| Owner | Filings | Most Recent |
|---|---|---|
| St Clare of Assisi Church | 3 | 03/21/2026 |
| Nynex | 1 | 03/21/2026 |
| St Clares School | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Associates | 9 | 08/25/2025 |
| KZ Engineering | 1 | 08/27/2024 |
| PC Studio Architect | 3 | 04/06/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Poseidon Expediting & Consulting SE | 18 | 03/21/2026 |
| Milrose Consultants | 1 | 03/21/2026 |
| Municipal Building Consultants | 2 | 03/21/2026 |
| Synergy Building Consultants | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Pipe Rite | Plumbing | 3 | 07/08/2026 |
| The Metro Group | Scaffold | 3 | 03/21/2026 |
| Jakes Sheetrock | General Contractor | 2 | 03/21/2026 |
| Ace Chimney & Fireplace | General Contractor | 2 | 03/21/2026 |
| The Metro Group | General Contractor | 1 | 07/08/2026 |
| M.B.S. Electric | Electrical | 1 | 03/21/2026 |
| The Metro Group Electric | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Metrospec Sia | 6420 | 7 | 12/14/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | Pipe Rite | 06/11/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | The Metro Group | 08/27/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | The Metro Group | 08/02/2024 |
| DOB NOW | General Construction | Permit Issued | Ace Chimney Fireplace | 12/29/2021 |
| DOB NOW | Boiler Equipment | Signed-off | Michael S. Kaplan | 08/22/2021 |
| DOB NOW | Boiler Equipment | Permit Issued | Michael S. Kaplan | 08/19/2021 |
| DOB NOW | Plumbing | Permit Issued | Pipe Rite | 08/18/2021 |
| DOB NOW | General Construction | Signed-off | Jakes Sheetrock | 06/11/2021 |
| BIS | FS | ISSUED | East Coast Mechanical | 10/02/2019 |
| BIS | FS | ISSUED | East Coast Mechanical | 08/16/2019 |
| BIS | FP | ISSUED | Lund Fire Products Co | 05/28/2004 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2025 | Permit Issued | Pipe Rite | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2025 | Complete | The Metro Group Electric | General Wiring |
| 12/21/2020 | Permit Issued | Abilene Electric | — |
| 08/24/2020 | Complete | Mid City Electrical | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2024 | Permit Issued | The Metro Group | Scaffold |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/02/2025 | HVAC-R and service water heating system controls | Michael Risbergs | energy_progress |
| 05/02/2025 | HVAC-R and service water piping design and insulation | Michael Risbergs | energy_progress |
| 05/02/2025 | HVAC-R and service water heating equipment | Michael Risbergs | energy_progress |
| 05/02/2025 | Energy Code Compliance Inspections | Michael Risbergs | progress |
| 05/02/2025 | Maintenance information | Michael Risbergs | energy_progress |
| 10/02/2023 | Final | JOSEPH YOUNG | progress |
| 10/02/2023 | Mechanical Systems | JOSEPH YOUNG | special |
| 10/02/2023 | Fire-Resistant Penetrations and Joints | JOSEPH YOUNG | special |
| 08/03/2022 | Maintenance information | Michael Risbergs | energy_progress |
| 08/03/2022 | Heating Systems | Michael Risbergs | special |
| 05/20/2022 | Heating Systems | Michael Risbergs | special |
| 05/20/2022 | Maintenance information | Michael Risbergs | energy_progress |
| 02/18/2022 | Heating Systems | Michael Risbergs | special |
| 02/18/2022 | Maintenance information | Michael Risbergs | energy_progress |
| 09/03/2021 | HVAC-R and service water piping design and insulation | Michael Risbergs | energy_progress |
| 09/03/2021 | Energy Code Compliance Inspections | Michael Risbergs | progress |
| 09/03/2021 | Maintenance information | Michael Risbergs | energy_progress |
| 09/03/2021 | HVAC-R and service water heating equipment | Michael Risbergs | energy_progress |
| 09/03/2021 | HVAC-R and service water heating system controls | Michael Risbergs | energy_progress |
| 09/03/2021 | Heating Systems | Michael Risbergs | special |
| 09/03/2021 | Maintenance information | Michael Risbergs | energy_progress |
| 09/02/2021 | Masonry | Michael Risbergs | special |
| 09/02/2021 | Fire-Resistant Penetrations and Joints | Michael Risbergs | special |
| 08/03/2021 | Chimneys and vents | Michael Risbergs | special |
| 08/03/2021 | Final | Michael Risbergs | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| St. Clare of Assisi School | Education | Entire building | Project X01090662 Project X00942065 Project X00569419 Project X00553734 Project X00553755 Project X00479271 Project X00370758 |