project M00190370 |