| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 171 BALTIC ST CO | 1 | 03/22/2026 |
| 171 BALTIC STREET CONDOMINIUM | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SHAKESPEARE, GORDON, VLADO ARCHITEC | 7 | 10/14/2025 |
| M-CON ENGINEERING, PC | 1 | 09/05/2024 |
| PIRO STUDIO LLC | 1 | 08/13/2024 |
| BARRY STRUCTURAL ENGINEERING, PLLC | 1 | 10/27/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| CONVERSANO ASSOCIATES, INC. | 18 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A & K CREATIVE CONSTRUCT* | General Contractor | 8 | 07/08/2026 |
| SUSTAINABLE STRATEGIES | General Contractor | 2 | 03/21/2026 |
| BRIAN & CO GENERAL CONTRACTING | General Contractor | 1 | 07/08/2026 |
| SIGNORE & SONS PLBG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TRIANGLE INSPECTION & TES | 7495 | 6 | 10/14/2025 |
| M-CON ENGINEERING | 7341 | 1 | 09/05/2024 |
| PIRO STUDIO LLC | 7503 | 2 | 08/13/2024 |
| BARRY STRUCTURAL ENGINEER | 749 | 1 | 10/27/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | A & K CREATIVE CONSTRUCT* | 01/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | A & K CREATIVE CONSTRUCT* | 01/13/2025 |
| DOB NOW | Solar | Signed-off | SUSTAINABLE STRATEGIES | 09/13/2024 |
| DOB NOW | Plumbing | Signed-off | SIGNORE & SONS PLBG CORP | 03/28/2024 |
| DOB NOW | Structural | Signed-off | A & K CREATIVE CONSTRUCT* | 03/05/2024 |
| DOB NOW | General Construction | Permit Issued | A & K CREATIVE CONSTRUCT* | 03/04/2024 |
| DOB NOW | General Construction | Signed-off | BRIAN & CO GENERAL CONTRA | 03/23/2022 |
| BIS | OT | ISSUED | ZOOM CONTRACTING INC | 03/26/2012 |
| BIS | OT | ISSUED | ZOOM CONTRACTING INC | 03/26/2012 |
| BIS | OT | ISSUED | ZOOM CONTRACTING INC | 12/20/2011 |
| BIS | OT | ISSUED | ZOOM CONTRACTING INC | 12/20/2011 |
| BIS | PL | ISSUED | AUTHENTIC PLBG CORP | 12/07/2011 |
| BIS | OT | ISSUED | ZOOM CONTRACTING INC | 12/06/2011 |
| BIS | MH | ISSUED | ZOOM CONTRACTING INC | 12/06/2011 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/14/2025 | Permit Issued | A & K CREATIVE CONSTRUCT* | Air Conditioning Systems | Cooling Mitsubishi Electric MXZ-SM48-NAM-U1 48,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/25/2025 | Complete | SOURCE ELECTRIC INC | 1 meters |
| 03/13/2024 | Complete | LENS ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2025 | Permit Issued | A & K CREATIVE CONSTRUCT* | Steel, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/15/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/18/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/18/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/31/2023 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 07/28/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/28/2023 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/14/2025 | Exterior Insulation and Finish Systems (EIFS) | Rajasekhar Sakhamuri | special |
| 10/14/2025 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 10/14/2025 | Fire-Resistance Rated Construction | Rajasekhar Sakhamuri | progress |
| 10/14/2025 | Insulation placement and R values | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Fenestration areas | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Fenestration and door U-factor and product ratings | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Fenestration air leakage | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Lighting controls | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Maintenance information | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Exterior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Lighting in dwelling units | Rajasekhar Sakhamuri | energy_progress |
| 10/14/2025 | Air barrier - visual inspection | Rajasekhar Sakhamuri | energy_progress |
| 10/29/2024 | Duct leakage testing, insulation and design | PIETRO ROSATO | energy_progress |
| 10/29/2024 | Maintenance information | PIETRO ROSATO | energy_progress |
| 09/03/2024 | Energy Code Compliance Inspections | Michelle Contri | progress |
| 09/03/2024 | Final | Michelle Contri | progress |
| 09/03/2024 | Air barrier - visual inspection | Michelle Contri | energy_progress |
| 09/03/2024 | Fire-Resistant Penetrations and Joints | Michelle Contri | special |
| 09/03/2024 | Structural Stability – Alterations of existing buildings | Michelle Contri | special |
| 08/23/2024 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 08/19/2024 | Fire-Resistant Penetrations and Joints | PIETRO ROSATO | special |
| 08/01/2024 | Energy Code Compliance Inspections | PIETRO ROSATO | progress |
| 08/01/2024 | HVAC-R and service water heating system controls | PIETRO ROSATO | energy_progress |
| 08/01/2024 | HVAC-R and service water heating equipment | PIETRO ROSATO | energy_progress |
| 08/01/2024 | HVAC-R and service water piping design and insulation | PIETRO ROSATO | energy_progress |