| B01360036 ↗ | 478 10 STREET BROOKLYN | Alteration | Permit Issued | 05/22/2026 | 09/24/2026 | Design SGVA Contractor A & K CREATIVE CONSTRUCT* | RENOVATION OF EXISTING TWO-FAMILY BUILDING. EXTERIOR WORK: NEW WINDOWS AT FRONT FACADE AND ENLARGEMENT OF SELECTED OPENINGS AT REAR FACADE W… |
| B01187061 ↗ | 312 21 STREET BROOKLYN | Alteration CO | Permit Issued | 07/11/2025 | 09/15/2026 | Design JENNIFER CRAMM Owner BNYDC Contractor NO LIMIT CONTRACTING INC | STRUCTURAL WORK FILED IN CONJUNCTION WITH RENOVATION TO EX. 2-FAMILY RESIDENCE. RE-FRAME THE 1ST FLOOR. ENLARGE WINDOW OPENINGS AT FRONT AND… |
| B01321033 ↗ | 5 TEMPLE COURT BROOKLYN | Alteration | Permit Issued | 12/29/2025 | 09/09/2026 | Design AHT ENGINEERING PLLC Contractor REDLINE CONSTR & MGMT LLC | PLUMBING SCOPE IN CONJUNCTION WITH INTERIOR RENOVATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| B01322447 ↗ | 628 CARLTON AVENUE BROOKLYN | Alteration CO | Permit Issued | 12/15/2025 | 09/08/2026 | Design HARPER ARCHITECTURE, PC Contractor RHY CONSTRUCTION LLC | RELOCATION OF THE STAIR OPENING AT EACH LEVEL, REINFOREMENT OF THE EXISTINGGARAGE ROOF FRAMING, TOTAL REPLACEMENT OF THE EXISTING ROOF FRAMI… |
| B01347842 ↗ | 17 MONTGOMERY PLACE BROOKLYN | Alteration | Permit Issued | 01/28/2026 | 08/25/2026 | Contractor STUDIO WOODMAN LLC Filer JOSEPH FELLNER | Structural work filed in conjunction with the renovation and enlargement of two family residence. Includes framing for two story enlargement… |
| M01289390 ↗ | 252 WEST 11 STREET MANHATTAN | Alteration CO | Permit Issued | 09/30/2025 | 08/17/2026 | Contractor ABA INNOVATIVE BUILDERS I | STRUCTURAL SCOPE OF WORK IN-CONJUNCTION WITH GENERAL CONSTRUCTION INTERIOR AND EXTERIOR RENOVATION APPLICATION, WITH NEW BULKHEAD NEW ROOF L… |
| Name | Projects together | Most recent |
|---|---|---|
| BARRY STRUCTURAL ENGINEERING, PLLC | 64 | 08/12/2026 |
| ERIC SAFYAN ARCHITECT PC | 12 | 05/29/2026 |
| MALETZ DESIGN | 11 | 11/12/2025 |
| ANAT SOUDRY ARCHITECT | 8 | 08/12/2026 |
| HARPER ARCHITECTURE, PC | 8 | 05/28/2026 |
| GREEN SOLUTIONS ENGINEERING & ENERG | 6 | 12/08/2025 |
| SGVA | 6 | 08/11/2026 |
| LUBRANO CIAVARRA ARCHITECTS, PLLC | 5 | 08/29/2025 |
| PH ARCHITECTURE+SUSTAINABLEDESIGNPC | 5 | 07/03/2025 |
| D'ANTONIO CONSULTING ENGINEERS | 4 | 03/25/2026 |
| DOUGLAS MUIR ARCHITECT | 3 | 05/23/2025 |
| Haynes Architecture PC | 3 | 06/13/2026 |
| CES ENGINEERING LLC | 2 | 08/29/2025 |
| DAVID CUNNINGHAM ARCHITECTURE PLANN | 2 | 11/07/2023 |
| ELLEN MARTIN ARCHITECT PC | 2 | 06/01/2026 |
| JENNIFER CRAMM | 2 | 06/16/2026 |
| JUDGE ARCHITECTURE PC | 2 | 06/11/2025 |
| Jennifer Cramm Architect PLLC | 2 | 06/16/2026 |
| MARCELLO FERRI ARCHITECT | 2 | 07/27/2025 |
| PIRO STUDIO LLC | 2 | 10/14/2025 |
| TAN ENGINEERING PC | 2 | 07/30/2025 |
| WILLIAM F. RYAN, JR. P.E. PC | 2 | 07/17/2023 |
| AHT ENGINEERING PLLC | 1 | 12/29/2025 |
| ANZ CONSULTING ENGINEERING, PLLC | 1 | 08/12/2026 |
| BENDIX ENGINEERING, P.C. | 1 | 05/28/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| AUROUS CONSTRUCTION COLL* | 7 | 04/22/2026 |
| CROSSFIELD PLBG.&HTG | 7 | 10/02/2025 |
| TK CONSTRUCTION OF NY,INC | 5 | 05/12/2026 |
| REDLINE CONSTR & MGMT LLC | 4 | 12/29/2025 |
| WULFING CONSTRUCTION LLC | 4 | 12/05/2024 |
| HENRY MYERS P & H, INC | 3 | 07/29/2024 |
| ORBIT PLBG & HTG INC | 3 | 11/12/2025 |
| REDLINE CONSTRUCTION & MA | 3 | 11/22/2024 |
| TUMEN, INC | 3 | 12/12/2025 |
| A & K CREATIVE CONSTRUCT* | 2 | 08/11/2026 |
| ABSOLUTE COMFORT SOLUTION | 2 | 11/15/2024 |
| AP PLUMBING & HVAC LLC | 2 | 02/01/2024 |
| ARCO PLBG AND HTG INC | 2 | 06/16/2026 |
| CITY LINE INTERIORS INC | 2 | 03/17/2026 |
| DONATO PLUMBING, INC | 2 | 08/29/2025 |
| DYNAMIC BLUE WATER MECH | 2 | 07/30/2025 |
| ETHOS PLUMBING CORP | 2 | 03/17/2026 |
| GTN RENOVATION INC | 2 | 04/26/2022 |
| HARPER DESIGN BUILD INC | 2 | 07/22/2021 |
| ICE AGE MECHANICAL CORP | 2 | 03/17/2026 |
| KBRNY, INC | 2 | 10/07/2022 |
| NEW PLBG & HTG CORP | 2 | 12/05/2024 |
| NO LIMIT CONTRACTING INC | 2 | 06/16/2026 |
| P.S.I. MECHANICAL | 2 | 03/14/2025 |
| PLUMB-IT MECHANICAL INC | 2 | 12/08/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| HARPER DESIGN BUILD | 3 | 11/22/2024 |
| 11 BLEECKER | 1 | 04/19/2022 |
| 110 HOYT STREET CONDOMINIUM | 1 | 07/27/2025 |
| 175 DIAMOND STREET CONDOMINIUM | 1 | 03/09/2023 |
| AKAM ASSOCIATES, INC. | 1 | 08/23/2024 |
| ALCAM PROPERTY MANAGEMENT LLC | 1 | 11/07/2023 |
| BEDNARK STUDIO, INC | 1 | 10/30/2024 |
| BNYDC | 1 | 06/16/2026 |
| ELIZABETH MALETZ, ARCHITECT | 1 | 03/15/2024 |
| Empire State Property Management | 1 | 06/01/2026 |
| JULIE F. KAY PLLC | 1 | 12/05/2024 |
| PLUS RENOVATION LLC | 1 | 07/03/2025 |
| SJLL, LLC | 1 | 08/17/2023 |
| VAN LEENEN DEVELOPMENTS LLC | 1 | 03/17/2026 |
| WATERGLADES TOWER 200 | 1 | 07/28/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| JOSEPH FELLNER | 17 | 08/12/2026 |
| EPAC BUILDING CONSULTING INC | 11 | 11/12/2025 |
| MUNICIPAL BUILDING CONSULTANTS | 7 | 05/28/2026 |
| JAM CONSULTANTS, INC. | 4 | 08/29/2025 |
| BMB BUILDING CONSULTING INC. | 3 | 11/07/2023 |
| RIZZO GROUP | 3 | 06/11/2025 |
| CONVERSANO ASSOCIATES, INC. | 2 | 08/11/2026 |
| EAB ENGINEERING PC | 2 | 08/01/2022 |
| J.A. EXPEDITING, LLC | 2 | 11/15/2024 |
| PH ARCHITECTURE+SUSTAINABLEDESIGNPC | 2 | 07/03/2025 |
| SOL BUILDING CONSULTING SERVICES | 2 | 06/01/2026 |
| THOMAS E. HAYNES, ARCHITECT | 2 | 03/14/2025 |
| ANZALONE ARCHITECTURE, PLLC | 1 | 06/16/2026 |
| BIG ORANGE EXPEDITING, INC | 1 | 02/27/2024 |
| BOYD CONSULTING, INC | 1 | 03/25/2021 |
| CAVALRY LLC | 1 | 01/07/2026 |
| CROSSFIELD PLUMBING & HEATING CORP | 1 | 08/20/2024 |
| ENKAY DESIGN & CONSULTING, LLC | 1 | 03/25/2026 |
| ERIC SAFYAN ARCHITECT PC | 1 | 12/12/2025 |
| JOSH MANES ARCHITECTURE, DPC | 1 | 05/03/2021 |
| LEVIN ENGINEERING PLLC | 1 | 05/15/2026 |
| METROPOLIS GROUP INC | 1 | 11/21/2022 |
| MK ARCHITECTURE PC | 1 | 05/08/2025 |
| NEXUS CONSULTING NYC, INC | 1 | 12/08/2025 |
| SATWIN ARCHITECT, PC | 1 | 03/26/2026 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01360036 ↗ | 478 10 STREET BROOKLYN | Alteration | Permit Issued | 05/22/2026 | 09/24/2026 | Design SGVA Contractor A & K CREATIVE CONSTRUCT* | RENOVATION OF EXISTING TWO-FAMILY BUILDING. EXTERIOR WORK: NEW WINDOWS AT FRONT FACADE AND ENLARGEMENT OF SELECTED OPENINGS AT REAR FACADE W… |
| B01187061 ↗ | 312 21 STREET BROOKLYN | Alteration CO | Permit Issued | 07/11/2025 | 09/15/2026 | Design JENNIFER CRAMM Owner BNYDC Contractor NO LIMIT CONTRACTING INC | STRUCTURAL WORK FILED IN CONJUNCTION WITH RENOVATION TO EX. 2-FAMILY RESIDENCE. RE-FRAME THE 1ST FLOOR. ENLARGE WINDOW OPENINGS AT FRONT AND… |
| B01321033 ↗ | 5 TEMPLE COURT BROOKLYN | Alteration | Permit Issued | 12/29/2025 | 09/09/2026 | Design AHT ENGINEERING PLLC Contractor REDLINE CONSTR & MGMT LLC | PLUMBING SCOPE IN CONJUNCTION WITH INTERIOR RENOVATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| B01322447 ↗ | 628 CARLTON AVENUE BROOKLYN | Alteration CO | Permit Issued | 12/15/2025 | 09/08/2026 | Design HARPER ARCHITECTURE, PC Contractor RHY CONSTRUCTION LLC | RELOCATION OF THE STAIR OPENING AT EACH LEVEL, REINFOREMENT OF THE EXISTINGGARAGE ROOF FRAMING, TOTAL REPLACEMENT OF THE EXISTING ROOF FRAMI… |
| B01347842 ↗ | 17 MONTGOMERY PLACE BROOKLYN | Alteration | Permit Issued | 01/28/2026 | 08/25/2026 | Contractor STUDIO WOODMAN LLC Filer JOSEPH FELLNER | Structural work filed in conjunction with the renovation and enlargement of two family residence. Includes framing for two story enlargement… |
| M01289390 ↗ | 252 WEST 11 STREET MANHATTAN | Alteration CO | Permit Issued | 09/30/2025 | 08/17/2026 | Contractor ABA INNOVATIVE BUILDERS I | STRUCTURAL SCOPE OF WORK IN-CONJUNCTION WITH GENERAL CONSTRUCTION INTERIOR AND EXTERIOR RENOVATION APPLICATION, WITH NEW BULKHEAD NEW ROOF L… |
| M00997959 ↗ | 159 EAST 78 STREET MANHATTAN | Alteration | Permit Issued | 01/30/2024 | 08/06/2026 | Design Haynes Architecture PC Contractor VECTRA CONSTRUCTION CORP | PROPOSED PLUMBING ON FLOORS 001 THRU 003. REMOVAL, RELOCATION AND NEW PLUMBING FIXTURES PROPOSED AS PER PLANS FILED HEREWITH. NO CHANGE TO U… |
| B00837845 ↗ | 257 HICKS STREET BROOKLYN | Alteration CO | Permit Issued | 03/28/2023 | 08/04/2026 | Design TAN ENGINEERING PC Contractor STEERING HOUSE CONSTRUCT Filer JAM CONSULTANTS, INC. | Convert from Two Family to a One Family Dwelling. General Construction and renovation throughout per plans. |
| B01395335 ↗ | 78 8 AVENUE BROOKLYN | Alteration | Permit Issued | 06/01/2026 | 08/03/2026 | Design ELLEN MARTIN ARCHITECT PC Contractor CROWN PLUMBING INC | Interior renovation and apartment combination of existing Units 2F & 2G including partition relocation, removal of one kitchen, bathroom ren… |
| B01384430 ↗ | 910 ST JOHNS PLACE BROOKLYN | Alteration | Permit Issued | 04/22/2026 | 07/27/2026 | Contractor AUROUS CONSTRUCTION COLL* | This is a filing to remove an existing deck and install a new steel deck as per drawings. |
| B00729484 ↗ | 344 20 STREET BROOKLYN | Alteration | Signed-off | 07/08/2022 | 07/06/2026 | Contractor EMDAD CONSTRUCTION INC | RENOVATION OF AN EXISTING TWO-FAMILY BUILDING. INTERIOR WORK TO INCLUDE, NEW NON LOAD-BEARING PARTITIONS, FINISHES, AND FITTINGS. EXTERIOR W… |
| B01393991 ↗ | 597 MAC DONOUGH STREET BROOKLYN | Alteration | Permit Issued | 05/12/2026 | 06/26/2026 | Contractor TK CONSTRUCTION OF NY,INC | Enlargement of opening at 1st Floor existing rear masonry wall. |
| M01377775 ↗ | 159 EAST 78 STREET MANHATTAN | Alteration | Filed — no permit on record | 03/27/2026 | — | Design Haynes Architecture PC | — |
| B01370611 ↗ | 375 2 STREET BROOKLYN | Alteration | Filed — no permit on record | 03/26/2026 | — | Design CHOSHIELDS STUDIO Filer SATWIN ARCHITECT, PC | — |
| B01018539 ↗ | 293 13 STREET BROOKLYN | Alteration | Signed-off | 04/18/2024 | 03/20/2026 | Contractor REDLINE CONSTR & MGMT LLC | STRUCTURAL SCOPE IN CONJUNCTION WITH HORIZONTAL AND VERTICAL ADDITION OF EXISTING 3 STORY + CELLAR BUILDING AS PER PLANS FILED HEREWITH. NO … |
| B01045741 ↗ | 293 13 STREET BROOKLYN | Alteration | Signed-off | 06/11/2024 | 03/20/2026 | Design GEO Contractor REDLINE CONSTR & MGMT LLC | SUPPORT AND EXCAVATION WORK FOR PARTIAL DEMO OF EXISTING REAR WALL FOR EXTENSION INTO REAR YARD AND THE LOWERING OF CELLAR AS PER PLANS FILE… |
| M01295401 ↗ | 534 WEST 149 STREET MANHATTAN | Alteration CO | Permit Issued | 10/02/2025 | 03/05/2026 | Design OSTERMIER ARCHITECTURE PLLC Contractor VESTA CONSTRUCTION, INC Filer CAVALRY LLC | WORK IS LIMITED TO INTERIOR WORK AND WINDOW REPLACEMENT,GENERAL CONSTRUCTION INCLUDING LOAD BEARING & NON-LOADING BEARING PARTITIONS AND FIN… |
| B01038008 ↗ | 344 STATE STREET BROOKLYN | Alteration | Permit Issued | 04/25/2024 | 02/25/2026 | Design MALETZ DESIGN Contractor PARADISE CONSTRUCTION GRO | SUBSEQUENT FILING FOR STRUCTURAL WORKS WITH NEW CONCRETE FOOTINGS FOR EXISTING COLUMNS AT CELLAR, A NEW SLAB-ON-GRADE AT CELLAR, AND NEW WOO… |
| B01222695 ↗ | 1055 HERKIMER STREET BROOKLYN | Alteration | Permit Issued | 05/23/2025 | 02/17/2026 | Design DOUGLAS MUIR ARCHITECT Contractor DOMINGUEZ CONSTRUCTION C | Addition of deck at First floor with stair to yard, plus one glazed door at exterior wall at deck level. |
| B01278169 ↗ | 233A CLINTON STREET BROOKLYN | Alteration | Permit Issued | 12/11/2025 | 01/14/2026 | Contractor MONELLO ENTERPRISES INC | INSTALLATION OF NEW ROOFTOP STEEL DUNNAGE AND BASEMENT FRAMING TO SUPPORT A NEW MECHANICAL UNIT, AND REINFORCEMENT OF NEW DUCT PENETRATIONS.… |
| X01285374 ↗ | 4 ROCHELLE STREET BRONX | Alteration | Permit Issued | 09/22/2025 | 01/07/2026 | Design ERIC SAFYAN ARCHITECT PC Contractor C.I. CONTRACTING CORP Filer JOSEPH FELLNER | This application is filed for the structural scope associated with proposed horizontal additions at the Basement, 1st Floor, and 2nd Floor, … |
| B00884732 ↗ | 70 EAST 4 STREET BROOKLYN | Alteration CO | Permit Issued | 07/19/2023 | 12/22/2025 | Design HARPER ARCHITECTURE, PC Contractor ORBIT MECHANICAL SOLUTIO* | Subsequent filing for Structural work. Scope of work is new window openings at rear masonry wall, partial reinforcement of 2nd floor framing… |
| B01242207 ↗ | 359 11 STREET BROOKLYN | Alteration | Signed-off | 07/24/2025 | 12/16/2025 | Contractor TUMEN, INC Filer ERIC SAFYAN ARCHITECT PC | Structural Work in Conjunction with Architectural filing. New Rear Porch. |
| B01033617 ↗ | 293 13 STREET BROOKLYN | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 04/19/2024 | 12/01/2025 | Design HARPER ARCHITECTURE, PC Contractor REDLINE CONSTR & MGMT LLC | ALTCO FILED TO CHANGE EGRESS OF A THREE(3) FAMILY WITH INTERIOR RENOVATION, HORIZONTAL AND VERTICAL ADDITION TO THE EXISTING 3 STORY + CELLA… |
| B01094604 ↗ | 413A 6 AVENUE BROOKLYN | Alteration | Signed-off | 08/15/2024 | 10/27/2025 | Design SGVA Contractor TK CONSTRUCTION OF NY,INC | Subsequent application for structural work as indicated. |
| M01216736 ↗ | 144 WEST 18 STREET MANHATTAN | Alteration | Permit Issued | 05/13/2025 | 10/24/2025 | Contractor CASTLES UNLIMITED LLC Filer RIZZO GROUP | Replace existing HVAC unit with new with related ductwork and accessories |
| Q01149385 ↗ | 16-59 STEPHEN STREET QUEENS | Alteration | Permit Issued | 01/06/2025 | 10/23/2025 | Contractor MIKE'S HOME SOLUTIONS LLC | STRUCTURAL MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01254609 ↗ | 7 WEST 96 STREET MANHATTAN | Alteration | Signed-off | 07/30/2025 | 10/17/2025 | Design TAN ENGINEERING PC Contractor D & D 1 CORPORATION Filer JAM CONSULTANTS, INC. | Renovate exist. Kitchen in same location, interior non structural partitions to be modified, structural work limited to steel lintels at new… |
| B01222543 ↗ | 670 EAST 18 STREET BROOKLYN | Alteration | Permit Issued | 06/05/2025 | 10/07/2025 | Contractor AUROUS CONSTRUCTION COLL* | This application is filed for the structural scope associated with new lintels for enlarged openings at existing rear walls, A new steel bea… |
| B01242612 ↗ | 188 BERGEN STREET BROOKLYN | Alteration | Filed — no permit on record | 07/11/2025 | — | Design LEVIN ENGINEERING PLLC Filer JOSEPH FELLNER | — |
| B00910123 ↗ | 418 5 STREET BROOKLYN | Alteration | Signed-off | 08/11/2023 | 06/05/2025 | Design MALETZ DESIGN Contractor HOME AIR INC | subsequent filing for plumbing works. |
| B01093061 ↗ | 489 7 AVENUE BROOKLYN | Alteration CO | Permit Issued | 09/19/2024 | 05/06/2025 | Design ERIC SAFYAN ARCHITECT PC Contractor CITY LINE INTERIORS Filer JOSEPH FELLNER | Structural work filed in conjunction with the renovation of four story multiple dwelling. Reinforce some existing framing. Opening in rear w… |
| B00970457 ↗ | 110 HOYT STREET BROOKLYN | Alteration | Signed-off | 12/22/2023 | 04/08/2025 | Design MARCELLO FERRI ARCHITECT Contractor CITYWIDE PLBG HTG & SPKLS | Reinforcement of existing Third Floor joists above Second Floor bedroom and new steel angle for removal of Second Floor chimney. Submitting … |
| M01099166 ↗ | 140 WEST 10 STREET MANHATTAN | Alteration | Signed-off | 01/07/2025 | 04/08/2025 | Owner PLUS RENOVATION LLC Contractor PLUS RENOVATION LLC | VRF TYPE SPLIT HEAT PUMP UNIT SERVING FULLY DUCTED AIR HANDLING UNITS, CONTROLS AND CONDENSATE SYSTEMS. VENTILATING SYSTEMS SERVING THE WC. |
| B00719832 ↗ | 611 11 STREET BROOKLYN | Alteration CO | Permit Issued | 05/05/2022 | 02/26/2025 | Design JSPY ARCHITECTURE Contractor RED OAK RENOVATIONS CORP | subsequent filing for plumbing works. |
| B00724212 ↗ | 171 BALTIC STREET BROOKLYN | Alteration CO | Permit Issued | 05/19/2022 | 01/23/2025 | Design SGVA Contractor A & K CREATIVE CONSTRUCT* | Vertical enlargement - roof structure meets the requirements for floor area. |
| B00937438 ↗ | 608 3 STREET BROOKLYN | Alteration | Signed-off | 11/02/2023 | 12/23/2024 | Design MALETZ DESIGN Contractor AUROUS CONSTRUCTION COLL* | subsequent filing for plumbing works. |
| B00706767 ↗ | 591 7 STREET BROOKLYN | Alteration | Signed-off | 07/07/2022 | 12/18/2024 | Design SGVA Contractor BRIAN & CO GENERAL CONTRA | Subsequent filing for selective moderate Structural work as indicated. |
| B00753553 ↗ | 91 8 AVENUE BROOKLYN | Alteration CO | Permit Issued | 07/19/2022 | 11/25/2024 | Design ENGINEERING SOLUTIONS Contractor M DADDIO INC | Subsequent application to install a wet pipe sprinkler system and components throughout, tie into Existing 3 Fire Service. Appl filed in co… |
| B00913224 ↗ | 296 HICKS STREET BROOKLYN | Alteration | Signed-off | 08/10/2023 | 11/22/2024 | Design CES ENGINEERING LLC Owner WATERGLADES TOWER 200 Contractor R. SUTTON & CO LLC Filer JAM CONSULTANTS, INC. | Structural scope associated with Cellar level to repair exist. Masonry wall and slab on grade, Basement pour concrete Pier footings for Rear… |
| M00994386 ↗ | 154 PERRY STREET MANHATTAN | Alteration | Signed-off | 03/15/2024 | 09/19/2024 | Design MALETZ DESIGN Owner AKAM ASSOCIATES, INC. Contractor ETHOS PLUMBING CORP | subsequent filing for plumbing works. |
| B00858695 ↗ | 15 ORIENT AVENUE BROOKLYN | Alteration | Signed-off | 04/14/2023 | 08/27/2024 | Contractor ECOSTRUCT LLC | STRUCTURAL SCOPE IN CONJUNCTION WITH THE INTERIOE RENOVATION OF AN EXISTING ONE FAMILY HOUSE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, … |
| B00906156 ↗ | 623 8 AVENUE BROOKLYN | Alteration | Signed-off | 09/08/2023 | 08/13/2024 | Design ANAT SOUDRY ARCHITECT Contractor WULFING CONSTRUCTION LLC Filer JOSEPH FELLNER | Replacement of steel landing at 2nd Floor, replacement of exterior steel stairs from landing to existing garage roof and to grade level, ste… |
| B01066465 ↗ | 27 MINNA STREET BROOKLYN | Alteration | Permit Issued | 06/26/2024 | 08/08/2024 | Design MALETZ DESIGN Contractor DPH PLUMBING & HTG CORP | PROPOSED RENOVATION OF EXISTING 2 FAMILY HOUSE ON THE FIRST FLOOR LEVEL. NO CHANGE IN USE, EGRESS AND OCCUPANCY. |
| B01030679 ↗ | 60 JORALEMON STREET BROOKLYN | Alteration | Signed-off | 05/14/2024 | 07/08/2024 | Design ANAT SOUDRY ARCHITECT Contractor BAYSIDE BUILDERS INC Filer JOSEPH FELLNER | Structural work filed in conjunction with the partial renovation of one family residence. Framing for rear porch at 1st floor. Lintels for … |
| B01044482 ↗ | 98 GARFIELD PLACE BROOKLYN | Alteration | Signed-off | 05/09/2024 | 06/25/2024 | Design ANAT SOUDRY ARCHITECT Owner JULIE F. KAY PLLC Contractor WULFING CONSTRUCTION LLC Filer JOSEPH FELLNER | PLUMBING WORK FILED IN CONJUNCTION WITH INTERIOR RENOVATION OF SECOND FLOOR OF A 2-FAMILY RESIDENCE |
| B00571534 ↗ | 53 ST PAULS PLACE BROOKLYN | Alteration CO | Permit Issued | 08/13/2021 | 05/24/2024 | Design ERIC SAFYAN ARCHITECT PC Owner BEDNARK STUDIO, INC Contractor BEDNARK STUDIO, INC Filer JOSEPH FELLNER | Structural work filed in conjunction with the renovation and enlargement of the building. Includes framing for the enlargement, wall opening… |
| B00763748 ↗ | 291 6 AVENUE BROOKLYN | Alteration CO | Permit Issued | 07/05/2022 | 05/24/2024 | Design ERIC SAFYAN ARCHITECT PC Contractor NYC SPECIAL CONTRACTORS Filer JOSEPH FELLNER | SUPPORT OF EXCAVATION FOR THE HORIZONTAL EXTENSION OF EXISTING BUILDING |
| B00952979 ↗ | 174 STERLING STREET BROOKLYN | Alteration CO | Permit Issued | 11/07/2023 | 05/08/2024 | Design MALETZ DESIGN Contractor AUROUS CONSTRUCTION COLL* | This application is filed for the structural scope associate4d with basement level concrete pier footings for rear deck, first floor, steel … |
| B00551887 ↗ | 525 CLINTON ST. BROOKLYN | Alteration CO | Permit Issued | 07/20/2021 | 05/02/2024 | Design R.J. MCGEE ENGINEERING, PLLC Contractor AMERIFLO PLUMBING AND HEA | Subsequently filed structural work associated with the reinforcement of the existing roof framing for future green roof and solar panel load… |
| B00360098 ↗ | 33 LINCOLN PLACE BROOKLYN | Alteration | Signed-off | 10/14/2020 | 04/19/2024 | Owner SJLL, LLC Contractor P JOE CONSTRUCTION CORP Filer NYCCODE LLC | This application is filed for the Structural Scope associated with the proposed enlargement of an existing townhouse. The proposed scope inc… |
| M00925003 ↗ | 333 EAST 68 STREET MANHATTAN | Alteration | Signed-off | 09/06/2023 | 04/08/2024 | Contractor WALKER RIDGE CONST NY LLC | MECHANICAL WORK TO REPLACE EXISTING AC UNITS AND INSTALL PTAC UNITS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| B00721693 ↗ | 351 CLINTON STREET BROOKLYN | Alteration CO | Permit Issued | 04/28/2022 | 03/22/2024 | Design CES ENGINEERING LLC Contractor R. SUTTON & CO LLC Filer JAM CONSULTANTS, INC. | Structural reinforcements related to New Outdoor rear deck at the first floor. |
| B01010816 ↗ | 533 9 STREET BROOKLYN | Alteration CO | Filed — no permit on record | 03/11/2024 | — | Design ERIC SAFYAN ARCHITECT PC Filer JOSEPH FELLNER | — |
| M00597143 ↗ | 41 CONVENT AVENUE MANHATTAN | Alteration | Permit Issued | 12/20/2021 | 02/22/2024 | Design JOSH MANES ARCHITECTURE, DPC Contractor KBRNY, INC | REPLACE, RELOCATE AND ADD PLUMBING FIXTURES AS PER SCHEDULE B AND PLANS FILED HEREWITH. NO CHANGE, ETC. |
| B00702528 ↗ | 562 2 STREET BROOKLYN | Alteration | Signed-off | 03/28/2022 | 02/16/2024 | Design HARPER ARCHITECTURE, PC Contractor ARIES CONSTRUCTION CO,INC | Subsequent filing for enlarging openings at rear masonry wall, extend 1fl rear steel deck, steel stair partial reinforcement of exist rear a… |
| B00890853 ↗ | 427 HANCOCK STREET BROOKLYN | Alteration | Signed-off | 07/03/2023 | 02/16/2024 | Contractor MODERN STEEL CONSTRUCTION | New outdoor structural steel deck at rear of 1st Floor. |
| B00729802 ↗ | 543 2 STREET BROOKLYN | Alteration | Signed-off | 10/07/2022 | 02/01/2024 | Design DOUGLAS MUIR ARCHITECT Contractor O&B ASSOCIATES GROUP CORP | Work consists of the addition of a steel deck and stair at the rear facade of the house plus modifications to the concrete stair well from t… |
| B00672104 ↗ | 624 3 STREET BROOKLYN | Alteration | Signed-off | 06/30/2022 | 01/31/2024 | Design HARPER ARCHITECTURE, PC Contractor WULFING CONSTRUCTION LLC | Subsequent application to modify Plumbing fixtures . |
| B00895904 ↗ | 116 ST JAMES PLACE BROOKLYN | Alteration | Signed-off | 07/03/2023 | 01/25/2024 | Design MALETZ DESIGN Contractor AUROUS CONSTRUCTION COLL* | subsequent filing for plumbing works (bathroom). |
| B00692393 ↗ | 26 APOLLO STREET BROOKLYN | Alteration | Signed-off | 04/05/2022 | 01/03/2024 | Design HEATHER BRAUN, RA Contractor NY CLASS CONSTRUCTION LLC | SUBSEQUENT APPLICATION TO MODIFY PLUMBING FIXTURES. REM/RPL EXIST. FIXTURES AS INDICATED IN DEMO PLANS. FURNISH AND INSTALL A COMPLETELY OPE… |
| B00915982 ↗ | 43 JORALEMON STREET BROOKLYN | Alteration | Signed-off | 09/25/2023 | 12/28/2023 | Design JENNIFER CRAMM Contractor NO LIMIT CONTRACTING INC Filer MK ARCHITECTURE PC | Plumbing filed in conjunction with Interior Renovations as per plans. No Change in Use, Egress or Occupancy. |
| M00933714 ↗ | 143 EAST 62 STREET MANHATTAN | Alteration | Permit Issued | 09/16/2023 | 12/28/2023 | Design Haynes Architecture PC Contractor VECTRA CONSTRUCTION CORP | Proposed lintel over 1st floor front exterior door openings and proposed header to sister exsitign stair trimmer @ 3rd floor stair opening. … |
| B00876560 ↗ | 575 5 STREET BROOKLYN | Alteration | Signed-off | 06/27/2023 | 11/09/2023 | Design ANAT SOUDRY ARCHITECT Contractor BOXWOOD CONSTRUCTION LLC Filer JOSEPH FELLNER | STRUCTURAL WORK RELATED TO LOWERING A PORTION OF THE CELLAR SLAB AND REPLACING CELLAR COLUMNS WITH NEW STEEL COLUMNS |
| B08020047 ↗ | 257 6 AVENUE BROOKLYN | Alteration CO | Permit Issued | 10/25/2022 | 11/03/2023 | Design ERIC SAFYAN ARCHITECT PC Contractor TK CONSTRUCTION OF NY,INC Filer JOSEPH FELLNER | Plumbing work filed in conjunction with the renovation of this two family residence. |
| B00473229 ↗ | 415 6 AVENUE BROOKLYN | Alteration | Signed-off | 03/24/2021 | 11/01/2023 | Design JAMES KOSTER ARCHITECT, PLLC Contractor SAHARA CONTRACTING CORP | GENERAL CONSTRUCTION WORK FOR NEW ROOF BULKHEAD AND ROOF TERRACE FOR AN EXISTING 2-FAMILY RESIDENCE. STRUCTURAL FRAMING AT ROOF FOR NEW ROOF… |
| B00729264 ↗ | 43 PARK PLACE BROOKLYN | Alteration CO | Permit Issued | 05/19/2022 | 09/18/2023 | Design ERIC SAFYAN ARCHITECT PC Contractor TUMEN, INC Filer JOSEPH FELLNER | Plumbing work filed in conjunction with the renovation of the building |
| B00804135 ↗ | 1107 PARK PLACE BROOKLYN | Alteration | Permit Issued | 01/20/2023 | 07/14/2023 | Contractor AVJ INTERIORS LLC | Repairs and reinforcement of existing 2nd Floor framing at stair opening. |
| Q00818337 ↗ | 87-38 69 AVENUE QUEENS | Alteration | Signed-off | 04/26/2023 | 06/24/2023 | Design YAO W GUO ARCHITECT, PC Contractor EMILIANO CONSTRUCTION COR | Renovate attic with added dormers and access stair to create an occupied 3rd Floor. Replace cellar stair. Renovate kitchen in place. Renovat… |
| B00401893 ↗ | 69 CRANBERRY STREET BROOKLYN | Alteration | Signed-off | 11/03/2020 | 05/09/2023 | Contractor RA SOMERBY Filer METROPOLIS GROUP INC | install plywood sheathing to building, framing for relocated window opening. No change to use egress or occupancy |
| M00706079 ↗ | 11 BLEECKER STREET MANHATTAN | Alteration | Signed-off | 04/19/2022 | 04/24/2023 | Owner 11 BLEECKER Contractor A&L CONSTRUCTION SRVCS Filer RIZZO GROUP | Filing Structural modifications as per plans filed herewith. |
| B00531522 ↗ | 187 6 AVENUE BROOKLYN | Alteration CO | Permit Issued | 06/05/2021 | 02/07/2023 | Contractor RADISA MLADENOVIC | STRUCTURAL WORK IN CONJUNCTION WITH BUILDING RENOVATION |
| B00714208 ↗ | 18 FILLMORE PLACE BROOKLYN | Alteration | Signed-off | 04/11/2022 | 12/09/2022 | Contractor ABSOLUTE COMFORT SOLUTION Filer J.A. EXPEDITING, LLC | THIS APPLICATION IS FOR THE STRUCTURAL SCOPE ASSOCIATED WITH A NEW CONCRETE RETAINING WALL& FOOTING AT THE REAR YARD& THE REINFORCEMENT OF T… |
| B00711743 ↗ | 68 ST JAMES PLACE BROOKLYN | Alteration | Permit Issued | 05/03/2022 | 12/08/2022 | Design ANAT SOUDRY ARCHITECT Contractor BNH CONSTRUCTION NY INC Filer JOSEPH FELLNER | STRUCTURAL PLANS FILED IN CONJUNCTION WITH BUILDING RENOVATION. NEW LINTELS AT THE REAR WALL, STRUCTURE FOR A REAR PORCH, STEEL SUPPORT FOR … |
| B00724540 ↗ | 18 FILLMORE PLACE BROOKLYN | Alteration CO | Permit Issued | 06/07/2022 | 10/28/2022 | Design LESTER KATZ, NCARB Contractor ABSOLUTE COMFORT SOLUTION Filer J.A. EXPEDITING, LLC | HEREBY FILING TO CONVERT 2 FAMILY TO 1 FAMILY DWELLING. LOWER EXISTING CELLAR, INTERIOR AND EXTERIOR RENOVATION OF RENOVATION. |
| M00627643 ↗ | 27 KING STREET MANHATTAN | Alteration | Signed-off | 01/12/2022 | 08/25/2022 | Contractor BOLSTER.US,INC | filed for the structural scope consisting of a proposed mezzanine level to an existing apartment and the relocation of the stair to the mezz… |
| B00504293 ↗ | 597 6 STREET BROOKLYN | Alteration | Signed-off | 04/21/2021 | 07/19/2022 | Design ANAT SOUDRY ARCHITECT Contractor WULFING CONSTRUCTION LLC Filer JOSEPH FELLNER | Structural plans for rear porch. |
| B00475515 ↗ | 431 4 STREET BROOKLYN | Alteration | Signed-off | 03/12/2021 | 05/26/2022 | Design HARPER ARCHITECTURE, PC Contractor HARPER DESIGN BUILD INC | DEMOLISH AND ERECT NEW INTERIOR PARTITIONS, FLOOR FINISHES & PARTIAL CEILING: NEW KITCHEN CABINETS AND APPLIANCES, NEW PLUMBING FIXTURES AND… |
| B00497039 ↗ | 633 CARROLL STREET BROOKLYN | Alteration | Permit Issued | 09/24/2021 | 05/26/2022 | Contractor N.P. CLASSIC CONSTR CORP | This application is filed for the structural scope associated with a rear deck at the firs floor reinforcement of the existing timber framin… |
| B00551268 ↗ | 57 ST MARKS AVENUE BROOKLYN | Alteration | Signed-off | 07/14/2021 | 05/18/2022 | Design ANAT SOUDRY ARCHITECT Contractor NYC BUILDERS CNTRCTNG GR Filer JOSEPH FELLNER | Structural work filed in conjunction with the alteration of the residence. Minor enlargement at the 1st floor rear. Modification to the exis… |
| B00581214 ↗ | 205 29 STREET BROOKLYN | Alteration CO | Permit Issued | 08/24/2021 | 05/03/2022 | Design MALETZ DESIGN Contractor AUROUS CONSTRUCTION COLL* | Subsequent filing for plumbing works. |
| B00668209 ↗ | 423 10 STREET BROOKLYN | Alteration | Signed-off | 02/10/2022 | 04/08/2022 | Design SGVA Contractor HENRY MYERS P & H, INC | Subsequent application to modify plumbing fixtures. |
| B00629048 ↗ | 217 16 STREET BROOKLYN | Alteration | Signed-off | 11/13/2021 | 04/07/2022 | Contractor H&M RENOVATION AND MORE I | Addition of an outdoor structural steel deck 20'-0 x 8'-0 at rear yard. No change to use or egress to the building. |
| B00707935 ↗ | 536 PROSPECT AVENUE BROOKLYN | Alteration | Filed — no permit on record | 04/06/2022 | — | — | |
| B00467730 ↗ | 47 SHERMAN STREET BROOKLYN | Alteration | Signed-off | 02/25/2021 | 02/28/2022 | Contractor AMM GEN'L CONTRACTING INC Filer EAB ENGINEERING PC | REMOVE / RELOCATE OR REPLACE PLUMBING FIXTURES IN EXISITNG TWO FAMILY DWELLING. |
| B00637540 ↗ | 35 LEFFERTS AVENUE BROOKLYN | Alteration | Signed-off | 12/07/2021 | 02/16/2022 | Contractor GTN RENOVATION INC | INTERIOR RENOVATIONS, ASSOCIATED PLUMBING WORK AND HVAC WORK, AND EXTERIOR ENVELOPE REPAIRS. NO CHANGE TO USE, EGRESS OR OCCUPANCY. |
| B00601656 ↗ | 339 UNION STREET BROOKLYN | Alteration | Signed-off | 11/23/2021 | 01/21/2022 | Contractor PRO RENO INC | PROPOSE STRUCTURAL WORK INCONJUNCTION WITH ARCH DESIGN AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. |
| B00467744 ↗ | 47 SHERMAN STREET BROOKLYN | Alteration | Signed-off | 02/25/2021 | 01/19/2022 | Contractor DFE CONTRACTOR LLC Filer EAB ENGINEERING PC | RENOVATION OF AN EXISTING 2-FAMILYRESIDENCE. WORK TO INCLUDE THE CONSTRUCTION OF NON-LOADBEARING PARTITIONS, FINISHES, AND FITTINGS. NO CHAN… |
| B00481874 ↗ | 364 STERLING PLACE BROOKLYN | Alteration CO | Permit Issued | 03/17/2021 | 01/04/2022 | Design ERIC SAFYAN ARCHITECT PC Contractor PULATANI BUILDERS INC Filer JOSEPH FELLNER | Renovation of two-family residence. Partition work, replace windows rear porch. Obtain C.O. |
| B00590882 ↗ | 339 UNION STREET BROOKLYN | Alteration | Signed-off | 10/14/2021 | 12/22/2021 | Contractor PRO RENO INC | PROPOSE COMBINING (2) EXISTING APARTMENT UNITS #2 & #3 , WORK INCLUDES MINOR PARTITION, & INTERIOR FINISHED AS PER PLAN. PLUMBING WORK WILL … |
| B00509118 ↗ | 1184 UNION STREET BROOKLYN | Alteration | Signed-off | 05/06/2021 | 11/01/2021 | Design ERIC SAFYAN ARCHITECT PC Contractor TUMEN, INC Filer JOSEPH FELLNER | Structural work filed in conjunction with the renovation of one family residence. Replace beams and columns in the cellar. Structure for reb… |
| B00549243 ↗ | 1319 PROSPECT AVENUE BROOKLYN | Alteration | Signed-off | 07/05/2021 | 10/20/2021 | Design JUDGE ARCHITECTURE PC Contractor GRD CONSTRUCTION INC Filer RIZZO GROUP | GC-RENO OF EXIST BAS, 1ST & 2ND FLS NEW PARTITIONS, FINISHES, DECK @ REAR, SIDING, REP INSUL @ ROF NEW ENTRY PORCH & STAIRS STRUCT - STEEL … |
| B00550617 ↗ | 161 PRESIDENT STREET BROOKLYN | Alteration | Signed-off | 07/06/2021 | 08/26/2021 | Design WILLIAM F. RYAN, JR. P.E. PC Contractor TK CONSTRUCTION OF NY,INC | Subsequent application to Modify Plumbing fixtures. |
| B00507747 ↗ | 358 EASTERN PARKWAY BROOKLYN | Alteration | Permit Issued | 04/22/2021 | 08/18/2021 | Design MALETZ DESIGN Contractor DMA CONTRACTING INC | Superseded expired Alt 2# 321676469. NEW GUARDRAIL AT ROOF LEVEL. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B00490115 ↗ | 431 4 STREET BROOKLYN | Alteration | Signed-off | 06/03/2021 | 08/09/2021 | Owner HARPER DESIGN BUILD Contractor HARPER DESIGN BUILD INC | FILING FOR THE STRUCTURAL SCOPE ASSOCAITED WITH A NEW OUTDOOR REAR DECK AT THE FIRST FLOOR AND REINFORCEMENT OF THE EXISTING TIMBER FRAMING … |
| B00512779 ↗ | 206 17 STREET BROOKLYN | Alteration | Signed-off | 04/30/2021 | 05/25/2021 | Design ERIC SAFYAN ARCHITECT PC Contractor J'S CUSTOM CONTRACTING IN | LEGALIZE REAR PORCH TO RESOLVE VIOLATION #39026689H. NO CHANGE TO USE, OCCUPANCY OR EGRESS. |
| B00502718 ↗ | 849 CARROLL STREET BROOKLYN | Alteration | Signed-off | 05/03/2021 | 05/19/2021 | Contractor KBRNY, INC | INSTALLATION OF A LINTEL TO CREATE AN OPENING IN AN INTERIOR BEARING WALL AT THE SECOND FLOOR. |
| B00481559 ↗ | 306 14 STREET BROOKLYN | Alteration | Signed-off | 03/25/2021 | 05/07/2021 | Contractor REDLINE CONSTRUCTION & MA Filer BOYD CONSULTING, INC | This application is filed for the structural scope associated with the proposed removal of the existing fireplace at the cellar level and th… |
| B00416234 ↗ | 115 WILLOW STREET BROOKLYN | Alteration | Signed-off | 11/10/2020 | 05/01/2021 | Contractor PAUL QUINN PLBG & HTG INC Filer JAM CONSULTANTS, INC. | MODIFICATION TO PLUMBING AND GAS FIXTURES FOR MASTER BATHROOM, KITCHEN AND LAUNDRY ROOM. |
| B00488195 ↗ | 710 GREENWOOD AVENUE BROOKLYN | Alteration | Filed — no permit on record | 03/31/2021 | — | — |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 08/20/2026 | Concrete - Cast-In-Place | 478 10 STREET | — | special |
| 08/20/2026 | Structural Steel - Details | 478 10 STREET | — | special |
| 08/20/2026 | Final | 478 10 STREET | — | progress |
| 08/20/2026 | Structural Steel - High Strength Bolting | 478 10 STREET | — | special |
| 08/20/2026 | Structural Stability – Alterations of existing buildings | 478 10 STREET | — | special |
| 08/20/2026 | Structural Cold-Formed Steel | 478 10 STREET | — | special |
| 08/20/2026 | Structural Steel - Welding | 478 10 STREET | — | special |
| 06/24/2026 | Structural Stability – Alterations of existing buildings | 91 8 AVENUE | MICHAEL BARRY | special |
| 06/18/2026 | Maintenance information | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Exterior lighting power | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Lighting controls | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Protection of exposed foundation insulation | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Lighting in dwelling units | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Air barrier - visual inspection | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Subsurface Investigations (Borings/Test Pits) | 628 CARLTON AVENUE | BRIAN FLYNN | special |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | 291 6 AVENUE | Eric Safyan | special |
| 06/18/2026 | Structural Stability – Alterations of existing buildings | 291 6 AVENUE | MICHAEL BARRY | special |
| 06/18/2026 | Fire-Resistance Rated Construction | 291 6 AVENUE | Eric Safyan | progress |
| 06/18/2026 | Energy Code Compliance Inspections | 291 6 AVENUE | Eric Safyan | progress |
| 06/18/2026 | Fenestration air leakage | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Metering | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Insulation placement and R values | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Fenestration areas | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/18/2026 | Fenestration and door U-factor and product ratings | 291 6 AVENUE | Eric Safyan | energy_progress |
| 06/11/2026 | Structural Stability – Alterations of existing buildings | 159 EAST 78 STREET | MICHAEL BARRY | special |
| 06/11/2026 | Structural Steel - Details | 159 EAST 78 STREET | — | special |
| 06/11/2026 | Structural Cold-Formed Steel | 159 EAST 78 STREET | MICHAEL BARRY | special |
| 06/11/2026 | Masonry | 159 EAST 78 STREET | MICHAEL BARRY | special |
| 06/11/2026 | Concrete - Cast-In-Place | 159 EAST 78 STREET | MICHAEL BARRY | special |
| 05/29/2026 | Energy Code Compliance Inspections | 78 8 AVENUE | ELLEN MARTIN | progress |
| 05/29/2026 | Metering | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Fenestration areas | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Fenestration and door U-factor and product ratings | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Lighting controls | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Insulation placement and R values | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Air barrier - visual inspection | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Lighting in dwelling units | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Protection of exposed foundation insulation | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Exterior lighting power | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Fenestration air leakage | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Maintenance information | 291 6 AVENUE | Eric Safyan | energy_progress |
| 05/29/2026 | Fire-Resistance Rated Construction | 291 6 AVENUE | Eric Safyan | progress |
| 05/29/2026 | Energy Code Compliance Inspections | 291 6 AVENUE | Eric Safyan | progress |
| 05/29/2026 | Structural Stability – Alterations of existing buildings | 291 6 AVENUE | MICHAEL BARRY | special |
| 05/29/2026 | Fire-Resistant Penetrations and Joints | 291 6 AVENUE | Eric Safyan | special |
| 05/28/2026 | Fire-Resistant Penetrations and Joints | 78 8 AVENUE | Texer Nam | special |
| 05/28/2026 | Structural Stability – Alterations of existing buildings | 78 8 AVENUE | MICHAEL BARRY | special |
| 04/30/2026 | Final | 78 8 AVENUE | ELLEN MARTIN | progress |
| 04/29/2026 | Structural Stability – Alterations of existing buildings | 17 MONTGOMERY PLACE | MICHAEL BARRY | special |
| 04/29/2026 | Structural Steel - Details | 17 MONTGOMERY PLACE | MICHAEL BARRY | special |