← Back
BuildNYC
City residence, one family
18 EAST 74TH STREET
MANHATTAN · BIN 1041516
💬 Discuss this project
1871Year Built
6Stories
A4Building Class
R8BZoning
8,277 sfGross Floor Area
1Units
0 Active Violations
City residence, one family · Owner of record: 18E74, LLC · 2,146 sf lot · 3.86 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofUnder Construction11p · 2 filings · 20 docs
PenthouseUnit PH1Under Construction13p · 4 filings · 20 docs
Floor 7Rear extension and foundation alterations12p · 1 filing · 20 docs
Floor 6Rear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
Floor 5Rear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
Floor 4Rear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
Floor 3Rear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
Floor 2Rear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
Floor 1Rear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
CellarRear extension and foundation alterationsUnder Construction11p · 4 filings · 20 docs
Basement1p · 1 filing · 20 docs
Site & exteriorLight duty pipe scaffold12p · 6 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
18E74LLC4610/04/2026
Silver Rail Associates Inc Dba Silver RA2307/08/2026
18E74, LLC103/22/2026
Candela Group103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/20/2021$18.8M—— → —$2,265/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
J.A.M. Associates2603/21/2026
Michael Zenreich Architect1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Silver Rail AssociatesGeneral Contractor3107/08/2026
Andamio ScaffoldingScaffold2307/08/2026
Anchor PlumbingPlumbing510/04/2026
Anchor PlumbingFire Protection406/27/2026
Donato PlumbingPlumbing107/08/2026
Warren Ostroff ElectricElectrical103/21/2026
Warren Ostroff ElectricElectrical103/22/2026
Borowide Elect'l ContractorsElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Kendall Engineering4154805/18/2026
Special Testing & Consulting16881309/29/2025
Michael Zenreich Architects1724201/09/2024
CES Engineering1277310/03/2022
Gza Geoenvironmental of N1179208/01/2022
Building Lifecycle
All (215)Filed (32)Permit Issued (45)Signed Off (7)Violation (18)Inspection (3)Objection (80)Special Inspection (30)
09/04/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/01/2026
Permit issued — Plumbing
M00647803-I1-PL
06/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KEVIN KENDALL
06/25/2026
Special inspection requirement — Sprinkler Systems
KEVIN KENDALL
05/18/2026
Filed — Alteration
M00740560-P1
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KEVIN KENDALL
03/20/2026
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00865980-I1
03/12/2026
Signed off — Alteration
Removal of rear extension and main rear wall. Lowering of cellar slab and excavation of rear yard. Partial floor and roof framing replacement. New foundations for building rear and new pool. Erection of steel frame and masonry wall for new rear extension.
M00729007-I1
03/03/2026
Filed — Alteration
Filing for the removal of plumbing fixtures and addition of new fixtures and components on floors 001 through 006, as per plans submitted.
M00647803-P4
02/20/2026
Objection resolved — Addressed
02/19/2026
Objection resolved — Addressed
02/19/2026
Objection resolved — Addressed
01/23/2026
Permit issued — Mechanical Systems
M00634458-S1-MS
01/23/2026
Permit issued — General Construction
M00634458-I1-GC
12/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KEVIN KENDALL
12/01/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/30/2025
Objection raised — Admin
10/30/2025
Objection raised — Cost
10/14/2025
Objection raised — Scope
10/03/2025
Permit issued — Sprinklers
M00740560-I1-EW-SP
10/01/2025
Signed off — Alteration
M00866012-I1
09/29/2025
Filed — Alteration
Removal of rear extension and main rear wall. Lowering of cellar slab and excavation of rear yard. Partial floor and roof framing replacement. New foundations for building rear and new pool. Erection of steel frame and masonry wall for new rear extension.
M00729007-P3
09/11/2025
Permit issued — Plumbing
M00647803-I1-PL
09/08/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY BARRIERS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY SHALL COMPLY WITH CHAPTER#33 OF 2022 THE NY BUILDING CODE.
M00866135-I1
09/04/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
06/06/2025
Filed — Alteration
Filing for interior and exterior renovation of single family townhouse . Work includes reallocation of floor area, facades, and new elevator bulkhead. Structural work filed separately. No change to use, egress or occupancy.
M00634458-P6
05/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Steel - Details
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Subgrade Inspections
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Steel - Welding
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Masonry
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Concrete - Cast-In-Place
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Wood Frame
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Steel - Welding
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Steel - High Strength Bolting
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Concrete - Cast-In-Place
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Final
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Masonry
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Subgrade Inspections
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Sprayed fire-resistant materials
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Post-installed Anchors
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Steel - High Strength Bolting
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Steel - Details
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Structural Wood Frame
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Post-installed Anchors
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Sprayed fire-resistant materials
SEBASTIAN SETTEDUCATE JR., P.E
05/30/2025
Special inspection requirement — Final
SEBASTIAN SETTEDUCATE JR., P.E
04/17/2025
Permit issued — Protection and Mechanical Methods
M00866135-I1-PMM
04/17/2025
Permit issued — Supported Scaffold
M00865980-I1-SF
03/28/2025
Signed off — Alteration
M00866033-I1
03/06/2025
Permit issued — Structural
M00729007-I1-ST
02/28/2025
Filed — Alteration
Filing for the removal of plumbing fixtures and addition of new fixtures and components on floors 001 through 006, as per plans submitted.
M00647803-P3
02/21/2025
Permit issued — General Construction
M00634458-I1-GC
02/21/2025
Permit issued — Mechanical Systems
M00634458-S1-MS
02/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KEVIN KENDALL
11/20/2024
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00865980-P5
11/12/2024
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00865980-P4
11/11/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01049857-I1
11/01/2024
Permit issued — Sprinklers
M00740560-I1-EW-SP
Latest 60 of 215 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAnchor Plumbing09/01/2026
DOB NOWMechanical SystemsPermit IssuedSilver Rail Associates01/23/2026
DOB NOWGeneral ConstructionPermit IssuedSilver Rail Associates01/23/2026
DOB NOWSprinklersSigned-offAnchor Plumbing10/03/2025
DOB NOWPlumbingPermit IssuedAnchor Plumbing09/11/2025
DOB NOWProtection and Mechanical MethodsSigned-offAndamio Scaffolding04/17/2025
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding04/17/2025
DOB NOWStructuralSigned-offSilver Rail Associates03/06/2025
DOB NOWGeneral ConstructionPermit IssuedSilver Rail Associates02/21/2025
DOB NOWMechanical SystemsPermit IssuedSilver Rail Associates02/21/2025
DOB NOWSprinklersSigned-offAnchor Plumbing11/01/2024
DOB NOWPlumbingPermit IssuedAnchor Plumbing10/10/2024
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding05/15/2024
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding04/26/2024
DOB NOWConstruction FenceSigned-offAndamio Scaffolding04/26/2024
DOB NOWProtection and Mechanical MethodsSigned-offAndamio Scaffolding04/26/2024
DOB NOWProtection and Mechanical MethodsSigned-offAndamio Scaffolding04/26/2024
DOB NOWStructuralSigned-offSilver Rail Associates02/22/2024
DOB NOWGeneral ConstructionPermit IssuedSilver Rail Associates02/22/2024
DOB NOWMechanical SystemsPermit IssuedSilver Rail Associates02/21/2024
DOB NOWSupport of ExcavationSigned-offSilver Rail Associates02/21/2024
DOB NOWSprinklersSigned-offAnchor Plumbing12/01/2023
DOB NOWPlumbingPermit IssuedAnchor Plumbing11/02/2023
DOB NOWSupport of ExcavationSigned-offSilver Rail Associates09/25/2023
DOB NOWProtection and Mechanical MethodsSigned-offAndamio Scaffolding05/02/2023
DOB NOWProtection and Mechanical MethodsSigned-offAndamio Scaffolding05/02/2023
DOB NOWConstruction FenceSigned-offAndamio Scaffolding05/02/2023
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding05/02/2023
DOB NOWStructuralSigned-offSilver Rail Associates03/23/2023
DOB NOWStructuralSigned-offSilver Rail Associates03/11/2023
DOB NOWGeneral ConstructionPermit IssuedSilver Rail Associates03/11/2023
DOB NOWMechanical SystemsPermit IssuedSilver Rail Associates03/11/2023
DOB NOWGeneral ConstructionPermit IssuedSilver Rail Associates03/03/2023
DOB NOWStructuralSigned-offSilver Rail Associates03/02/2023
DOB NOWMechanical SystemsPermit IssuedSilver Rail Associates03/02/2023
DOB NOWStructuralSigned-offSilver Rail Associates01/05/2023
DOB NOWMechanical SystemsPermit IssuedSilver Rail Associates12/21/2022
DOB NOWSprinklersSigned-offAnchor Plumbing12/02/2022
DOB NOWGeneral ConstructionPermit IssuedSilver Rail Associates11/30/2022
DOB NOWPlumbingPermit IssuedAnchor Plumbing10/28/2022
+ 19 more permits on file
1 project · most recent 06/06/2025
Air Conditioning Systems Heating and Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/06/2025Permit IssuedSilver Rail AssociatesAir Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Seresco NC-B-1V 75,100 BTU · Condensing Unit ×2
Daikin ×6
Heat / Cool
Mitsubishi Electric MXZ-SM60NAM2-U1 42,411 BTU · Vrf Outdoor ×2
PURY-EP120TNU-A 115,081 BTU · Vrf Outdoor ×2
PURY-EP144TNU-A 140,663 BTU · Vrf Outdoor ×2
Heating
Burnham ASPN-270 270,000 BTU · Boiler ×4
Ventilation
Panasonic FV-0511VK2, FV-10NLF1, FV-05-11VK1 80 CFM · Exhaust Fan ×6
FV-0511VK2, FV-0511VK2 50 CFM · Exhaust Fan ×4
FV-10NLF1, FV-10NLF1 100 CFM · Exhaust Fan ×4
FV-20NLF1 200 CFM · Exhaust Fan ×4
FV-0511VK2 110 CFM · Exhaust Fan ×2
FV-30NLF1 300 CFM · Exhaust Fan ×2
Greenheck CUE-120-VG, CSP-A1050-VG 1,000 CFM · Exhaust Fan ×4
CUE-95-VG 600 CFM · Exhaust Fan ×2
Fantech DBF4XLT 150 CFM · Exhaust Fan ×2
FG 4XL EC 25 CFM · Exhaust Fan ×2
1 project · most recent 03/03/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/03/2026Permit IssuedAnchor PlumbingGas, Storm, Water/Sanitary
6 projects · most recent 09/22/2026
General Wiring
FiledStatusContractorScope
09/22/2026Permit IssuedWarren Ostroff ElectricGeneral Wiring
04/07/2025Permit IssuedWarren Ostroff Electric1 meters, 1 new_meters
05/29/2024CompleteBorowide Elect'l Contractors—
12/05/2022Permit IssuedWarren Ostroff Electric—
10/07/2022Permit IssuedTransel Elev. & ElectricGeneral Wiring
02/01/2022Permit IssuedIndy Electric—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
09/04/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/01/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/04/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 80
DateRequirementInspectorRole
06/25/2026Sprinkler SystemsKEVIN KENDALLspecial
06/25/2026Fire-Resistant Penetrations and JointsKEVIN KENDALLspecial
03/26/2026Fire-Resistant Penetrations and JointsKEVIN KENDALLspecial
12/16/2025Fire-Resistant Penetrations and JointsKEVIN KENDALLspecial
05/30/2025Subgrade InspectionsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025FinalSEBASTIAN SETTEDUCATE JR., P.Eprogress
05/30/2025Structural Wood FrameSEBASTIAN SETTEDUCATE JR., P.Eprogress
05/30/2025Concrete - Cast-In-PlaceSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025MasonrySEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Post-installed AnchorsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Sprayed fire-resistant materialsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Stability – Alterations of existing buildingsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Steel - DetailsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Steel - High Strength BoltingSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Steel - WeldingSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Wood FrameSEBASTIAN SETTEDUCATE JR., P.Eprogress
05/30/2025FinalSEBASTIAN SETTEDUCATE JR., P.Eprogress
05/30/2025Subgrade InspectionsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Steel - WeldingSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Steel - High Strength BoltingSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Steel - DetailsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Structural Stability – Alterations of existing buildingsSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Concrete - Cast-In-PlaceSEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025MasonrySEBASTIAN SETTEDUCATE JR., P.Especial
05/30/2025Post-installed AnchorsSEBASTIAN SETTEDUCATE JR., P.Especial
Latest 25 of 80.
▾Documents — 175 on file (BIS + DOB NOW)
▸Plans & Drawings32
▸DOB NOWPlans/Sketch32
08/31/2026M00729007-P2Request digital key ↗
08/31/2026M00729007-P3Request digital key ↗
08/31/2026M00729007-I1Request digital key ↗
Showing 3 of 32 on file for this type
▸Applications & Permits21
▸DOB NOWLPC Approval/Permit18
08/31/2026M00729007-P2Open ↗
08/31/2026M00729007-I1Open ↗
08/31/2026M00729007-P1Open ↗
Showing 3 of 18 on file for this type
▸BISWORK PERMIT APPLICATION2
12/12/2007110049377Open ↗
12/12/2007110049377Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
12/11/2007110049377Open ↗
▸Seals & Professional Certifications70
▸DOB NOWDPL-1: Design Professional Seal & Signature32
08/31/2026M00729007-P2Open ↗
08/31/2026M00729007-I1Open ↗
08/31/2026M00729007-P1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature26
09/28/2026M00647803-P2Open ↗
09/19/2026M00634458-P2Open ↗
09/19/2026M00634458-P2Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
09/19/2026M00634458-P2Open ↗
09/01/2026M00729007-P1Open ↗
08/31/2026M00729007-P2Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
12/11/2007110049377Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
12/11/2007110049377Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
12/11/2007110049377Open ↗
▸Environmental & Asbestos22
▸DOB NOWDEP ACP-5: Asbestos Assessment Report21
08/31/2026M00729007-P2Open ↗
08/31/2026M00729007-P1Open ↗
08/31/2026M00729007-I1Open ↗
Showing 3 of 21 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
12/11/2007110049377Open ↗
▸Inspections & Test Reports1
▸BISNOTIF.-PROPOSED STEAM/HOT WATER INSPECTION1
12/11/2007110049377Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/19/2012110049377Open ↗
▸BISLANDMARKS APPROVAL1
12/11/2007110049377Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
12/11/2007110049377Open ↗
▸Other Documents25
▸DOB NOWWaiver Document12
08/23/2026M00634458-P5Open ↗
08/23/2026M00634458-P4Open ↗
08/23/2026M00634458-S1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProof of Historic Building10
08/23/2026M00634458-I1Open ↗
08/23/2026M00634458-P5Open ↗
08/23/2026M00634458-P4Open ↗
Showing 3 of 10 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
12/19/2012110049377Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026M00729007-S1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026M00729007-S1Open ↗