| Owner | Filings | Most Recent |
|---|---|---|
| ROYAL CHARTER PROPERTIES | 11 | 07/08/2026 |
| RREEF AMERICA REIT II CORP. MMMM6 NEW YO RK | 1 | 03/22/2026 |
| CUSHMAN & WAKEFILED US INC | 1 | 03/22/2026 |
| RREEF AMERICA REIT II | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| YAO W GUO ARCHITECT, PC | 1 | 12/05/2023 |
| H2M ARCHITECTS + ENGINEERS | 2 | 09/07/2023 |
| SHIGEHIRO SHISHIDO | 2 | 07/22/2022 |
| VALENTINO POMPEO ARCHITECT, P.C. | 2 | 10/11/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CITY WIDE EXPEDITING | 4 | 03/21/2026 |
| DDP ROOFING SERVICES | 2 | 03/21/2026 |
| W J PROFESSIONAL EXPEDITING COMPANY | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DDP ROOFING SERVICES LLC | General Contractor | 3 | 03/21/2026 |
| REEM PLBG & HTG CORP | Plumbing | 2 | 07/08/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| DAVEN ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| SPLEN CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| TA COMMERCIAL SERVICE INC | General Contractor | 1 | 07/08/2026 |
| MERIDIAN CONSTRUCTION GRP | General Contractor | 1 | 07/08/2026 |
| EXCALIBUR ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| KJK ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FUTURE TECH CONSULTANTS O | 589 | 2 | 09/07/2023 |
| AEG, P.C. | 1846 | 2 | 07/22/2022 |
| CHONG ENGINEERING P.C. | 7411 | 2 | 10/11/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | DDP ROOFING SERVICES LLC | 12/07/2023 |
| DOB NOW | Plumbing | Signed-off | REEM PLBG & HTG CORP | 11/21/2023 |
| DOB NOW | Plumbing | Signed-off | REEM PLBG & HTG CORP | 09/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TA COMMERCIAL SERVICE INC | 09/19/2023 |
| DOB NOW | General Construction | Signed-off | MERIDIAN CONSTRUCTION GRP | 09/22/2022 |
| DOB NOW | Sprinklers | Signed-off | DW PLUMBING INC | 01/04/2022 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 12/14/2021 |
| DOB NOW | Sprinklers | Permit Issued | RALPH W. LANDOLFI JR. | 12/14/2021 |
| DOB NOW | General Construction | Permit Issued | SPLEN CONSTRUCTION INC | 11/29/2021 |
| BIS | OT | ISSUED | THE SCI CONSTRUCTION | 02/21/2020 |
| BIS | PL | ISSUED | SIGNORE & SONS PLBG CORP | 10/27/2010 |
| BIS | MH | ISSUED | CARE ENTERPRISES, INC | 06/07/2010 |
| BIS | PL | ISSUED | VARSITY PLBG & HTG INC | 04/01/2009 |
| BIS | MH | ISSUED | ASTORIA MECHANICAL CORPORATION | 08/15/2007 |
| BIS | PL | ISSUED | SIGNORE & SONS PLBG CORP | 12/28/2005 |
| BIS | OT | ISSUED | CARE ENTERPRISES, INC | 12/28/2005 |
| BIS | PL | ISSUED | SIGNORE & SONS PLBG CORP | 10/26/2004 |
| BIS | OT | ISSUED | CARE ENTERPRISES, INC | 10/26/2004 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/11/2021 | Permit Issued | RRP PLUMBING CORP | 152 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/11/2021 | Signed-off | TRI STATE PLBG & HTG INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/04/2024 | Complete | KONSKER ELECTRIC CORP. | — |
| 07/13/2022 | Complete | KJK ELECTRIC INC | General Wiring |
| 01/13/2021 | Complete | DAVEN ELECTRIC CORP | — |
| 03/19/2020 | Complete | EXCALIBUR ELECTRIC INC | — |
| 02/03/2020 | Complete | EXCALIBUR ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/01/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/21/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/15/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/13/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/07/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/06/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/03/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/03/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/25/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/25/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/19/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/19/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/24/2023 | Final | Yao Guo | progress |
| 08/22/2023 | HVAC-R and service water piping design and insulation | Stephen Marchese | energy_progress |
| 08/22/2023 | Fire-Resistant Penetrations and Joints | Stephen Marchese | special |
| 08/22/2023 | HVAC-R and service water heating equipment | Stephen Marchese | energy_progress |
| 08/22/2023 | HVAC-R and service water heating system controls | Stephen Marchese | energy_progress |
| 08/22/2023 | Maintenance information | Stephen Marchese | energy_progress |
| 07/22/2022 | Final | Yousuf Tai | progress |
| 07/22/2022 | Masonry | Yousuf Tai | special |
| 10/07/2021 | Energy Code Compliance Inspections | Tae Chong | progress |
| 10/06/2021 | Sprinkler Systems | Tae Chong | special |
| 09/08/2021 | Interior lighting power | Tae Chong | energy_progress |
| 09/08/2021 | Lighting controls | Tae Chong | energy_progress |
| 05/11/2021 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 05/11/2021 | Energy Code Compliance Inspections | Tae Chong | progress |
| 05/11/2021 | Fire-Resistance Rated Construction | Tae Chong | progress |
| 05/11/2021 | Structural Stability – Alterations of existing buildings | Tae Chong | special |