1910Year Built
7Stories
D4Building Class
R7AZoning
33,230 sfGross Floor Area
21Units
LL97 CoveredRent Stabilized18 Open Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 180 ST NICHOLAS HDFC · 5,712 sf lot · 5.82 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 10 docs
Bulkhead1p · 1 filing · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RAND ENGINEERING807/08/2026
FINGER MANAGEMENT1407/08/2026
TOPLINE NYC CONTRACTING603/22/2026
180 ST NICHOLAS HDFC1003/22/2026
180ST NICHOLAS HDFC103/22/2026
180 ST NICHOLAS HDFC FING103/22/2026
SHAMAS CONSTRUCTION403/22/2026
180 ST NICHOLAS AVE HDFC103/22/2026
OWNER OF BLDG 180 ST. NIC103/22/2026
B H B CONSTRUCTION203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SRA ARCHITECTURE + ENGINEERING, PC305/06/2024
ASR ENGINEERING PC109/29/2022
RIMKUS NEW YORK PLLC104/22/2022
MOHAMMAD AHEAD, PE104/04/2022
INGA CONSULTING ENGINEERS309/30/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ADVANCED BUILDERS SERVICES203/21/2026
RDDNY DESIGN BUILD303/21/2026
CORNERSTONE CONSULTING103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TOPLINE NYC CONTRACTINGGeneral Contractor903/21/2026
DIGITTER INCGeneral Contractor407/08/2026
ZAF CORPORATIONGeneral Contractor303/21/2026
ELITE QUALITY CONSTRUCTIOGeneral Contractor107/08/2026
MACINTOSH ELECTRIC CORPElectrical103/22/2026
A.M. SAGE PLG & HTG LLCPlumbing107/08/2026
PATRICK GILLESPIEElectrical103/21/2026
RICHARD NEUElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SRA INSPECTIONS3461205/06/2024
RIMKUS NEW YORK, PLLC8123104/22/2022
Building Lifecycle
All (121)Filed (9)Permit Issued (10)Signed Off (2)Facade (FISP) (16)Violation (60)Inspection (4)Objection (6)Special Inspection (14)
05/19/2026
Permit issued — General Construction
M00900542-I1-GC
04/22/2026
Permit issued — General Construction
M00900542-I1-GC
03/12/2026
Permit issued — General Construction
M00900542-I1-GC
10/30/2024
Permit issued — General Construction
M00900542-I1-GC
05/13/2024
Objection raised — Other
05/13/2024
Objection resolved — Addressed
05/13/2024
Objection raised — Scope
05/13/2024
Objection resolved — Addressed
05/13/2024
Objection raised — Structural
05/13/2024
Objection resolved — Addressed
05/06/2024
Filed — Alteration
INSTALLATION OF AN ADA COMPLIANT RAMP AT FRONT & SIDE OF THE BUILDING
M00900542-P1
05/06/2024
Filed — Alteration
INSTALLATION OF AN ADA COMPLIANT RAMP AT FRONT & SIDE OF THE BUILDING
M00900542-S1
05/06/2024
Special inspection requirement — Final
Spencer Goroff
05/06/2024
Special inspection requirement — Tenant Protection Plan Compliance
Adrian Figueroa
03/12/2024
Special inspection requirement — Tenant Protection Plan Compliance
Adrian Figueroa
03/12/2024
Special inspection requirement — Final
Spencer Goroff
08/29/2023
Filed — Alteration
INSTALLATION OF AN ADA COMPLIANT RAMP AT FRONT & SIDE OF THE BUILDING
M00900542-I1
07/20/2023
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M00709789-I1
05/19/2023
Cycle 9 facade report submitted
05/16/2023
Cycle 9 facade report signed — SAFE
04/27/2023
Cycle 9 facade inspection completed
03/27/2023
Permit issued — Sidewalk Shed
M00709789-I1-SH
03/22/2023
Signed off — Alteration
M00590912-I1
09/30/2022
Permit issued — Supported Scaffold
M08011370-I1-SF
09/29/2022
Filed — Alteration
M08011370-I1
09/23/2022
Permit issued — General Construction
M00590912-I1-GC
07/28/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/22/2022
Filed — Alteration
M00590912-I1
04/05/2022
Permit issued — Sidewalk Shed
M00709789-I1-SH
04/04/2022
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M00709789-I1
03/30/2022
Special inspection requirement — Air barrier - visual inspection
Brian Sullivan
03/30/2022
Special inspection requirement — Insulation placement and R values
Brian Sullivan
03/30/2022
Special inspection requirement — Masonry
Brian Sullivan
03/30/2022
Special inspection requirement — Post-installed Anchors
Brian Sullivan
03/30/2022
Special inspection requirement — Energy Code Compliance Inspections
Brian Sullivan
02/22/2022
Cycle 9 facade report submitted
02/22/2022
Cycle 9 facade report signed — UNSAFE
02/22/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/22/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/16/2022
Cycle 9 facade inspection completed
02/16/2022
Violation issued (HPD, closed)
A
11/03/2021
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/25/2021
Inspection — Pass-Final CO-Alt-1 Inspection Up to 4 Total Levels
Pass
View inspection ↗
10/21/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/12/2021
Permit issued — Plumbing
M00590526-I1-PL
09/30/2021
Filed — Alteration
MINOR INTERIOR RENOVATION OF AN EXISTING APARTMENT. RELOCATING EXISTING PLUMBING FIXTURES AND ADDING ONE PLUMBING FIXTURE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00590526-P1
09/15/2021
Filed — Alteration
MINOR INTERIOR RENOVATION OF AN EXISTING APARTMENT. RELOCATING EXISTING PLUMBING FIXTURES AND ADDING ONE PLUMBING FIXTURE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00590526-I1
09/09/2021
Special inspection requirement — Final
Brian Sullivan
06/18/2021
Permit issued — General Construction
M00537009-I1-GC
06/11/2021
Filed — Alteration
MINOR INTERIOR RENOVATION OF AN EXISTING RESIDENTIAL APARTMENT. REMOVE NON LOAD BEARING WALLS, DOORS & COUNTERS, FINISHES AS REQUIRED AND AS PER PLANS. NEW NON LOAD BEARING PARTITIONS, DOORS AND COUNTERS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
M00537009-I1
06/11/2021
Special inspection requirement — Lighting controls
Andrew Inga
06/11/2021
Special inspection requirement — Interior lighting power
Andrew Inga
06/11/2021
Special inspection requirement — Lighting in dwelling units
Andrew Inga
06/09/2021
Special inspection requirement — Final
Andrew Inga
05/19/2020
Violation issued (ECB, closed)
Boilers
09/06/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/20/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/20/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/13/2017
Cycle 8 facade report submitted
Latest 60 of 121 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedDIGITTER INC05/19/2026
DOB NOWGeneral ConstructionPermit IssuedDIGITTER04/22/2026
DOB NOWGeneral ConstructionPermit IssuedDIGITTER03/12/2026
DOB NOWGeneral ConstructionPermit IssuedDIGITTER10/30/2024
DOB NOWSidewalk ShedSigned-offTOPLINE NYC CONTRACTING03/27/2023
DOB NOWSupported ScaffoldPermit IssuedTOPLINE NYC CONTRACTING09/30/2022
DOB NOWGeneral ConstructionSigned-offELITE QUALITY CONSTRUCTIO09/23/2022
DOB NOWSidewalk ShedSigned-offTOPLINE NYC CONTRACTING04/05/2022
DOB NOWPlumbingPermit IssuedA.M. SAGE PLG & HTG LLC10/12/2021
DOB NOWGeneral ConstructionPermit IssuedZAF CORPORATION06/18/2021
BISPLISSUEDTRISTAR PLUMBING & HTG IN11/15/2016
BISOTISSUEDREDLINE CONSTRUCTION & MA10/19/2016
BISPLISSUEDTRISTAR PLUMBING & HTG IN08/20/2015
BISOTISSUEDREDLINE CONSTRUCTION & MA07/23/2015
BISBLISSUEDDOUGLAS SIMMONS09/26/2014
BISEQISSUEDB H & B CONSTRUCTION INC09/03/2014
BISEQISSUEDB H & B CONSTRUCTION INC08/11/2014
BISOTISSUEDSHAMAS CONTRACTING CO.INC07/22/2014
BISPLISSUEDWYNNE PLBG & HEATING CORP11/07/2012
BISOTISSUEDTRINCHESE CONSTRUCTION IN04/05/2012
BISOTISSUEDSHAMAS CONTRACTING CO.INC06/15/2009
BISEQISSUEDM.S.S. CONSTRUCTION CORP11/20/2008
BISOTISSUED2 SHELLS INTERIORS INC08/19/2004
1 project · most recent 09/30/2021
Water/Sanitary
FiledStatusContractorScope
09/30/2021Permit IssuedA.M. SAGE PLG & HTG LLCWater/Sanitary
3 projects · most recent 04/05/2022
General Wiring
FiledStatusContractorScope
04/05/2022Permit IssuedRICHARD NEU—
01/07/2022Permit IssuedCONTROL SPEC ELECL SYSTEMGeneral Wiring
06/25/2020Permit IssuedMACINTOSH ELECTRIC CORPGeneral Wiring
1 project · most recent 05/06/2024
Fence
FiledStatusContractorScope
05/06/2024Permit IssuedDIGITTER INCFence
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
07/28/2022Pass-Final CND-Occupancy InspectionPassView ↗
11/03/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/25/2021Pass-Final CO-Alt-1 Inspection Up to 4 Total LevelsPassView ↗
10/21/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
05/06/2024FinalSpencer Goroffprogress
05/06/2024Tenant Protection Plan ComplianceAdrian Figueroaspecial
03/12/2024Tenant Protection Plan ComplianceAdrian Figueroaspecial
03/12/2024FinalSpencer Goroffprogress
03/30/2022Air barrier - visual inspectionBrian Sullivanenergy_progress
03/30/2022Insulation placement and R valuesBrian Sullivanenergy_progress
03/30/2022MasonryBrian Sullivanspecial
03/30/2022Post-installed AnchorsBrian Sullivanspecial
03/30/2022Energy Code Compliance InspectionsBrian Sullivanprogress
09/09/2021FinalBrian Sullivanprogress
06/11/2021Lighting controlsAndrew Ingaenergy_progress
06/11/2021Interior lighting powerAndrew Ingaenergy_progress
06/11/2021Lighting in dwelling unitsAndrew Ingaenergy_progress
06/09/2021FinalAndrew Ingaprogress
▾Documents — 161 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
09/03/2026M00537009-I1Request digital key ↗
09/03/2026M00590526-P1Request digital key ↗
09/03/2026M00590526-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits30
▸BISWORK PERMIT APPLICATION16
11/18/2016122819646Open ↗
10/24/2016122819646Open ↗
09/09/2015140346677Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION13
12/19/2017122819646Open ↗
10/28/2016122819646Open ↗
07/19/2016122819646Open ↗
Showing 3 of 13 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
12/10/2009110396624Open ↗
▸Seals & Professional Certifications52
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
10/24/2016122819646Open ↗
07/19/2016122819646Open ↗
03/31/2015140228796Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/03/2026M00590526-P1Open ↗
09/03/2026M00590526-I1Open ↗
09/02/2026M00709789-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
08/31/2026M00537009-I1Open ↗
08/31/2026M00537009-I1Open ↗
08/31/2026M00537009-I1Open ↗
Showing 3 of 9 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
06/12/2015140346677Open ↗
09/16/2014140253829Open ↗
09/02/2014140247775Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
06/12/2015140346677Open ↗
09/16/2014140253829Open ↗
09/02/2014140247775Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
09/23/2014140253829Open ↗
04/09/2012121030650Open ↗
06/15/2009120074864Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
09/16/2014140253829Open ↗
09/02/2014140247775Open ↗
08/08/2014140237553Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/29/2026M00900542-I1Open ↗
08/29/2026M00590912-I1Open ↗
08/29/2026M00590912-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
04/09/2012121030650Open ↗
06/15/2009120074864Open ↗
11/20/2008110396624Open ↗
▸Trade Schedules & Equipment8
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
12/19/2017122819646Open ↗
10/28/2016122819646Open ↗
07/19/2016122819646Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
05/31/2013121030650Open ↗
03/21/2013121030650Open ↗
▸BISSCHEDULE B - PLUMBING2
06/12/2015140346677Open ↗
04/09/2012121030650Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
09/16/2014140253829Open ↗
▸Safety & Tenant Protection3
▸BISTenant Protection Plan and Notes2
07/21/2016122819646Open ↗
07/19/2016122819646Open ↗
▸BISSTREET TREE CHECKLIST1
06/12/2015140346677Open ↗
▸Environmental & Asbestos11
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
07/19/2016122819646Open ↗
06/12/2015140346677Open ↗
09/16/2014140253829Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
09/03/2026M00590526-P1Open ↗
09/03/2026M00590526-I1Open ↗
09/02/2026M00590912-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
06/15/2009120074864Open ↗
11/20/2008110396624Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
07/21/2016122819646Open ↗
07/19/2016122819646Open ↗
03/31/2015140228796Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
06/12/2015140346677Open ↗
09/16/2014140253829Open ↗
07/22/2014140228796Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
09/16/2014140253829Open ↗
07/22/2014140228796Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
05/10/2016140346677Open ↗
03/31/2015140228796Open ↗
▸BISTECHNICAL REPORT: ENERGY1
04/09/2012121030650Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
09/02/2026M00590912-I1Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
06/12/2015140346677Open ↗
09/16/2014140253829Open ↗
09/02/2014140247775Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs10
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
05/10/2016140346677Open ↗
03/31/2015140228796Open ↗
03/11/2015140247775Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
04/09/2012121030650Open ↗
06/15/2009120074864Open ↗
11/20/2008110396624Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/14/2009120074864Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT8
07/19/2016122819646Open ↗
05/10/2016140346677Open ↗
03/31/2015140228796Open ↗
Showing 3 of 8 on file for this type
▸Filing & Intake Forms12
▸BISEFILING JOB APPLICATION COVER SHEET5
06/12/2015140346677Open ↗
09/16/2014140253829Open ↗
09/02/2014140247775Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
07/19/2016122819646Open ↗
04/09/2012121030650Open ↗
06/15/2009120074864Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION2
12/27/2016122819646Open ↗
08/21/2015140346677Open ↗
▸BISBOROUGH INTAKE FORM1
12/19/2017122819646Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
05/10/2016140346677Open ↗