2007Year Built
6Stories
W5Building Class
R6Zoning
68,823 sfGross Floor Area
1Units
LL97 Covered9 Open Violations ▸FDNY Report ↗
City university · Owner of record: DORMITORY AUTHORITY OF NYS · 15,720 sf lot · 4.38 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction19p · 4 filings · 20 docs
Penthouse1p · 1 filing · 4 docs
Floor 51p · 1 filing · 3 docs
Floor 4
Floor 3
Floor 2
Floor 1
CellarUnder Construction30p · 4 filings · 20 docs
Sub-Basement1p · 1 filing · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DASNY6609/15/2026
DORMITORY AUTHORITY OF THE STATE OF NEW YORK603/22/2026
TO THE OWNER OF 123 CROWN203/22/2026
SAME103/21/2026
ASNY103/21/2026
PASNY103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JMV ASSOCIATES LLC703/21/2026
MUNICIPAL BUILDING CONSULTANTS403/21/2026
CONSTRUCTION PERMIT SERVICES403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
R.A.M.S. MECHANICAL INCGeneral Contractor704/09/2026
SIERRA MECHANICAL CONTRACTINGGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FUTURE TECH CONSULTANTS O5891008/17/2026
Building Lifecycle
All (158)Filed (14)Permit Issued (9)Violation (60)Inspection (3)Objection (42)Special Inspection (30)
08/17/2026
Filed — Alteration
Proposed Structural scope to replace and repair damaged tiles and substrate structure of existing raised floor system at sever room B43 caused by the removal of 3-existing CRAC units. All as per Plans filed herewith.
B08018909-P2
07/30/2026
Special inspection requirement — Post-installed Anchors
MARISA HARTE
07/30/2026
Special inspection requirement — Final
Panagiotis Koklanos
07/09/2026
Permit issued — Boiler Equipment
B01205579-I1-BE
04/01/2026
Permit issued — General Construction
B08015455-I1-GC
04/01/2026
Permit issued — Structural
B08018909-I1-ST
04/01/2026
Permit issued — Mechanical Systems
B07995060-I1-MS
11/19/2025
Permit issued — Boiler Equipment
B01205579-I1-BE
10/24/2025
Permit issued — Mechanical Systems
B07995060-I1-MS
10/09/2025
Permit issued — Structural
B08018909-I1-ST
10/06/2025
Objection resolved — Addressed
09/29/2025
Objection raised — Admin
09/16/2025
Filed — Alteration
Proposed replacement of existing Computer Room Air Conditionings (CRAC) units serving Academic Building 1, of the following CRAC Units:CRAC-6, CRAC-7,CRAC-8,ACC-3.. All as per Plans filed herewith. No change in use, egress, or Occupancy.
B07995060-P2
09/16/2025
Objection resolved — Addressed
09/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
09/12/2025
Special inspection requirement — Heating Systems
MARISA HARTE
09/12/2025
Special inspection requirement — Mechanical Systems
MARISA HARTE
09/12/2025
Special inspection requirement — Energy Code Compliance Inspections
MARISA HARTE
09/12/2025
Special inspection requirement — Final
Frank Ulisse
09/12/2025
Special inspection requirement — HVAC-R and service water heating system controls
MARISA HARTE
09/12/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MARISA HARTE
09/12/2025
Special inspection requirement — Maintenance information
MARISA HARTE
09/12/2025
Special inspection requirement — HVAC-R and service water heating equipment
MARISA HARTE
09/12/2025
Special inspection requirement — Shutoff dampers
MARISA HARTE
09/11/2025
Permit issued — General Construction
B08015455-I1-GC
08/27/2025
Objection raised — Scope
08/19/2025
Filed — Alteration
Proposed Structural scope to replace and repair damaged tiles and substrate structure of existing raised floor system at sever room B43 caused by the removal of 3-existing CRAC units. All as per Plans filed herewith.
B08018909-P1
08/19/2025
Filed — Alteration
Proposed replacement of existing Computer Room Air Conditionings (CRAC) units serving Academic Building 1, of the following CRAC Units:CRAC-6, CRAC-7,CRAC-8,ACC-3.. All as per Plans filed herewith. No change in use, egress, or Occupancy.
B07995060-P1
08/19/2025
Filed — Alteration
Proposed Architectural General Construction scope to replace and repair damaged tiles and substrate structure of existing raised floor system at sever room B43 caused by the removal of 3-existing CRAC units. All as per Plans filed herewith.
B08015455-P1
08/11/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/31/2025
Violation issued (FDNY_NOV, closed)
07/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MARISA HARTE
07/29/2025
Special inspection requirement — Maintenance information
MARISA HARTE
07/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
MARISA HARTE
07/29/2025
Special inspection requirement — Post-installed Anchors
MARISA HARTE
07/29/2025
Special inspection requirement — Shutoff dampers
MARISA HARTE
07/29/2025
Special inspection requirement — Structural Steel - Details
MARISA HARTE
07/29/2025
Special inspection requirement — Structural Steel - High Strength Bolting
MARISA HARTE
07/29/2025
Special inspection requirement — Structural Steel - Welding
MARISA HARTE
07/29/2025
Special inspection requirement — Final
Panagiotis Koklanos
07/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
07/29/2025
Special inspection requirement — Heating Systems
MARISA HARTE
07/29/2025
Special inspection requirement — Mechanical Systems
MARISA HARTE
07/29/2025
Special inspection requirement — Energy Code Compliance Inspections
MARISA HARTE
07/29/2025
Special inspection requirement — Final
Frank Ulisse
07/29/2025
Special inspection requirement — Preliminary
MARISA HARTE
07/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
MARISA HARTE
07/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
07/29/2025
Special inspection requirement — Final
Roberta Curtis
07/21/2025
Violation issued (FDNY_ORDER, closed)
07/21/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
07/03/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
06/25/2025
Permit issued — Mechanical Systems
B01205579-S1-GC-CX
05/20/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
Latest 60 of 158 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offCHAMPION COMBUSTION CORP07/09/2026
DOB NOWGeneral ConstructionPermit IssuedR.A.M.S. MECHANICAL INC04/01/2026
DOB NOWStructuralPermit IssuedR.A.M.S. MECHANICAL INC04/01/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC04/01/2026
DOB NOWBoiler EquipmentSigned-offCHAMPION COMBUSTION CORP11/19/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC10/24/2025
DOB NOWStructuralPermit IssuedR.A.M.S. MECHANICAL INC10/09/2025
DOB NOWGeneral ConstructionPermit IssuedR.A.M.S. MECHANICAL INC09/11/2025
DOB NOWMechanical SystemsPermit IssuedSIERRA MECHANICAL CONTRAC06/25/2025
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2017
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2017
BISMHISSUEDINFINITY CONTRACTING SERV11/09/2017
BISPLISSUEDPAR PLUMBING CO., INC03/20/2017
BISOTISSUEDPETK, INC11/14/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/14/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/14/2016
BISMHISSUEDINFINITY CONTRACTING SERV11/14/2016
BISMHISSUEDINFINITY CONTRACTING SERV11/09/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2016
BISOTRE-ISSUEDPETK, INC11/09/2016
BIS—ISSUEDRED HOOK SIGN AND ELECT C05/15/2014
BIS—ISSUEDRED HOOK SIGN AND ELECT C05/15/2014
BISPLISSUEDRICHARDS P AND H CO, INC03/12/2014
BISOTISSUEDRICHARDS PLUM & HTG CO,IN07/05/2013
BISFBISSUEDRICHARDS P&H CO INC03/25/2013
BISOTISSUEDRICHARDS PLUM & HTG CO,IN03/22/2013
BISPLISSUEDRICHARDS P AND H CO, INC03/12/2013
BISOTISSUEDRICHARDS PLUM & HTG CO,IN03/12/2013
BISOTISSUEDD A S N Y11/10/2010
BISCCISSUEDTHE URBAN GROUP LTD07/09/2010
BISCCISSUEDTHE URBAN GROUP LTD07/09/2010
BISPLISSUEDRICHARDS P AND H CO, INC05/11/2010
BISOTISSUEDMETROTECH CONTRACTING COR05/03/2010
BISFPISSUEDJEM FIRE PREVENTION INC03/31/2010
BISOTISSUEDMETROPOLITAN HEAT & POWER CO01/06/2010
BIS—ISSUEDM.A. ANGELIADES, INC01/06/2010
BISFBISSUEDMETROPOLITAN HT&POWER CO09/30/2009
BIS—ISSUEDM.A. ANGELIADES, INC09/28/2009
BISSDISSUEDA & A ASSOCIATES, INC09/23/2009
+ 19 more permits on file
1 project · most recent 09/16/2025
Air Conditioning Systems Heating Systems Others
FiledStatusContractorScopeMake / Model / Capacity
09/16/2025Permit IssuedR.A.M.S. MECHANICAL INCAir Conditioning Systems, Heating Systems, Others
Cooling
Data-Aire GFWU-07034-C 6,800 CFM · Crac Unit ×6
GFWU-03534-C 3,800 CFM · Crac Unit ×3
Liebert DS053KD 8,400 CFM · Crac Unit ×9
Heating
Data-Aire GFWU-07034-C 6,800 BTU · Crac Unit ×6
GFWU-03534-C 3,800 BTU · Crac Unit ×3
Liebert DS053KD 8,400 BTU · Crac Unit ×9
Other
Liebert DDO 466A26 22,770 CFM · Crac Unit ×9
1 project · most recent 07/11/2025
General Wiring
FiledStatusContractorScope
07/11/2025Permit IssuedAUJLA ELECTRIC CORPGeneral Wiring
1 project · most recent 08/17/2026
Steel Concrete
FiledStatusContractorScope
08/17/2026Permit IssuedR.A.M.S. MECHANICAL INCSteel, Concrete
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
08/11/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/21/2025Fail-Final CND-Occupancy InspectionFailView ↗
07/03/2025Fail-Final CND-Occupancy InspectionFailView ↗
▾Special Inspection Requirements (DOB NOW) — 37
DateRequirementInspectorRole
07/30/2026Post-installed AnchorsMARISA HARTEspecial
07/30/2026FinalPanagiotis Koklanosprogress
09/12/2025Fire-Resistant Penetrations and JointsMARISA HARTEspecial
09/12/2025Heating SystemsMARISA HARTEspecial
09/12/2025Mechanical SystemsMARISA HARTEspecial
09/12/2025Energy Code Compliance InspectionsMARISA HARTEprogress
09/12/2025FinalFrank Ulisseprogress
09/12/2025HVAC-R and service water heating system controlsMARISA HARTEenergy_progress
09/12/2025HVAC-R and service water piping design and insulationMARISA HARTEenergy_progress
09/12/2025Maintenance informationMARISA HARTEenergy_progress
09/12/2025HVAC-R and service water heating equipmentMARISA HARTEenergy_progress
09/12/2025Shutoff dampersMARISA HARTEenergy_progress
07/29/2025HVAC-R and service water piping design and insulationMARISA HARTEenergy_progress
07/29/2025Maintenance informationMARISA HARTEenergy_progress
07/29/2025HVAC-R and service water heating system controlsMARISA HARTEenergy_progress
07/29/2025Post-installed AnchorsMARISA HARTEspecial
07/29/2025Shutoff dampersMARISA HARTEenergy_progress
07/29/2025Structural Steel - DetailsMARISA HARTEspecial
07/29/2025Structural Steel - High Strength BoltingMARISA HARTEspecial
07/29/2025Structural Steel - WeldingMARISA HARTEspecial
07/29/2025FinalPanagiotis Koklanosprogress
07/29/2025Fire-Resistant Penetrations and JointsMARISA HARTEspecial
07/29/2025Heating SystemsMARISA HARTEspecial
07/29/2025Mechanical SystemsMARISA HARTEspecial
07/29/2025Energy Code Compliance InspectionsMARISA HARTEprogress
Latest 25 of 37.
▾Documents — 325 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch14
08/28/2026B00763394-I1Request digital key ↗
08/28/2026B00762724-I1Request digital key ↗
08/28/2026B00762447-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸Applications & Permits62
▸BISWORK PERMIT APPLICATION32
11/13/2017321396422Open ↗
11/13/2017321396422Open ↗
11/13/2017321396422Open ↗
Showing 3 of 32 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION23
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
Showing 3 of 23 on file for this type
▸BISPLACE OF ASSEMBLY6
10/25/2011310184467Open ↗
10/25/2011310184458Open ↗
11/04/2009310184458Open ↗
Showing 3 of 6 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
05/15/2018321396422Open ↗
▸Seals & Professional Certifications88
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION51
08/19/2019321396422Open ↗
08/19/2019321396422Open ↗
08/19/2019321396422Open ↗
Showing 3 of 51 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/28/2026B00763394-I1Open ↗
08/28/2026B00762447-I1Open ↗
08/21/2026B01205579-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/29/2026B01205579-S1Open ↗
08/29/2026B07995060-P2Open ↗
08/29/2026B07995060-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/29/2026B01205579-S1Open ↗
08/29/2026B01205579-I1Open ↗
08/29/2026B07995060-P2Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
09/24/2010320218732Open ↗
Showing 1 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
09/24/2010320218732Open ↗
Showing 1 of 4 on file for this type
▸BISProfessional and Owner Certification (POC3)2
07/10/2014320926717Open ↗
07/10/2014320888795Open ↗
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment29
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT14
11/20/2013320407083Open ↗
12/03/2011320407083Open ↗
08/16/2010310200813Open ↗
Showing 3 of 14 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT4
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING3
01/07/2015320407083Open ↗
07/02/2012320407083Open ↗
12/03/2011320407083Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
06/02/2016321396422Open ↗
10/14/2014320407083Open ↗
09/02/2014320407083Open ↗
▸BISEQUIPMENT USE PERMITS2
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
▸BISSIGN HANGER CERTIFICATE1
09/24/2010320218732Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
11/24/2010310026414Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
11/07/2014320407083Open ↗
▸Environmental & Asbestos23
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER12
12/06/2011320407083Open ↗
09/24/2010320218732Open ↗
10/09/2009320080256Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/21/2026B01205579-S1Open ↗
08/21/2026B01205579-I1Open ↗
08/20/2026B08018909-P1Open ↗
Showing 3 of 10 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/09/2016321396422Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
08/19/2019321396422Open ↗
08/19/2019321396422Open ↗
11/09/2016321396422Open ↗
Showing 3 of 7 on file for this type
▸BISTR8: Energy Code Progress Inspections1
03/19/2012320407083Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
08/19/2019321396422Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
11/09/2016321396422Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
11/09/2016321396422Open ↗
▸Approvals, Objections & Sign-offs55
▸BISADMINISTRATIVE OBJECTIONS15
09/10/2014320407083Open ↗
07/10/2014320926717Open ↗
07/10/2014320888795Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter14
08/28/2026B00763394-I1Open ↗
08/28/2026B00762447-I1Open ↗
08/20/2026B08015455-I1Open ↗
Showing 3 of 14 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION13
07/10/2014320926717Open ↗
07/10/2014320888795Open ↗
01/27/2011310026414Open ↗
Showing 3 of 13 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
09/14/2019321396422Open ↗
08/19/2019321396422Open ↗
05/03/2011320218732Open ↗
Showing 3 of 13 on file for this type
▸Cost, Insurance & Ownership20
▸BISCOST AFFIDAVIT20
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
Showing 3 of 20 on file for this type
▸Filing & Intake Forms22
▸BISEFILING COVER SHEET13
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
Showing 3 of 13 on file for this type
▸BISADDITIONAL INFORMATION4
08/08/2019321396422Open ↗
09/02/2014320407083Open ↗
10/25/2011310184467Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAI1 Form3
08/13/2026B07995060-P2Open ↗
08/13/2026B07995060-I1Open ↗
08/13/2026B07995060-P1Open ↗
▸BISBOROUGH INTAKE FORM2
09/14/2019321396422Open ↗
08/19/2019321396422Open ↗
▸Other Documents1
▸BISFIRE SUPP ANSUL APPROVL- FD-FSS1
10/27/2010320080256Open ↗