← Back
Three families
175 HALSEY STREET
BROOKLYN · BIN 3052794
💬 Discuss this project
1886Year Built
3Stories
C0Building Class
R6BZoning
3,268 sfGross Floor Area
3Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
Three families · 1,520 sf lot · 2.15 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
Roof1p · 1 filing · 16 docs
Floor 3Under Construction24p · 2 filings · 20 docs
Floor 2Under Construction24p · 2 filings · 20 docs
Floor 1Under Construction22p · 2 filings · 20 docs
CellarUnder Construction27p · 5 filings · 20 docs
BasementUnder Construction22p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PARSONS CONSTRUCTION507/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/19/2020$1000K—— → —$306/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
W. ALLEN ENGINEERING PLLC405/29/2026
NC2 ARCHITECTURE LLC304/14/2026
SOLHJOU ENGINEERING205/22/2024
AP PROFESSIONAL ENGINEERING PLLC105/17/2023
RV ENGINEERS, PC112/20/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LLOYD NOEL BUILDING CONSULTANT703/21/2026
NOEL BUILDING CONSULTING INC203/21/2026
SANDEEP KAUR103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GECKO BUILDS, LLCGeneral Contractor507/08/2026
BDS ELECTRIC CORP.Electrical103/22/2026
VILLAGE P & H NY INCFire Protection107/08/2026
PARSONS CONSTRUCTION INCGeneral Contractor107/08/2026
LIQUID PLBG & HTNG SCS INPlumbing107/08/2026
ZONE PLUMBING & HEATING CPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CENTURY TESTING & CONSULT4081505/29/2026
NC2 ARCHITECTURE LLC3454204/14/2026
RV ENGINEERS, PC.5953404/14/2026
RYAN SPECIAL ENGINEERING2018112/20/2022
Building Lifecycle
All (156)Filed (11)Permit Issued (9)Signed Off (5)Violation (48)Inspection (12)Objection (58)Special Inspection (13)
08/27/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/07/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
06/22/2026
Permit issued — General Construction
B00667725-I1-GC
06/03/2026
Signed off — Alteration
PAA RESPECTFULLY SUBMITTED IN ORDER TO AMEND MECHANICAL SCHEDULE TO INCLUDE SERIAL NUMBERS FOR UNITS. NO OTHER CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00807122-I1
05/29/2026
Filed — Alteration
PAA RESPECTFULLY SUBMITTED IN ORDER TO AMEND MECHANICAL SCHEDULE TO INCLUDE SERIAL NUMBERS FOR UNITS. NO OTHER CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B00807122-P1
05/29/2026
Special inspection requirement — Mechanical Systems
FRANZ SEBORGA
05/29/2026
Special inspection requirement — Final
FRANZ SEBORGA
05/27/2026
Special inspection requirement — Final
FRANZ SEBORGA
05/27/2026
Special inspection requirement — Mechanical Systems
FRANZ SEBORGA
05/18/2026
Signed off — Alteration
B00875816-I1
04/17/2026
Signed off — Alteration CO
Gut Renovate Basement, First, Second and Third floor except the occupied tenant apartment. Restore stoop. Replace windows. Open up rear wall for new doors on the first floor.
B00667725-S1
04/14/2026
Filed — Alteration CO
Gut Renovate Basement, First, Second and Third floor except the occupied tenant apartment. Restore stoop. Replace windows. Open up rear wall for new doors on the first floor.
B00667725-P2
04/13/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
GUERMAN VAINBLAT
04/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Richard Goodstein
04/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
Richard Goodstein
04/07/2026
Signed off — Alteration
Installation of Bathroom and kitchen fixtures. No change of use, egress or occupancy under this application.
B00807127-I1
04/07/2026
Signed off — Alteration
Installation of Sprinkler heads. No change of use, egress or occupancy under this application.
B00986237-I1
04/06/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/12/2026
Objection resolved — Addressed
02/23/2026
Objection raised — Admin
02/16/2026
Objection resolved — Addressed
02/12/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/11/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/10/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
01/23/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/21/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/20/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/16/2026
Permit issued — Mechanical Systems
B00807122-I1-MS
12/29/2025
Objection raised — Accessibility
12/29/2025
Objection raised — Accessibility
12/29/2025
Objection raised — Other
12/29/2025
Objection raised — Fire_Protection
12/29/2025
Objection raised — Admin
12/29/2025
Objection raised — Cost
12/29/2025
Objection raised — Scope
12/29/2025
Objection raised — Fire_Protection
12/29/2025
Objection raised — Scope
12/15/2025
Permit issued — Sprinklers
B00986237-I1-EW-SP
12/12/2025
Filed — Alteration CO
Gut Renovate Basement, First, Second and Third floor except the occupied tenant apartment. Restore stoop. Replace windows. Open up rear wall for new doors on the first floor.
B00667725-P1
11/24/2025
Permit issued — Plumbing
B00807127-I1-PL
10/09/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
GUERMAN VAINBLAT
10/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Richard Goodstein
10/09/2025
Special inspection requirement — Fire-Resistance Rated Construction
Richard Goodstein
04/09/2025
Permit issued — General Construction
B00667725-I1-GC
02/07/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/07/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
11/06/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/25/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/31/2024
Special inspection requirement — Sprinkler Systems
FRANZ SEBORGA
05/22/2024
Filed — Alteration
Installation of Sprinkler heads. No change of use, egress or occupancy under this application.
B00986237-P1
05/20/2024
Special inspection requirement — Sprinkler Systems
04/10/2024
Violation issued (HPD, closed)
A
02/08/2024
Filed — Alteration
Installation of Sprinkler heads. No change of use, egress or occupancy under this application.
B00986237-I1
Latest 60 of 156 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedGECKO BUILDS, LLC06/22/2026
DOB NOWMechanical SystemsSigned-offGECKO BUILDS, LLC01/16/2026
DOB NOWSprinklersSigned-offVILLAGE P & H NY INC12/15/2025
DOB NOWPlumbingSigned-offZONE PLUMBING & HEATING C11/24/2025
DOB NOWGeneral ConstructionPermit IssuedGECKO BUILDS, LLC04/09/2025
DOB NOWSidewalk ShedSigned-offPARSONS CONSTRUCTION INC05/19/2023
DOB NOWPlumbingSigned-offLIQUID PLBG & HTNG SCS IN04/18/2023
DOB NOWStructuralSigned-offGECKO BUILDS, LLC02/16/2023
DOB NOWGeneral ConstructionPermit IssuedGECKO BUILDS, LLC09/21/2022
2 projects · most recent 05/26/2026
General Wiring
FiledStatusContractorScope
05/26/2026CompleteRIVIERA ELECTRIC CORPGeneral Wiring
05/30/2023Permit IssuedBDS ELECTRIC CORP.—
1 project · most recent 04/14/2026
Steel Concrete Wood
FiledStatusContractorScope
04/14/2026Permit IssuedGECKO BUILDS, LLCSteel, Concrete, Wood
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
08/27/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/07/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
04/06/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/12/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/11/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/23/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/21/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/20/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/07/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/06/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/25/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
05/29/2026Mechanical SystemsFRANZ SEBORGAspecial
05/29/2026FinalFRANZ SEBORGAprogress
05/27/2026FinalFRANZ SEBORGAprogress
05/27/2026Mechanical SystemsFRANZ SEBORGAspecial
04/13/2026Structural Stability – Alterations of existing buildingsGUERMAN VAINBLATspecial
04/13/2026Fire-Resistant Penetrations and JointsRichard Goodsteinspecial
04/13/2026Fire-Resistance Rated ConstructionRichard Goodsteinprogress
10/09/2025Structural Stability – Alterations of existing buildingsGUERMAN VAINBLATspecial
10/09/2025Fire-Resistant Penetrations and JointsRichard Goodsteinspecial
10/09/2025Fire-Resistance Rated ConstructionRichard Goodsteinprogress
05/31/2024Sprinkler SystemsFRANZ SEBORGAspecial
05/20/2024Sprinkler Systems—special
01/03/2023Sprinkler SystemsFRANZ SEBORGAspecial
▾Documents — 75 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/27/2026B00807122-P1Request digital key ↗
08/27/2026B00807122-I1Request digital key ↗
08/27/2026B00807134-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits6
▸DOB NOWLPC Approval/Permit6
08/27/2026B00807122-P1Open ↗
08/19/2026B00667725-P2Open ↗
08/19/2026B00667725-I1Open ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/19/2026B00667725-I1Open ↗
▸Seals & Professional Certifications23
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/27/2026B00807122-P1Open ↗
08/27/2026B00875816-I1Open ↗
08/26/2026B00986237-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/01/2026B00986237-I1Open ↗
08/31/2026B00807122-I1Open ↗
08/26/2026B00667725-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/31/2026B00807122-I1Open ↗
08/26/2026B00667725-P1Open ↗
08/24/2026B00667725-P2Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection14
▸DOB NOWHPD-3: Single Room Occupancy Multiple Dwelling (SRO MD) Anti-Harassment Checklist11
08/27/2026B00807122-P1Open ↗
08/19/2026B00667725-P2Open ↗
08/13/2026B00986237-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWStreet Tree Checklist3
08/19/2026B00667725-P2Open ↗
08/13/2026B00667725-P1Open ↗
08/13/2026B00667725-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/27/2026B00807122-P1Open ↗
08/26/2026B00986237-P1Open ↗
08/26/2026B00986237-I1Open ↗
Showing 3 of 10 on file for this type
▸Approvals, Objections & Sign-offs1
▸DOB NOWLandmark Approval1
08/13/2026B00667725-I1Open ↗
▸Other Documents9
▸DOB NOWProof of Historic Building5
08/27/2026B00807122-P1Open ↗
08/19/2026B00667725-P2Open ↗
08/13/2026B00667725-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification3
08/19/2026B00667725-P2Open ↗
08/13/2026B00667725-I1Open ↗
08/13/2026B00667725-P1Open ↗
▸DOB NOWFinal Survey1
08/19/2026B00667725-I1Open ↗