| Owner | Filings | Most Recent |
|---|---|---|
| 161-165 East 91st Street Owners | 23 | 03/22/2026 |
| Investment Private Wealth Advisor | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Mobile Office Architects, PC (Moa) | 2 | 06/28/2025 |
| Eric Sheffield Architect | 2 | 10/14/2022 |
| Melone Architects | 2 | 09/20/2022 |
| Enthink Engineers | 1 | 08/30/2022 |
| Porter Clapp Architects | 2 | 07/31/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Boyd Consulting | 4 | 03/21/2026 |
| J.A.M. Associates | 4 | 03/21/2026 |
| BMB Building Consulting | 2 | 03/21/2026 |
| Tribeca Construction Consulting | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| I Dimension | General Contractor | 6 | 03/21/2026 |
| Andamio Scaffolding | Scaffold | 3 | 03/21/2026 |
| Jepol Construction | General Contractor | 3 | 07/08/2026 |
| Garadice Builders | General Contractor | 2 | 03/21/2026 |
| American Standard P&H Cororp | Plumbing | 1 | 07/08/2026 |
| HI-Tech Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| G-Electric | Electrical | 1 | 03/21/2026 |
| J&M Plumbing of Westchester | Plumbing | 1 | 07/08/2026 |
| Power Surge Electric | Electrical | 1 | 03/21/2026 |
| Power Surge Electric | Electrical | 1 | 03/22/2026 |
| Skyeline Construction | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Eric Sheffield Architect | 2195 | 1 | 10/14/2022 |
| Melone Architects | 2944 | 1 | 09/20/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Skyeline Construction | 08/13/2025 |
| DOB NOW | General Construction | Signed-off | I Dimension | 03/31/2025 |
| DOB NOW | Plumbing | Signed-off | American Standard P&H Cororp | 04/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | I Dimension | 04/23/2024 |
| DOB NOW | General Construction | Signed-off | Hudson Meridian Construction GP | 10/24/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 08/30/2022 |
| DOB NOW | Plumbing | Signed-off | J&M Plumbing of Westchest | 08/29/2022 |
| DOB NOW | General Construction | Signed-off | CR Safety Group | 08/24/2022 |
| DOB NOW | General Construction | Signed-off | Hudson Meridian Construction GP | 08/27/2021 |
| DOB NOW | Plumbing | Signed-off | HI-Tech Plumbing & Heating | 07/27/2020 |
| BIS | MH | ISSUED | Euda Construction | 11/30/2020 |
| BIS | OT | ISSUED | Skyeline Construction | 09/04/2020 |
| BIS | OT | ISSUED | Skyeline Construction | 07/20/2020 |
| BIS | OT | ISSUED | Euda Construction | 02/21/2020 |
| BIS | MH | ISSUED | Euda Construction | 08/06/2019 |
| BIS | BL | ISSUED | Abilene | 12/04/2017 |
| BIS | BL | ISSUED | Abilene | 08/11/2017 |
| BIS | PL | ISSUED | Bell Fuel Oil | 06/21/2017 |
| BIS | BL | ISSUED | Abilene | 06/21/2017 |
| BIS | MH | ISSUED | Emg Industrial Chimney | 11/14/2016 |
| BIS | PL | ISSUED | Plumbing & Heating Doctor | 12/17/2015 |
| BIS | OT | ISSUED | Focus & Struga Building D | 11/25/2015 |
| BIS | EQ | ISSUED | Rockledge Scaffold | 07/15/2014 |
| BIS | PL | ISSUED | A. Heating and Plumbing Works | 03/18/2014 |
| BIS | OT | ISSUED | Arza Contracting | 03/14/2014 |
| BIS | PL | ISSUED | Steve Belsito Sons | 05/21/2009 |
| BIS | OT | ISSUED | CLN Home Improvement | 04/14/2009 |
| BIS | PL | ISSUED | Pyrosvestic Mechanical | 09/26/2007 |
| BIS | PL | ISSUED | Pyrosvestic Mechanical | 03/26/2007 |
| BIS | OT | ISSUED | J.A.L. Interiors | 03/07/2007 |
| BIS | PL | ISSUED | I.M.P. Plumbing & Heating | 02/28/2007 |
| BIS | OT | ISSUED | J.A.L. Interiors | 02/21/2007 |
| BIS | EQ | ISSUED | Spring Scaffolding | 03/25/2003 |
| BIS | PL | ISSUED | Graham PLG Co | 10/16/1998 |
| BIS | OT | ISSUED | Beech Associates | 08/24/1998 |
| BIS | PL | ISSUED | Signore & Sons Plumbing | 03/11/1994 |
| BIS | — | ISSUED | J.O.S. Construction | 09/20/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2024 | Complete | G-Electric | General Wiring |
| 03/04/2024 | Complete | Power Surge Electric | General Wiring |
| 08/23/2022 | Complete | Borowide Elect'l Contractors | — |
| 04/28/2022 | Complete | Titan Electrical & Elev Contracting | — |
| 07/30/2020 | Permit Issued | Mac Elect'l Contracting | General Wiring |
| 03/01/2020 | Complete | J.G.C. Electric | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/07/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/04/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/30/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/22/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/24/2025 | Final | Alan Ho | progress |
| 08/26/2022 | Masonry | Nicholas Melone | special |
| 08/26/2022 | Final | Nicholas Melone | progress |
| 07/31/2022 | Final | P McClure Clapp | progress |
| 07/31/2022 | Lighting controls | P McClure Clapp | energy_progress |
| 07/31/2022 | Lighting in dwelling units | P McClure Clapp | energy_progress |