Public elementary, junior or senior high
Success Academy Charter School - Williamsburg
183 SOUTH 3RD STREET · BIN 3063128
💬 Discuss this project
1920Year Built
5Stories
W1Building Class
R6Zoning
162,600 sfGross Floor Area
1Units
LL97 Covered7 Active Violations 3 unresolved · 4 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC Department of Education · 48,840 sf lot · 3.33 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofSuccess Academy Charter School - WilliamsburgUnder Construction39p · 1 filing · 20 docs
Floor 2Success Academy Charter School - Williamsburg7p · 1 filing · 20 docs
Floor 1Success Academy Charter School - Williamsburg1p · 2 filings · 20 docs
CellarSuccess Academy Charter School - Williamsburg1p · 2 filings · 20 docs
Site & exteriorJ.H.S. 50K, Success Academy Charter School - WilliamsburgUnder Construction66p · 7 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority16009/23/2026
NYC Department of Education503/22/2026
JHS 050103/22/2026
New York City Public School103/21/2026
NYC School103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STV902/24/2026
Eme Group/Salas O'Brien111/11/2025
Dseny Engineering Services108/19/2025
NYMS Consulting803/13/2025
HRM Engineering Services411/15/2024
Salam & Giacalone Architects211/15/2024
MSS Engineering711/22/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STV1803/21/2026
Precision 3Sixty NYC1203/21/2026
Dseny Engineering Services203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Maric MechanicalScaffold2707/08/2026
BTF ConstructionScaffold1307/08/2026
Kel-Tech ConstructionScaffold909/23/2026
Maric Mechanicalspecialty_contractor707/08/2026
A & S ElectricElectrical503/21/2026
BTF ConstructionGeneral Contractor407/08/2026
Empire Control Abatementspecialty_contractor403/21/2026
Latty's Gen Plumbing ContPlumbing207/08/2026
Samco ElectricElectrical103/21/2026
Mechanical Electr'lElectrical103/22/2026
LCJ Electrical ContractorsElectrical103/22/2026
Stanco System Electrical ContElectrical103/21/2026
J.H. Electric of New YorkElectrical103/21/2026
I.M.P. Plumbing & HeatingPlumbing107/08/2026
R.M.F. ElectricElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Future Tech Consultants O5891102/24/2026
Socotec Engineering4983202/24/2026
JPC Logistics Dba JPCL EN351111/11/2025
Municipal Testing Laborat230911/15/2024
Building Lifecycle
All (229)Filed (32)Permit Issued (51)Signed Off (6)Violation (60)Inspection (2)Objection (48)Special Inspection (30)
09/22/2026
Permit issued — Sidewalk Shed
B01267253-I1-SH
06/03/2026
Violation issued (ECB, open)
Construction
06/03/2026
Violation issued (ECB, open)
Construction
06/03/2026
Violation issued (ECB, open)
Construction
05/28/2026
Signed off — Alteration
K050_Proposed work to remove existing roof drain and replace with new.
B00580204-I1
05/28/2026
Signed off — Alteration
K050_Proposed work to remove existing roof drain and replace with new.
B00580204-S1
05/11/2026
Permit issued — Sidewalk Shed
B08001662-I1-SH
03/26/2026
Permit issued — Sidewalk Shed
B08001662-I1-SF
03/26/2026
Permit issued — Sidewalk Shed
B08001662-I1-FN
03/26/2026
Permit issued — Mechanical Systems
B08001662-S2-MS
03/24/2026
Objection resolved — Addressed
03/17/2026
Special inspection requirement — Concrete - Cast-In-Place
Noel Tolentino
02/26/2026
Objection raised — Other
02/24/2026
Filed — Alteration
K050_Proposed work to remove existing roof drain and replace with new.
B00580204-P6
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/13/2025
Signed off — Alteration
SUBMITTED ON BEHALF OF CONTRACTOR FOR THE INSTALLATION OF TEMPORARY CONSTRUCTION EQUIPMENT (SCAFFOLD - 250-SF) , IN CONJUNCTION WITH DOB#B00580204, NO CHANGE IN USE, OCCUPANCY OR EGRESS. CONTRACTOR TO USE NEWLY APPROVED EGRESS PLAN.
B08039333-I1
11/11/2025
Filed — Alteration
B01301101-I1
11/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Asma Hashmi
11/11/2025
Special inspection requirement — Maintenance information
Asma Hashmi
11/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
Asma Hashmi
11/11/2025
Special inspection requirement — HVAC-R and service water heating system controls
Asma Hashmi
10/17/2025
Signed off — Alteration
SUBMITTED ON BEHALF OF CONTRACTOR FOR THE INSTALLATION OF TEMPORARY CONSTRUCTION EQUIPMENT (FENCE - 60 LF) , IN CONJUNCTION WITH DOB# B00580204 NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B08039317-I1
10/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Asma Hashmi
10/14/2025
Special inspection requirement — Post-installed Anchors
Asma Hashmi
10/14/2025
Special inspection requirement — Energy Code Compliance Inspections
Asma Hashmi
10/10/2025
Special inspection requirement — Mechanical Systems
Asma Hashmi
10/10/2025
Special inspection requirement — Final
Asma Hashmi
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/07/2025
Violation issued (FDNY_ORDER, closed)
10/01/2025
Permit issued — Sidewalk Shed
B01267253-I1-SH
09/23/2025
Signed off — Alteration
SUBMITTED ON BEHALF OF CONTRACTOR FOR THE INSTALLATION OF TEMPORARY CONSTRUCTION EQUIPMENT (SHED - 28 LF) , IN CONJUNCTION WITH DOB# B00580204 NO CHANGE IN USE, OCCUPANCY OR EGRESS. CONTRACTOR TO USE APPROVED EGRESS PLAN AS PER CONTRACT DOCUMENTS.
B08039327-I1
09/09/2025
Objection resolved — Addressed
08/26/2025
Objection raised — Other
08/19/2025
Filed — Alteration
SH/JHS50K - FOR TEMPORARY CONSTRUCTION EQUIPMENT (EMERGENCY SHED)SUBMITTING ON BEHALF OF CONTRACTOR, RELATED TO LLW # 142835, NO CHANGE IN USE,OCCUPANCY OR EGRESS
B01267253-I1
08/15/2025
Violation issued (FDNY_ORDER, closed)
08/15/2025
Violation issued (FDNY_ORDER, closed)
08/14/2025
Special inspection requirement — Structural Steel - Details
Noel Tolentino
08/14/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Noel Tolentino
08/14/2025
Special inspection requirement — Masonry
Noel Tolentino
08/14/2025
Special inspection requirement — Post-installed Anchors
Noel Tolentino
08/14/2025
Special inspection requirement — Exterior lighting power
Noel Tolentino
08/14/2025
Special inspection requirement — Lighting controls
Noel Tolentino
08/14/2025
Special inspection requirement — Structural Steel - Welding
Noel Tolentino
08/14/2025
Special inspection requirement — Final
Noel Tolentino
08/13/2025
Permit issued — Supported Scaffold
B08039333-I1-SF
08/13/2025
Permit issued — Construction Fence
B08039317-I1-FN
08/13/2025
Permit issued — General Construction
B00580204-I1-GC-CX
08/04/2025
Permit issued — Plumbing
B00580204-S1-PL
05/27/2025
Violation issued (ECB, open)
Construction
Latest 60 of 229 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedKel-Tech Construction09/22/2026
DOB NOWSidewalk ShedPermit IssuedMaric Mechanical05/11/2026
DOB NOWSidewalk ShedPermit IssuedMaric Mechanical03/26/2026
DOB NOWSidewalk ShedPermit IssuedMaric Mechanical03/26/2026
DOB NOWMechanical SystemsPermit IssuedMaric Mechanical03/26/2026
DOB NOWSidewalk ShedPermit IssuedKel-Tech Construction10/01/2025
DOB NOWSupported ScaffoldSigned-offBTF Construction08/13/2025
DOB NOWConstruction FenceSigned-offBTF Construction08/13/2025
DOB NOWGeneral ConstructionSigned-offBTF Construction08/13/2025
DOB NOWPlumbingSigned-offLatty's Gen Plumbing Cont08/04/2025
DOB NOWSupported ScaffoldPermit IssuedMaric Mechanical04/07/2025
DOB NOWMechanical SystemsPermit IssuedMaric Mechanical03/19/2025
DOB NOWSupported ScaffoldPermit IssuedMaric Mechanical03/19/2025
DOB NOWSidewalk ShedSigned-offBTF Construction03/13/2025
DOB NOWConstruction FenceSigned-offBTF Construction03/12/2025
DOB NOWConstruction FencePermit IssuedMaric Mechanical01/22/2025
DOB NOWMechanical SystemsPermit IssuedMaric Mechanical01/21/2025
DOB NOWConstruction FencePermit IssuedMaric Mechanical01/21/2025
DOB NOWSidewalk ShedPermit IssuedMaric Mechanical01/17/2025
DOB NOWGeneral ConstructionSigned-offBTF Construction12/31/2024
DOB NOWSupported ScaffoldSigned-offBTF Construction12/17/2024
DOB NOWPlumbingSigned-offLatty's Gen Plumbing Cont08/07/2024
DOB NOWPlumbingPermit IssuedI.M.P. Plumbing & Heating08/01/2024
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement07/24/2024
DOB NOWMechanical SystemsPermit IssuedEmpire Control Abatement07/24/2024
DOB NOWSupported ScaffoldPermit IssuedMaric Mechanical06/21/2024
DOB NOWSupported ScaffoldPermit IssuedMaric Mechanical04/09/2024
DOB NOWMechanical SystemsPermit IssuedMaric Mechanical04/09/2024
DOB NOWSidewalk ShedSigned-offBTF Construction01/25/2024
DOB NOWSupported ScaffoldSigned-offBTF Construction12/18/2023
DOB NOWStructuralSigned-offBTF Construction12/18/2023
DOB NOWConstruction FenceSigned-offBTF Construction12/13/2023
DOB NOWSidewalk ShedPermit IssuedMaric Mechanical04/05/2023
DOB NOWConstruction FencePermit IssuedMaric Mechanical04/05/2023
DOB NOWSidewalk ShedPermit IssuedMaric Mechanical04/05/2023
DOB NOWSupported ScaffoldPermit IssuedMaric Mechanical04/01/2023
DOB NOWMechanical SystemsPermit IssuedMaric Mechanical03/31/2023
DOB NOWStructuralSigned-offBTF Construction01/17/2023
DOB NOWSidewalk ShedSigned-offBTF Construction01/11/2023
DOB NOWSupported ScaffoldSigned-offBTF Construction01/09/2023
+ 60 more permits on file
1 project · most recent 11/15/2024
Water/Sanitary
FiledStatusContractorScope
11/15/2024Permit IssuedI.M.P. Plumbing & HeatingWater/Sanitary
20 projects · most recent 05/27/2026
General Wiring Lighting
FiledStatusContractorScope
05/27/2026CompleteGemini Electric Co—
02/25/2026Permit IssuedAce Electrical ConstructionGeneral Wiring
09/11/2025Permit IssuedStanco System Electrical Cont—
08/26/2025CompleteCharan Electrical Enterp's—
06/28/2024CompleteJames F. Volpe ElectricalGeneral Wiring
08/16/2023CompleteCharan Electrical Enterp's—
06/28/2023CompleteCharan Electrical Enterp's—
01/11/2023CompleteDynamo ElectricalGeneral Wiring
11/10/2022Permit IssuedTribeca Electrical—
09/22/2022Permit IssuedLCJ Electrical ContractorsGeneral Wiring
09/22/2022Permit IssuedLCJ Electrical Contractors—
03/08/2022CompleteCharan Electrical Enterp's—
10/05/2021CompleteStanco System Electrical Cont—
01/21/2020CancelledSamco Electric—
09/11/2019CompleteCharan Electrical Enterp's—
1 project · most recent 09/06/2023
Steel Concrete
FiledStatusContractorScope
09/06/2023——Steel, Concrete
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/27/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/20/2023Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 69
DateRequirementInspectorRole
03/17/2026Concrete - Cast-In-PlaceNoel Tolentinospecial
11/11/2025HVAC-R and service water piping design and insulationAsma Hashmienergy_progress
11/11/2025HVAC-R and service water heating equipmentAsma Hashmienergy_progress
11/11/2025Maintenance informationAsma Hashmienergy_progress
11/11/2025HVAC-R and service water heating system controlsAsma Hashmienergy_progress
10/14/2025Fire-Resistant Penetrations and JointsAsma Hashmispecial
10/14/2025Post-installed AnchorsAsma Hashmispecial
10/14/2025Energy Code Compliance InspectionsAsma Hashmiprogress
10/10/2025Mechanical SystemsAsma Hashmispecial
10/10/2025FinalAsma Hashmiprogress
08/14/2025MasonryNoel Tolentinospecial
08/14/2025Structural Steel - DetailsNoel Tolentinospecial
08/14/2025Lighting controlsNoel Tolentinoenergy_progress
08/14/2025FinalNoel Tolentinoprogress
08/14/2025Structural Steel - WeldingNoel Tolentinospecial
08/14/2025Structural Stability – Alterations of existing buildingsNoel Tolentinospecial
08/14/2025Post-installed AnchorsNoel Tolentinospecial
08/14/2025Exterior lighting powerNoel Tolentinoenergy_progress
03/14/2025Post-installed AnchorsNoel Tolentinospecial
03/10/2025Post-installed AnchorsNoel Tolentinospecial
11/19/2024Fire-Resistant Penetrations and JointsSTEPHEN LATUSspecial
11/14/2024Fire-Resistant Penetrations and JointsSTEPHEN LATUSspecial
11/14/2024Fire-Resistant Penetrations and JointsSTEPHEN LATUSspecial
11/14/2024HVAC-R and service water piping design and insulationCLOUD LEEenergy_progress
11/14/2024Energy Code Compliance InspectionsCLOUD LEEprogress
Latest 25 of 69.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Success Academy Charter School - WilliamsburgEducationEntire building
Project B01301101 Alteration · Approved · 11/11/2025
Project B01050351 Alteration · Permit Entire · 05/16/2024
Project B00929144 Alteration · Approved · 09/06/2023
Project B08039333 Alteration · LOC Issued · 11/23/2022
Project B08039317 Alteration · LOC Issued · 11/16/2022
Project B08039327 Alteration · LOC Issued · 11/16/2022
Project B08001662 Alteration · Permit Entire · 09/21/2022
Project B00580204 Alteration · LOC Issued · 08/20/2021
Project B00300241 Alteration · LOC Issued · 02/26/2020
J.H.S. 50KEducation—
Project B01267253 Alteration · Permit Entire · 08/19/2025
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 245 on file (BIS + DOB NOW)
▸Plans & Drawings32
▸DOB NOWPlans/Sketch31
08/28/2026B08039317-I1Request digital key ↗
08/27/2026B08039333-I1Request digital key ↗
08/25/2026B01050351-P3Request digital key ↗
Showing 3 of 31 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00300241-I1Request digital key ↗
▸Applications & Permits3
▸BISWORK PERMIT APPLICATION3
04/16/2025322053558Open ↗
02/21/2024322053558Open ↗
02/02/2023322053558Open ↗
▸Seals & Professional Certifications71
▸DOB NOWDPL-1: Design Professional Seal & Signature32
08/28/2026B08039317-P1Open ↗
08/28/2026B08039317-I1Open ↗
08/27/2026B08039327-P1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature23
09/24/2026B01050351-P1Open ↗
09/23/2026B01050351-P2Open ↗
09/23/2026B08001662-S1Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/24/2026B01050351-P1Open ↗
09/24/2026B01050351-P1Open ↗
09/01/2026B08001662-S2Open ↗
Showing 3 of 16 on file for this type
▸Safety & Tenant Protection13
▸DOB NOWNYCSCA - Approved Site Safety Plans13
08/13/2026B08001662-P5Open ↗
08/13/2026B08039317-P1Open ↗
08/13/2026B08039333-P1Open ↗
Showing 3 of 13 on file for this type
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/22/2026B08001662-S2Open ↗
08/18/2026B00580204-P2Open ↗
08/18/2026B00580204-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/25/2026B01050351-I1Open ↗
08/25/2026B01050351-S1Open ↗
08/25/2026B01050351-S2Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/15/2026B00580204-I1Open ↗
▸Approvals, Objections & Sign-offs74
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter32
08/18/2026B00580204-P2Open ↗
08/18/2026B00580204-S1Open ↗
08/18/2026B00580204-P3Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)32
08/13/2026B08039317-I1Open ↗
08/13/2026B00580204-I1Open ↗
08/13/2026B00580204-P1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)7
08/18/2026B00580204-S1Open ↗
08/15/2026B00580204-I1Open ↗
08/13/2026B01050351-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP Variance (V5) letter3
08/13/2026B01050351-S1Open ↗
08/13/2026B01050351-I1Open ↗
08/13/2026B01050351-S2Open ↗
▸Filing & Intake Forms3
▸DOB NOWAI1 Form2
08/18/2026B00580204-S1Open ↗
08/15/2026B00580204-I1Open ↗
▸BISBOROUGH INTAKE FORM1
02/02/2023322053558Open ↗
▸Other Documents37
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal33
08/15/2026B00580204-I1Open ↗
08/14/2026B00580204-P6Open ↗
08/13/2026B08001662-P3Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWNYCSCA Exhibit 24
08/18/2026B00580204-S1Open ↗
08/15/2026B00580204-I1Open ↗
08/13/2026B08039333-I1Open ↗
Showing 3 of 4 on file for this type