💬 Discuss this project
2007Year Built
6Stories
W5Building Class
R6Zoning
68,823 sfGross Floor Area
1Units
LL97 Covered2 Active Violations 3 likely answered 1 old, status unconfirmed ▸FDNY Report ↗
City university · Owner of record: Dormitory Authority of NYS · 15,720 sf lot · 4.38 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofMedgar Evers College, Medgar EversUnder Construction16p · 5 filings · 17 docs
PenthouseMedgar Evers CollegeUnder Construction2p · 3 filings · 17 docs
Floor 5Fire resistance upgrades2 filings · 4 docs
Floor 4Fire resistance upgrades2 filings · 4 docs
Floor 3Fire resistance upgrades2 filings · 4 docs
Floor 2Fire resistance upgrades2 filings · 4 docs
Floor 1Fire resistance upgrades2 filings · 4 docs
CellarMedgar Evers CollegeUnder Construction28p · 5 filings · 17 docs
Sub-BasementMedgar Evers1p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Dasny6609/15/2026
Dormitory Authority of the State of New York603/22/2026
D.P. Consulting303/21/2026
Asny103/21/2026
Pasny103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Liro Engineers308/17/2026
The Liro Group309/16/2025
Curtis + Ginsberg Architects208/19/2025
Ramboll204/10/2025
Ahuja Partnership Architects109/26/2022
Willdan Energy Solutions209/23/2022
Robert Silman Associates109/21/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JMV Assosiates703/21/2026
Municipal Building Consultants403/21/2026
Construction Permit Services403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
R.A.M.S. Mechanicalspecialty_contractor704/09/2026
Sierra Mechanical ContractingGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Future Tech Consultants O5891008/17/2026
Building Lifecycle
All (155)Filed (14)Permit Issued (9)Violation (60)Objection (42)Special Inspection (30)
08/17/2026
Filed — Alteration
Proposed Structural scope to replace and repair damaged tiles and substrate structure of existing raised floor system at sever room B43 caused by the removal of 3-existing CRAC units. All as per Plans filed herewith.
B08018909-P2
07/30/2026
Special inspection requirement — Final
Panagiotis Koklanos
07/30/2026
Special inspection requirement — Post-installed Anchors
MARISA HARTE
07/09/2026
Permit issued — Boiler Equipment
B01205579-I1-BE
04/01/2026
Permit issued — Mechanical Systems
B07995060-I1-MS
04/01/2026
Permit issued — General Construction
B08015455-I1-GC
04/01/2026
Permit issued — Structural
B08018909-I1-ST
11/19/2025
Permit issued — Boiler Equipment
B01205579-I1-BE
10/24/2025
Permit issued — Mechanical Systems
B07995060-I1-MS
10/09/2025
Permit issued — Structural
B08018909-I1-ST
10/06/2025
Objection resolved — Addressed
09/29/2025
Objection raised — Admin
09/16/2025
Filed — Alteration
Proposed replacement of existing Computer Room Air Conditionings (CRAC) units serving Academic Building 1, of the following CRAC Units:CRAC-6, CRAC-7,CRAC-8,ACC-3.. All as per Plans filed herewith. No change in use, egress, or Occupancy.
B07995060-P2
09/16/2025
Objection resolved — Addressed
09/12/2025
Special inspection requirement — Shutoff dampers
MARISA HARTE
09/12/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MARISA HARTE
09/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
09/12/2025
Special inspection requirement — Heating Systems
MARISA HARTE
09/12/2025
Special inspection requirement — Mechanical Systems
MARISA HARTE
09/12/2025
Special inspection requirement — Energy Code Compliance Inspections
MARISA HARTE
09/12/2025
Special inspection requirement — Final
Frank Ulisse
09/12/2025
Special inspection requirement — HVAC-R and service water heating equipment
MARISA HARTE
09/12/2025
Special inspection requirement — HVAC-R and service water heating system controls
MARISA HARTE
09/12/2025
Special inspection requirement — Maintenance information
MARISA HARTE
09/11/2025
Permit issued — General Construction
B08015455-I1-GC
08/27/2025
Objection raised — Scope
08/19/2025
Filed — Alteration
Proposed Architectural General Construction scope to replace and repair damaged tiles and substrate structure of existing raised floor system at sever room B43 caused by the removal of 3-existing CRAC units. All as per Plans filed herewith.
B08015455-P1
08/19/2025
Filed — Alteration
Proposed Structural scope to replace and repair damaged tiles and substrate structure of existing raised floor system at sever room B43 caused by the removal of 3-existing CRAC units. All as per Plans filed herewith.
B08018909-P1
08/19/2025
Filed — Alteration
Proposed replacement of existing Computer Room Air Conditionings (CRAC) units serving Academic Building 1, of the following CRAC Units:CRAC-6, CRAC-7,CRAC-8,ACC-3.. All as per Plans filed herewith. No change in use, egress, or Occupancy.
B07995060-P1
07/31/2025
Violation issued (FDNY_NOV, closed)
07/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MARISA HARTE
07/29/2025
Special inspection requirement — Maintenance information
MARISA HARTE
07/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
MARISA HARTE
07/29/2025
Special inspection requirement — Shutoff dampers
MARISA HARTE
07/29/2025
Special inspection requirement — Post-installed Anchors
MARISA HARTE
07/29/2025
Special inspection requirement — Structural Steel - Details
MARISA HARTE
07/29/2025
Special inspection requirement — Structural Steel - High Strength Bolting
MARISA HARTE
07/29/2025
Special inspection requirement — Structural Steel - Welding
MARISA HARTE
07/29/2025
Special inspection requirement — Final
Panagiotis Koklanos
07/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
07/29/2025
Special inspection requirement — Heating Systems
MARISA HARTE
07/29/2025
Special inspection requirement — Mechanical Systems
MARISA HARTE
07/29/2025
Special inspection requirement — Energy Code Compliance Inspections
MARISA HARTE
07/29/2025
Special inspection requirement — Final
Frank Ulisse
07/29/2025
Special inspection requirement — Preliminary
MARISA HARTE
07/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
MARISA HARTE
07/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARISA HARTE
07/29/2025
Special inspection requirement — Final
Roberta Curtis
07/21/2025
Violation issued (FDNY_ORDER, closed)
06/25/2025
Permit issued — Mechanical Systems
B01205579-S1-GC-CX
05/20/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/07/2025
Objection raised — Admin
05/07/2025
Objection raised — Scope
Latest 60 of 155 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offChampion Combustion07/09/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. Mechanical04/01/2026
DOB NOWGeneral ConstructionPermit IssuedR.A.M.S. Mechanical04/01/2026
DOB NOWStructuralPermit IssuedR.A.M.S. Mechanical04/01/2026
DOB NOWBoiler EquipmentSigned-offChampion Combustion11/19/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. Mechanical10/24/2025
DOB NOWStructuralPermit IssuedR.A.M.S. Mechanical10/09/2025
DOB NOWGeneral ConstructionPermit IssuedR.A.M.S. Mechanical09/11/2025
DOB NOWMechanical SystemsPermit IssuedSierra Mechanical Contracting06/25/2025
BISOTISSUEDInfinity Contracting Service11/09/2017
BISOTISSUEDInfinity Contracting Service11/09/2017
BISMHISSUEDInfinity Contracting Service11/09/2017
BISPLISSUEDPar Plumbing Co03/20/2017
BISOTISSUEDInfinity Contracting Service11/14/2016
BISOTISSUEDInfinity Contracting Service11/14/2016
BISOTISSUEDPetk11/14/2016
BISMHISSUEDInfinity Contracting Service11/14/2016
BISOTRE-ISSUEDPetk11/09/2016
BISOTISSUEDInfinity Contracting Service11/09/2016
BISOTISSUEDInfinity Contracting Service11/09/2016
BISMHISSUEDInfinity Contracting Service11/09/2016
BIS—ISSUEDRed Hook Sign and Electric05/15/2014
BIS—ISSUEDRed Hook Sign and Electric05/15/2014
BISPLISSUEDRichards P and H Co03/12/2014
BISOTISSUEDRichards Plum & Heating Co07/05/2013
BISFBISSUEDRichards P&H Co03/25/2013
BISOTISSUEDRichards Plum & Heating Co03/22/2013
BISPLISSUEDRichards P and H Co03/12/2013
BISOTISSUEDRichards Plum & Heating Co03/12/2013
BISOTISSUEDDasny11/10/2010
BISPLISSUEDCatalano Plumbing & Heating09/13/2010
BISCCISSUEDThe Urban Group07/09/2010
BISCCISSUEDThe Urban Group07/09/2010
BISPLISSUEDRichards P and H Co05/11/2010
BISOTISSUEDMetrotech Contracting05/03/2010
BISFPISSUEDJem Fire Prevention03/31/2010
BISOTISSUEDMetropolitan Heat & Power Co01/06/2010
BIS—ISSUEDM.A. Angeliades01/06/2010
BISFBISSUEDMetropolitan HT & Power Co09/30/2009
BIS—ISSUEDM.A. Angeliades09/28/2009
+ 19 more permits on file
1 project · most recent 09/16/2025
Air Conditioning Systems Heating Systems Others
FiledStatusContractorScopeMake / Model / Capacity
09/16/2025Permit IssuedR.A.M.S. MechanicalAir Conditioning Systems, Heating Systems, Others
Cooling
Data-Aire GFWU-07034-C 6,800 CFM · Crac Unit ×6
GFWU-03534-C 3,800 CFM · Crac Unit ×3
Liebert DS053KD 8,400 CFM · Crac Unit ×9
Heating
Data-Aire GFWU-07034-C 6,800 BTU · Crac Unit ×6
GFWU-03534-C 3,800 BTU · Crac Unit ×3
Liebert DS053KD 8,400 BTU · Crac Unit ×9
Other
Liebert DDO 466A26 22,770 CFM · Crac Unit ×9
1 project · most recent 07/11/2025
General Wiring
FiledStatusContractorScope
07/11/2025Permit IssuedAujla ElectricGeneral Wiring
1 project · most recent 08/17/2026
Steel Concrete
FiledStatusContractorScope
08/17/2026Permit IssuedR.A.M.S. MechanicalSteel, Concrete
▾Special Inspection Requirements (DOB NOW) — 37
DateRequirementInspectorRole
07/30/2026FinalPanagiotis Koklanosprogress
07/30/2026Post-installed AnchorsMARISA HARTEspecial
09/12/2025Shutoff dampersMARISA HARTEenergy_progress
09/12/2025HVAC-R and service water piping design and insulationMARISA HARTEenergy_progress
09/12/2025Fire-Resistant Penetrations and JointsMARISA HARTEspecial
09/12/2025Heating SystemsMARISA HARTEspecial
09/12/2025Mechanical SystemsMARISA HARTEspecial
09/12/2025Energy Code Compliance InspectionsMARISA HARTEprogress
09/12/2025FinalFrank Ulisseprogress
09/12/2025HVAC-R and service water heating equipmentMARISA HARTEenergy_progress
09/12/2025HVAC-R and service water heating system controlsMARISA HARTEenergy_progress
09/12/2025Maintenance informationMARISA HARTEenergy_progress
07/29/2025HVAC-R and service water piping design and insulationMARISA HARTEenergy_progress
07/29/2025Maintenance informationMARISA HARTEenergy_progress
07/29/2025HVAC-R and service water heating system controlsMARISA HARTEenergy_progress
07/29/2025Shutoff dampersMARISA HARTEenergy_progress
07/29/2025Post-installed AnchorsMARISA HARTEspecial
07/29/2025Structural Steel - DetailsMARISA HARTEspecial
07/29/2025Structural Steel - High Strength BoltingMARISA HARTEspecial
07/29/2025Structural Steel - WeldingMARISA HARTEspecial
07/29/2025FinalPanagiotis Koklanosprogress
07/29/2025Fire-Resistant Penetrations and JointsMARISA HARTEspecial
07/29/2025Heating SystemsMARISA HARTEspecial
07/29/2025Mechanical SystemsMARISA HARTEspecial
07/29/2025Energy Code Compliance InspectionsMARISA HARTEprogress
Latest 25 of 37.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Medgar Evers CollegeEducationEntire building
Project B01205579 Alteration · Permit Entire · 04/10/2025
Project B00763394 Alteration · Approved · 09/21/2022
Project B07995060 Alteration · Permit Entire · 11/01/2022
Project B08015455 Alteration · Permit Entire · 10/31/2022
Project B08018909 Alteration · Permit Entire · 10/31/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 325 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch14
08/28/2026B00763394-I1Request digital key ↗
08/28/2026B00762724-I1Request digital key ↗
08/28/2026B00762447-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸Applications & Permits62
▸BISWORK PERMIT APPLICATION32
11/13/2017321396422Open ↗
11/13/2017321396422Open ↗
11/13/2017321396422Open ↗
Showing 3 of 32 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION23
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
Showing 3 of 23 on file for this type
▸BISPLACE OF ASSEMBLY6
10/25/2011310184467Open ↗
10/25/2011310184458Open ↗
11/04/2009310184458Open ↗
Showing 3 of 6 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
05/15/2018321396422Open ↗
▸Seals & Professional Certifications88
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION51
08/19/2019321396422Open ↗
08/19/2019321396422Open ↗
08/19/2019321396422Open ↗
Showing 3 of 51 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/28/2026B00763394-I1Open ↗
08/28/2026B00762447-I1Open ↗
08/21/2026B01205579-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/29/2026B01205579-S1Open ↗
08/29/2026B07995060-P2Open ↗
08/29/2026B07995060-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/29/2026B01205579-S1Open ↗
08/29/2026B01205579-I1Open ↗
08/29/2026B07995060-P2Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
09/24/2010320218732Open ↗
Showing 1 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
09/24/2010320218732Open ↗
Showing 1 of 4 on file for this type
▸BISProfessional and Owner Certification (POC3)2
07/10/2014320926717Open ↗
07/10/2014320888795Open ↗
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment29
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT14
11/20/2013320407083Open ↗
12/03/2011320407083Open ↗
08/16/2010310200813Open ↗
Showing 3 of 14 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT4
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING3
01/07/2015320407083Open ↗
07/02/2012320407083Open ↗
12/03/2011320407083Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
06/02/2016321396422Open ↗
10/14/2014320407083Open ↗
09/02/2014320407083Open ↗
▸BISEQUIPMENT USE PERMITS2
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
▸BISSIGN HANGER CERTIFICATE1
09/24/2010320218732Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
11/24/2010310026414Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
11/07/2014320407083Open ↗
▸Environmental & Asbestos23
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER12
12/06/2011320407083Open ↗
09/24/2010320218732Open ↗
10/09/2009320080256Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/21/2026B01205579-S1Open ↗
08/21/2026B01205579-I1Open ↗
08/20/2026B08018909-P1Open ↗
Showing 3 of 10 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/09/2016321396422Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
08/19/2019321396422Open ↗
08/19/2019321396422Open ↗
11/09/2016321396422Open ↗
Showing 3 of 7 on file for this type
▸BISTR8: Energy Code Progress Inspections1
03/19/2012320407083Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
08/19/2019321396422Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
11/09/2016321396422Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
11/09/2016321396422Open ↗
▸Approvals, Objections & Sign-offs55
▸BISADMINISTRATIVE OBJECTIONS15
09/10/2014320407083Open ↗
07/10/2014320926717Open ↗
07/10/2014320888795Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter14
08/28/2026B00763394-I1Open ↗
08/28/2026B00762447-I1Open ↗
08/20/2026B08015455-I1Open ↗
Showing 3 of 14 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION13
07/10/2014320926717Open ↗
07/10/2014320888795Open ↗
01/27/2011310026414Open ↗
Showing 3 of 13 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
09/14/2019321396422Open ↗
08/19/2019321396422Open ↗
05/03/2011320218732Open ↗
Showing 3 of 13 on file for this type
▸Cost, Insurance & Ownership20
▸BISCOST AFFIDAVIT20
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
09/14/2019321396422Open ↗
Showing 3 of 20 on file for this type
▸Filing & Intake Forms22
▸BISEFILING COVER SHEET13
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
06/02/2016321396422Open ↗
Showing 3 of 13 on file for this type
▸BISADDITIONAL INFORMATION4
08/08/2019321396422Open ↗
09/02/2014320407083Open ↗
10/25/2011310184467Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAI1 Form3
08/13/2026B07995060-P2Open ↗
08/13/2026B07995060-I1Open ↗
08/13/2026B07995060-P1Open ↗
▸BISBOROUGH INTAKE FORM2
09/14/2019321396422Open ↗
08/19/2019321396422Open ↗
▸Other Documents1
▸BISFIRE SUPP ANSUL APPROVL- FD-FSS1
10/27/2010320080256Open ↗